Fundamentals of Construction Project Management
Fundamentals of Construction Project Management
Figure 1.1.
1.1 INTRODUCTION
Construction and the ability to build things is one of the most ancient of
human skills.
Once a project has been defined, one of the most critical questions facing Figure 1.1 is shown as an equilateral triangle to represent an important
the construction manager is ‘‘What construction technique or method principle of project management: a balance is necessary between the scope,
should be selected?’’ The types of methods for placing construction are budget, and schedule.
diverse. New methods are continuously being perfected and a construction For any given project there is a certain amount of work that must be
manager must weigh the advantages and disadvantages of a given method performed and an associated cost and schedule for producing the work.
or technique.
Any adjustment in budget and/or schedule requires a corresponding
adjustment in scope.
DEFINITION OF PROJECT
This simple concept of a balance between scope, budget, and schedule is
• an endeavor that is undertaken to produce the results that are sometimes not fully recognized during early project development as well as
expected from the requesting party during design and construction.
• may be design only, construction only, or a combination of design WHY??? The source of many problems associated with a project is failure to
and construction properly de- fine the project scope. Too often the focus is just on budget or
schedule. Not only should the scope, budget, and schedule be well defined,
• consists of three components: scope, budget, and schedule but each must be linked together since one affects the other, both
individually and collectively.
When a project is first assigned to a project manager, it is important that all
three of these components be clearly defined. Throughout this book, the • The manager must be clever and innovative in the utilization of
term Scope represents the work to be accomplished, i.e., the quantity and resources available. Somewhat like a general in battle, the manager
quality of work. Budget refers to costs, measured in dollars and/or labor- must develop a plan of action and then direct and control forces
hours of work. Schedule refers to the logical sequencing and timing of the (resources) in a coordinated and timely fashion so that the
work to be performed. The quality of a project must meet the owner's objective is achieved.
Since the project scope defines the work to be accomplished, it should be MANAGEMENT CONCEPTS
the first task in the development of a project, prior to the development of
either the budget or the schedule. Too often, top management specifies a
project budget or schedule and then asks the project team to define a scope
to match the budget. This is the reverse order of defining a project and is
not a good project management practice. 'It is the duty of a project manager
to ensure that the project scope, budget, and schedule are linked together.
Construction project managers shoulder the responsibility of keeping the This type of management approach was the first to directly link orderly
project moving according to plan. The goal is to manage the project so that operations, human resource management, and communication to
it finishes on schedule and within budget, while still meeting building codes, organizational success.
plans, and specs.
The scientific management approach developed by Taylor is based on the
concept of planning of work to achieve efficiency, standardization,
specialization, and simplification. Acknowledging that the approach to
increased productivity was through mutual trust between management and
workers, Taylor suggested that, to increase this level of trust, the advantages
of productivity improvement should go to workers, physical stress and
anxiety should be eliminated as much as possible, capabilities of workers
should be developed through training, and the traditional ‘boss’ concept MANAGEMENT LEVELS OF CONSTRUCTION
should be eliminated.
Organizational considerations lead to a number of hierarchical levels that
Taylor developed the following four principles of scientific management for can be identified in construction. This derives from the project format.
improving productivity: Decision making at levels above the project relate to company management
considerations. Decisions within the project relate to operational
• Science, not rule-of-thumb. Old rules-of-thumb should be considerations (e.g., selection of production methods) as well as the
supplanted by a scientific approach to each element of a person’s application of resources to the various construction production processes
work. and work tasks selected to realize the constructed facility. Specifically, four
• Scientific selection of the worker. Organizational members should levels of hierarchy can be identified as follows:
be selected based on some analysis, and then trained, taught and Organizational. The organizational level is concerned with the legal and
developed. business structure of a firm, the various functional areas of management,
• Management and labour cooperation rather than and the interaction between head office and field managers performing
conflict. Management should collaborate with all organizational these management functions.
members so that all work can be done in conformity with the Project. Project-level vocabulary is dominated by terms relating to the
scientific principles developed. breakdown of the project for the purpose of time and cost control (e.g., the
• Scientific training of the worker. Workers should be trained by project activity and the project cost account). Also, the concept of resources
experts, using scientific methods. is defined and related to the activity as either an added descriptive attribute
of the activity or for resource scheduling purposes.
