Tender Documents
for
Engineering, Procuring, Constructing, Testing &
Commissioning (EPC) of 50 MLD Water treatment Plant
at Nimeta, Vadodara along with
Operation and Maintenance for Five (5) years
(3) Last date of On-line Tender Submission : 20.11-2019 Upto 16.00 hours
Last date of submission of Tender Fees,
(4) EMD, Tender & other documents (Hard : 22-11-2019 up to 17.00 hours
copy)
(5) Date of Tender (Technical Bid) Opening : 20-11-2019 at 17.00 hours
OCTOBER - 2019
Vadodara Municipal Corporation 50 MLD WTP Nimeta
INDEX
Sr.
Particulars
No.
1.0 Form of Technical Proposal
3.0 Schedule-I to V
Name of Contract:
Contract No:
To:
Executive Engineer (Water supply Project),
Vadodara Municipal Corporation,
Khanderao Market Building,
Raj Mahal Road, Vadodara-390209.
Gujarat, INDIA.
Sir,
We further undertake, if invited to do so by you, and at our own cost, to attend a clarification
meeting at a place of your choice, for the purpose of reviewing our Technical Proposal and
duly noting all amendments and additions thereto, and noting omissions therefrom that you
may require, and to submit a supplementary price proposal if the amendments, additions and
omissions that you require would alter our price proposal as submitted with our bid.
We are,
Yours faithfully
Address
___________________________________________
___________________________________________
___________________________________________
___________________________________________
Phone :
Fax :
Email :
Period for O & M Contract Five years from the date of issue of certificate
for completion / taking over certificate
Arbitration rules
Time for access to the Site Within 15 days from the date of Letter of
Work Order Acceptance / Letter of Intent
SCHEDULES
CONTENTS
Sr. Particulars
No.
1.0 Schedule - I : Deviation from Technical Specifications
2.0 Schedule - II : Deviations from Conditions of Contract
3.0 Schedule - III : Work Schedule
4.0 Schedule - IV : Sub-Contractors
5.0 Schedule – V : Project Execution Plan
SCHEDULE - I
All deviations from Technical Specifications shall be filled in by the Bidder clause by clause
in this Schedule. If deviations are discussed in the covering letter, then reference to the letter
shall be made below:
The bidder hereby certifies that the above mentioned are the only deviations from Technical
Specifications of the Bid.
SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
COMPANY SEAL
SCHEDULE - II
All deviations from the Conditions of Contract (Part I - General Conditions and Part II -
Conditions of Particular Application) shall be filled in by the Bidder clause by clause in this
Schedule. If deviations are discussed in the covering letter, then reference to the letter shall
be made below:
The Bidder hereby certifies that the above mentioned are the only deviations from the
Conditions of Contract.
SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
COMPANY SEAL
SCHEDULE - III
WORK SCHEDULE
The Bidder shall submit the following after award of work in sufficient details (Separate
Sheets) for evaluation ensuring to execute it within the Time of Completion.
1.1 This shall consist of a detailed bar chart showing in sufficient details completion of
various sections of Work and the date and order in which the Bidder proposes to carry
out different parts of the Works. The bar chart shall indicate the principal quantities of
work forecast for execution monthly and payments expected to be made in connection
therewith. In preparation of the programme, appropriate allowance should be made
for loss of time due to inclement weather. This construction schedule shall form the
basis for preparation of detailed CPM schedule to be furnished after the award of the
Contract.
The Bidder shall keep above in view while preparing his Work Schedule.
SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
COMPANY SEAL
SCHEDULE - IV
SUB CONTRACTORS
The bidder shall enter in this Schedule, a list of the sections and appropriate value of the work
for which he proposes to use sub-contractors, together with the names and addresses of the
proposed subcontractors. The bidder shall also enter a statement of similar works previously
executed by the proposed subcontractors, including description, location and value of work,
year completed, and name and address of the Employer/Engineer. Notwithstanding such
information the bidder, if awarded the Contract, shall remain entirely and solely responsible
for the satisfactory completion of the Works.
SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
COMPANY SEAL
SCHEDULE V
The Bidder is required to furnish Project Execution Plan (PEP) in the following format after
award of work. A brief but clear PEP is required for describing planning and programming
of the works.
e) Project Safety Plan: Provide a statement outlining the Health and Safety Plan
operated by the company.
f) Contractor shall indicate any permanently established groups within the organisation
which would provide specific functions in the execution of the contract.
Signature
Name
Designation
Company
Date
2. FLASH MIXER
No. of Units
Design Flow (M3/Hr.)
Detention Time at Design flow (min.)
MOC
Size (M x M)
Liquid depth
Free board
Drain Valve Size (mm)
Design F.S.L., m
3. CLARIFLOCCULATOR
Nos.
Flow through each clariflocculator
Detention time in Flocculator
GT Value of mechanical
Service factor for gear box
Surface loading in clarifier zone
Detention time in clarification zone
Liquid depth
Size of Clariflocculator
Free board
Floor slope
Weir loading
Outlet arrangement of the clarified water
Clarifier bridge width
Wheel Assembly
Peripheral speed of Scrapper Arm
Thickness of scrapper blade
MOC of Bridge & Scrapper & Flocculator
Inside finish
Outside finish
Platform
14. THICKENER
No. of thickener
Type of thickener
Inlet solids Kg./day
Inlet sludge solids concentration (%)
Outlet sludge solids concentration (%)
Specific gravity of Sludge
Solid loading rate kg/m2/day
Hydraulic loading rate kg/m3/day
Size of each unit
Liquid depth
Bottom slope
Free board
Material of Construction
18. CENTRIFUGE
Capacity (m3/hr)
Type
Quantity (Working + Standby)
Material of Construction
Bowl
SR. PARTICULARS TO BE
DESCRIPTION
NO FILLED BY BIDDER
A HT PANEL BOARD
1 General
a Manufacturer/ Type
b Bus Bar
Material (Al/Cu)
Continuous rating, A
c Short time (one second) withstand rating KA (rms)
d Clearances
Between phase, mm
Between live part and earth, mm
One minute power frequency withstand voltage KV
e
(rms)
f Thickness of steel sheey
Frame, mm
Door, mm
Cover, mm
g Dimensions of cubicle (mm)
Draw out space required in front (mm)
Weight of heaviest cubicle (Kg)
2 Circuit Breaker
a Manufacturer/ Type
b Rated voltage, V
c Rated current for various circuit breakers
Normal, A
De-rating factor for site conditions, A
When installed within cubicles, A
d Method of closing
Normal
Emergency
e Type of closing mechanism
f Normal ratting of closing mechanism (V/W)
g Type of tripping mechanism
h Normal rate of tripping mechanism (V/W) :
i Spring changing motor details
Output rating (KW)
Rated voltage (V)
3 FUSES (FOR PT’S)
a Manufacturer
b Type
c Rated Voltage, V
d Rated Current, A
e Category of duty
f Rupturing capacity (prospective current), KA
Alum Kg/Day
Kg/MLD
The guaranteed power requirement for each month or for duration as per duration /
billing cycle of power Supply Company shall be calculated based on daily power
requirement guaranteed by bidder as above for the calculation of Liquidated Damages for
failing O&M performance guarantees.
Total
Motor Input,
Motor Pump KWH for
Sl. Name of KW = Pump
Wkg S/B Total Rating, Input, Running Hours Daily
No. Unit Input KW /
KW KW Consumpti
Mot. Eff.
on
Each
Total
Unit/ Day
6= 8=
1 2 3 4 5 7 9=6*8
5 / Mot. Eff. 1*7