HSE RISK ASSESSMENT
Cluster : Mumbai
Name of the Job Site: Godrej BKC project
Name of activity- Finishing of wall/column at height. Date: 21.11.2013
Additional Control
Possible Measures (If the list Residu
Hazard / Risk /
Sl Outcome Probability Severity is exhaustive, give al Action
Activity Environment Existing Control Measure Impact
No Rating Rating only a doc. Ref no of Risk / By
Aspect Level
the Safe Work Impact
Method)
01
Errection Height work Fall of the Only experience person Continuous
of mobile material should allow to work 4 4 H supervision. L Site Eng
scaffold
Proper platform should be
Fall of the person provided with handrail and
mid rail
Proper safety belt
should be used
02
Movement L
of mobile Fall of Proper housekeeping and 4 4 M
scaffold. scaffold or Injury to workmen removal of obstruction on
person path way of mobile scaffold.
Rotating part of the m/c 4 3 M P&M
Wall Electrocution should be sufficiently Continuous
finishing guarded. supervision. &
by using L
grinding Health problems The electrical connection Site Eng
and with RCCB.
chipping Electrocution
m/c in Access and egress should
be provided.
Flying Dust
Below area should be well
03 maintained.
________________
PM / CM / Section Head EHSO