Humanistic management is an approach to management theory based on
the idea of human needs and human values. Employees are seen not merely Operation (and Process). The construction operation and process level is
concerned with the technology and details of how construction is
as economic assets valued primarily for their productivity but as people with
complex needs and a desire for meaningful and varied daily tasks. performed. It focuses on work at the field level. Usually, a construction
operation is so complex that it encompasses several distinct processes, each
Humanistic management is a people-oriented management that seeks having its own technology and work task sequences. However, for simple
profits for human ends. It contrasts with other types of management that situations involving a single process, the terms are synonymous.
are essentially oriented toward profits, with people seen as mere resources
to serve this goal. Task. The task level is concerned with the identification and assignment of
elemental portions of work to field units and work crews.
As the name implies, construction technology relates to the methods or
techniques used to place the physical materials and elements of
construction at the job site. In contrast to construction technology,
construction management addresses how the resources available to the
manager can be best applied. Typically, when speaking of resources for
construction, we think of the FIRST four M’s of construction: manpower,
machines, materials, and money. Management involves the timely and
efficient application of the four M’s to construct a project. The types of
methods for placing construction are diverse. New methods are
continuously being perfected and a construction manager must weigh the
advantages and disadvantages of a given method or technique. Hence, the
5th M is the method.
STRUCTURE OF ORGANIZATION
1. Construction technology
2. Construction management
1.2 PROJECT MANAGEMENT CONCEPT Designer
12. Build the project staff into an effective team that works
together as a unit
1.3 CONTRACTS AND SPECIFICATIONS o The definition of the scope, i.e. what exactly has to be
done, and what happens if the changes are required or
WHAT IS CONTRACT MANAGEMENT?
desired along the way;
Contract Management could be defined as a multi-stage process that goes
o When the works have to be concluded and what happens
on through the entire duration of the contract and ensures that the parties
if they are concluded on time;
meet their contractual obligations in order to deliver the specific objectives
provided in the contract. o When payments are due and what happens if they are not
paid on time;
From a legal point of view, contract is A mutual agreement between two or
more parties that something shall be done, an agreement enforceable at o Technical specifications and quality and performance
law. requirements and what happens if the agreed standards
are not met
According to Fédération Internationale Des Ingénieurs – Conseils (from
French, the International Federation of Consulting Engineers) or FIDIC, A
contract means the General Conditions, the Supplementary Conditions, the
TYPES OF CONSTRUCTION CONTRACT
Specifications, the Drawings, the Bill of Quantities, the Tender, the Letter of
Acceptance and the Contract Agreement.
Contract conditions, usually included in the book of specifications (or in the 2.1 INTRODUCTION
accompanying architectural drawings) of a contract, that set the minimum
Construction project management requires a broad variety of skills, along
performance requirements for the contractor. These conditions also include
with the ability to interface with a diverse range of agencies and people in
the rights and responsibilities of the parties involved
order to lead the project from concept to build. It’s important that
Contract conditions set out the principal legal relationship between the construction project managers follow the principles of project management
parties to a construction project, determining the allocation of risk and during every phase of the project.
consequently, price.
CONCEIVING AND INITIATING THE PROJECT
Specifications is the part of the Contract that consists of written
You can’t start a project unless you know you’ll be able to finish it. First
requirements for materials, equipment, systems, standards, and
comes the due diligence to determine if the project is even feasible. How do
workmanship as applied to the Work, and certain administrative
you figure this out? You want to go through a feasibility study or what is
requirements and procedural matters applicable to the Work.
often called a business case, in which you look at the goals, cost and timeline
to see if you have resources to reach a successful project end within those
constraints. You also want to define the reasoning behind the project and
make sure it’s sound. If so, then you create your project charter to help
initiate the project. You’ll also identify potential issues and risks in this
phase.
You have approval, now how are you going to achieve success? Outline the
tasks within the timeline, noting project milestones, and the resources
needed to do those tasks within the budget allotted. Be transparent in your
plan, so everyone is on the same page and understands what needs to be
done over the life cycle of the project. That includes detailing the cost,
scope, duration, quality and communications used in the project. This is also
when you’ll be able to conceptualize the best team for the project and begin
the process of assembling them.
