IM-08-B HSE Wall Grinding For Finishing Work

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

LARSEN & TOUBRO LIMITED:: ECC DIVISION

BUILDINGS AND FACTORIES OPERATING COMPANY

Ref: IM 08 B Rev 00
HSE RISK ASSESSMENT

Cluster : Mumbai
Name of the Job Site: Godrej BKC project
Name of activity- Finishing of wall/column at height. Date: 21.11.2013
Additional Control
Possible Measures (If the list Residu
Hazard / Risk /
Sl Outcome Probability Severity is exhaustive, give al Action
Activity Environment Existing Control Measure Impact
No Rating Rating only a doc. Ref no of Risk / By
Aspect Level
the Safe Work Impact
Method)
01         
Errection Height work Fall of the  Only experience person Continuous
of mobile material should allow to work 4 4 H supervision. L Site Eng
scaffold
Proper platform should be
Fall of the person provided with handrail and
mid rail
Proper safety belt
should be used
02
Movement L
of mobile Fall of Proper housekeeping and 4 4 M
scaffold. scaffold or Injury to workmen removal of obstruction on
person path way of mobile scaffold.
Rotating part of the m/c 4 3 M P&M
Wall Electrocution should be sufficiently Continuous
finishing guarded. supervision. &
by using L
grinding Health problems The electrical connection Site Eng
and with RCCB.
chipping Electrocution
m/c in Access and egress should
be provided.
Flying Dust
Below area should be well
03 maintained.

Provision for anchoring the


Full body Harness.

Proper use of ppe (nose


mask)
Locking arrangement of
scaffold.

________________
PM / CM / Section Head EHSO

P&M In- Charge: _______________________

Site Engineer: - ________________________