Now you’re executing the project, taking the plan and implementing it,
along with all the changes and issues that can arise during such a process.
Whatever deliverables you promised must come through in the timeframe 2.2 PROJECT INIATION
you noted. Now you must deal with stakeholders and customers and teams.
Planning is the formulation of a course of action to guide a project to
The latter have tasks must be completed, which means workload
completion. It starts at the beginning of a project, with the scope of work,
management and resource allocation. You’ll be setting up meetings and
and continues throughout the life of a project. The establishment of
reporting frequently throughout this stage. This is where your project
milestones and consideration of possible constraints are major parts of
management tool will really be tested, but more on that later.
planning. Successful project planning is best.
TRACK PROJECT PERFORMANCE
accomplished by the participation of all parties involved in a project. There
You can’t know the progress of your project if you don’t have a way to must be an explicit operational plan to guide the entire project throughout
monitor it. You’ll be doing this during the previous stages of the project, but its life.
it’s important enough to demand its own separate stage in your
Since the construction sector is so diverse, it is helpful to look at the major
management. You’ll want to have a way to note the progress, which is why
types of projects typical of construction to understand the structure of the
you need to set up key performance indicators for cost, time and quality. If
industry. Construction projects can be broadly classified as (a) building
you can stay on top of these figures, it’s less likely you’ll manage a failing
construction, (b) infrastructure construction, and (c) industrial construction,
project. Therefore, stay flexible and communicative throughout so you can
depending on whether they are associated with housing, public works, or
adapt quickly to change when it occurs, and it always occurs.
manufacturing processes.
Management is often summarized into four basic functions: planning,
organizing, directing, and controlling. Although these basic management
functions have been developed and used by managers of businesses, they
apply equally to the management of a project.
CONTRACT ARRANGEMENTS of construction, and has sufficient time to permit the design to be fully
completed before construction bids are obtained. This method is often used
There are different procurement systems and several ways of classifying
for very large, complex projects. Since the design is fully developed, an
them. On the basis of how the interaction between design and construction,
“apples to apples” comparison of multiple bids can be made.
how funding and operations are managed, mode of reimbursement of the
contractor, level of information available or required before a construction The primary disadvantage of the Design/Bid/Build process is the Architect’s
contract, and the magnitude of risk taken by participating parties. To deliver limited ability to establish an accurate cost estimate; consequently, the
a quality construction project on time and on budget, you must successfully Owner may not know the cost of his project until the bids are received. If
coordinate the efforts of the Owner, Architect and General Contractor in an the bids are higher than the budget, costly redesign is often required. Other
accepted and appropriate contract form. There are three basic project disadvantages include:
delivery methods: Design/Bid/Build, Construction Management, and
o Owner is responsible for the completeness and accuracy
Design/Build. Each method has its own advantages and disadvantages, and
of the Architect drawings
some methods are better suited for certain kinds of projects than others.
o Contractor has no input regarding more cost-efficient
materials or construction methods
Design/Build
The two primary disadvantages to the Design/Build method are: o Owner is provided advice on budget, schedule, and
constructability during design phase
• The Owner does not receive the benefit of the system of “checks
and balances” that exist when it contracts separately with an o CMAR can provide value-engineering advice to save client
Architect and a Contractor time and money
• It is difficult for the Owner to verify that the best price has been
o CMAR is responsible for schedule and budget
achieved for the work
o CMAR typically provides a Guaranteed Maximum Price
(GMP)
Disadvantages:
One variation of the Design/Bid/Build method is to secure the services of a o Construction costs may run over if design mistakes are not
Construction Manager. A Construction Manager At-Risk may be used detected early
instead of bidding the project to General Contractors. An Agency
o Involves negotiation of two separate contracts and
Construction Manager acts as an advisor to the client. It is important to
requires careful contract language establishing
understand the “risk shift” inherent in these two Construction Management
responsibilities of each party
methods.
The delivery method referred to as Construction Manager – Agency or CM
The most common form of Construction Management is CM At-Risk, where
(Agency) is a fee-based service in which the CM (Agency) acts as the Owner’s
an independent professional reduces the risk to the Owner because a
representative during each stage of the project. The CM (Agency) is the
Construction Manager At-Risk (CMAR) holds the subcontract agreements.
Owner’s trusted construction expert who advises the Owner and acts as a
“go to” person for all aspects of the project including design,
constructability, value-engineering, scheduling, negotiations with Architect industry. Construction projects can be broadly classified as (a) building
and Contractors, and qualification of design professionals, Contractors, and construction, (b) engineered construction, and (c) industrial construction,
subcontractors. It is important to note that the CM (Agency) is an advisor depending on whether they are associated with housing, public works, or
but is not accountable for schedule and budget and that the Owner enters manufacturing processes.
into the trade contracts, not the CM (Agency). Depending on how the
contract is structured, the CM (Agency) may be compensated for some
general condition items. This agreement places the majority of the risk CONTRACT DEVELOPMENT
during construction on the shoulders of the Owner.
People often associate engineering with the invention and construction of
infrastructure such as industrial plants, roads and bridges, but there is more
than meets the eye when it comes to this profession. Of the many fields of
study, Detailed Engineering Design is perhaps one that needs more
exploration.
During development of a project the client normally looks for construction Estimates are used for a number of different purposes in construction:
cost estimates. It is advisable to provide a probable cost of construction at
completion of the schematic design, design development, and construction • Determining the feasibility of a project
document phases. A design contingency is usually carried in cost estimates. • Calculating an approximate price of a project
It can be reduced as the documents are further developed. At completion • Providing value analysis
of the construction documents, the architect prepares, or has a consultant • Calculating & establishing bid prices
prepare, a final and most accurate estimate of construction cost, which can • Determining project budgets in cost control
be used for comparison with the bids submitted to perform the work.
TYPES OF ESTIMATES
Value engineering may be performed by consultants and construction
• Detailed Estimates
managers during the development of the construction documents. Value
• Square-Foot Estimates
engineering should address operating and maintenance costs as well as first
• Parametric Estimates
costs, to provide true life-cycle cost estimates for comparative analysis.
• Project Comparison Estimates
Value engineering is a systematic method to improve the “value” of a
Detailed Estimates
product or service that the project produces. It is an integral component of
project quality. • Determination of the quantities and costs of everything that is
required to complete the project.
• This includes materials, labor, equipment, insurance, bonds and
WHAT IS ESTIMATING? overhead, as well as an estimate of the profit.
• To perform this type of estimate, the contractor must have a
Estimation (or estimating) is the process of finding an estimate, or
complete set of contract documents.
approximation, which is a value that is usable for some purpose even if input
data may be incomplete, uncertain, or unstable. Square Foot/Approximate Estimates
• In construction, it is an approximation of cost of a project to the • Prepared by multiplying square footage of a building by a cost per
contractor. square foot and then adjusting the price to compensate for
• A process of calculating costs of a construction project based on a differences in the building heights, length of the building
design proposal and using comparisons with similar projects to perimeter, and other building components.
establish budgets prior to final pricing.
Parametric Estimates
ROLE OF AN ESTIMATOR
The Quantity Take-Off Rules of Measurement: All excavation is measured net with no allowance
for increasing in bulk after excavation or for the extra space required for
o Refers to the scaling or transferring of critical dimensions
working space or to accommodate earthwork support.
of construction components from drawings to paper or
software that are quantified as units of measurement. o Disposal
o This also includes a description of works that are - It is defined as the action or process of throwing away or getting rid of
influenced by the appropriate measurement guide. something.
Organization Of Quantity Take-Off Rules of Measurement: Disposal is based on all excavated material off site
and measured in terms of volume, m3
o The order of the take-off will generally follow the
sequence of work activities of the project and, o Fillings
conveniently for the estimator, the contract drawings are
- It is defined as a quantity of material that fills or is used to fill something.
usually presented in this sequence.
Rules of Measurement: Filling is obtained from excavated material which
Methods of Measurement
includes topsoil and any other material arising from the excavations that
o Principles of Measurement – International (POMI) have been specified to remain on site and measured in terms of volume, m 3.
Measuring Items of Works in Building Projects Rules of Measurement: Concrete volume is measured net. Deductions are
not made for the reinforcement, steel sections and voids smaller than 0.05
• Excavating and Filing
m3 (except voids in troughed and coffered slabs)
o Site clearance/preparation
o Formwork
- It is the removal of natural obstruction across the site such as grass,
- It is a temporary construction to contain wet concrete in the required
bushes, shrubs and trees.
shape while it is cast and setting.
Rules of Measurement: Site preparation is measured in terms of area, m2.
- This can be made of steel, wood, aluminum and/or prefabricated forms.
o Excavations
Rules of Measurement: It is measured to the faces of all cast in place C. Anchorage & Lap Splice Length
concrete which requires to be supported while the concrete sets. No
deductions shall be made for voids smaller than 5.00 m2. • Lap length is the length of bar overlap when bars are tied together
for extending the reinforcement length.
o Reinforcement • Anchorage length is the additional length of steel required to be
inserted from one structural member into another structural
A. Types of Steel Bar
member at the junction.
• Mild steel bars are plain in surface and are round sections of
diameter from 6 to 50mm.
• High yield steel bars are rods of steels provided with lugs, ribs or
deformation on the surface of the bar, these bars minimize
slippage in concrete and increases the bond between the two
materials.
Rules of Measurement:
• These are very significant especially when measuring links or • Computation for length of outer stirrups / links:
reinforcement that is bent up or bent around another bar. These
S = 2 x (w + d) – 8 x cc + hook
are usually given as multiples of bar diameter or given as specific
lengths in tabulated form. where:
Rules of Measurement: s = stirrup / link
1. Make sure to read the specifications or general notes and checked w = width of beam
all notes on plans you will be using and all other relevant
documents. d = depth of beam
2. Study carefully the drawings and details given. Make sure that you
cc = concrete cover
understand clearly the details given.
3. Check if there is enough information given to be able to measure hook = specified length or as multiples of stirrup diameter
lengths. Be sure to check specifications and general notes.
4. Tick off or loop through bar marks measured to check if all • Computation for the number of outer stirrups / links:
reinforcement for the particular element has already been taken or N = (L – 2 x cover from face of support) / spacing + 1
measured.
5. If there are any uncertainties in the details, make a query on this. where:
6. Check for any assumptions made to be put in measurement notes.
N = number of stirrups / links
7. Unit weight of rebar per meter is calculated by the surface area of
steel multiply by the density of steel. Thus, kg/m = (π D2/4) x 7850 L = clear length
kg/m3 or simply kg/m = D x D x 6165 kg/m3
G. Measurement of Slab Reinforcement
E. Measurement of Beam Reinforcement
There are two general types of slabs with regards to its load carrying
• Typically, reinforcement to ordinary beams will comprise of top bar capacity:
reinforcement, bottom bar reinforcement, links or stirrups and side
bars. • One-way slab – slab supported by beam / wall support (parallel to
• End conditions for beams are usually given with anchorage length, the long span) and whose reinforcement runs in one direction only,
either given lengths in tabulated form or given as multiples of bar i.e. from support to support.
diameter. S/L < 0.50 : S = SHORT SPAN, L = LONG SPAN
• Pay particular attention where anchorage length is measured from,
which is usually from the inner face of support or from the
centerline of support.
• Two-way slab – slabs which are supported on four sides and are I. Measurement of Wall Reinforcement
reinforced in two directions. Reinforcement is placed in such a way
• Reinforcement to walls comprised primarily of horizontal bars and
to transmit loads to the four supporting beams.
vertical bars. For thicker walls, links or binders may be provided.
S/L > 0.50 : S = SHORT SPAN, L = LONG SPAN • Measurement of reinforcement will still be generally the same as
the column.
Rules of Measurement:
• Adjustment to wall reinforcement due to openings in walls:
1. Always check if distribution bars have been provided, especially for
- Always check from elevation or from framing plans for locations
top bars. Unless top bars are continuous from support to support,
of wall openings like openings for doors, windows, etc. and make
there will always be distribution bars to main top bars.
sure that all necessary adjustments are made.
2. Pay careful attention that spacing for bars are not interchanged
between the two directions. - When measuring walls with openings, treat walls as if there is no
3. Pay attention for slabs that have drops in them. Extra details may openings in it, and later make the adjustments.
be provided or adjustments are to be made.
- Adjustment to opening in walls can be dealt with similarly to
H. Measurement of Column Reinforcement adjustment for slabs with voids or openings.
Basically, column reinforcement is made up of vertical bars and links. J. Measurement of Stair Reinforcement
• Computation for vertical bars: • Reinforcement to stair comprised primarily of the main bars,
secondary bars, nosing and chairs (as required).
When measuring vertical bars, always check the end conditions of the bars
• Measurement of reinforcement to stair stringer and stair landing is
and check for location of laps / anchorage lengths. Floor to floor height must
similar to the one way slab.
be verified from the framing plans, especially at termination points.
• Computation for the length of nosing bar and chair bar:
• Computation for links in column:
Nb = w – 2 x cc
Length of links – can be computed in similar way as the links / stirrups in
Cb = t + r – 2 x cc + 2 x AL
beam
where
Number of links - There are two (2) conditions to consider when computing
for number of links: Nb = nosing bar
1. when links are to be provided at clear height only w = width of stair
2. when links are provided at entire floor height including at
intersections with other members cc = concrete cover
AL = anchorage length
• Doors and Frames
Cb = chair bar - Doors and door frames shall be enumerated stating their size and
type of material.
t = stair tread
• Windows
r = stair riser
- To measure this work, individual windows shall be enumerated
• Computation for the number of nosing bar and chair bar:
and fully described together with the rough opening sizes for the
Nosing bar = as per number steps units.
• Finishing And Miscellaneous Works - The miscellaneous metals trade has a wide scope that in very
o Finishes general terms can be defined as metal items that are neither part
of the structural steel work nor part of any other trade section.
- Work shall be measured flat without addition for laps or Some of the common items contained in this section and their
seams. Internal and external work shall each be so described. measuring methods are as follows:
Rules of Measurement: 1. Measure miscellaneous angles and channels in linear feet or
meters, stating the size and location of the items.
1. Finishing shall be measured by area, classified as follows:
2. Measure in square feet or square meters and fully describe grates,
o Floors, which shall include landings
grilles, grillwork and louvers that are not part of the mechanical
o Walls, which shall include returns, reveals of openings or
system. Measure frames for this works in linear feet or meters,
recesses and attached and unattached columns
stating size and type of section.
o Ceilings, which shall include attached and unattached
3. Measure in linear feet or meters and fully describe metal handrails,
beams and soffits of staircases.
railings and balusters.
o Staircases, which shall include treads, risers and edges of
4. Enumerate and fully describe ladder rungs.
landings but exclude soffits.
5. Enumerate and fully describe metal corner guards.
2. Skirtings, coverings to kerbs, or the like shall be measured by length
3. Suspended ceilings shall be measured by area, classified as follows:
The specialties trade is another wide-ranging trade section of the Finish hardware includes the following items that shall be enumerated and
specifications that includes items of work as the following: fully described:
Most unit prices used to price materials are based on quotations from the
• Thermal and Moisture Protection suppliers of these materials, seldom are the unit prices used in the estimate
obtained directly from the suppliers. Even where suppliers do quote prices
Rules of Measurement:
for the same unit of measurement as the estimate, like concrete, the
1. Work shall be measured flat without addition for laps or seams. suppliers’ prices need to be adjusted to account for wastage of materials.
2. Coverings & linings:
When pricing any materials, there are a number of questions that should
Unless otherwise stated, roofing, tanking, waterproof coverings, linings or be answered before the prices are used in an estimate:
the like shall be measured by area, classified as follows:
• Do the materials offered by the supplier comply with the worker working for one hour. Determining the labor hours requires knowing
specifications? the quantity of work to be placed and the productivity rate for the specific
crew that will perform the work. The productivity rate is often expressed as
• Do the prices quoted include delivery of the materials to the site? a number of labor hours per unit of work, although it may also be expressed
• Can the contractor rely on the supplier’s prices to remain firm until as the quantity of work performed by a crew during a standard eight-hour
the owner awards the contract? day.
• Does the supplier’s price include state or city sales taxes? The productivity rates can come from a number of sources, but the most
reliable source is historical data. General formula is expressed as:
• The hourly wage rate of labor or hourly cost of equipment • When the conditions increase the speed at which the work
progresses, a productivity factor less than one is used, thus
• The productivity of the labor or equipment decreasing the number of labor hours to complete a unit of work.
Estimating labor requires determining the number of labor hours to do a • Availability and productivity of workers
specific task and then applying a wage rate. A labor hour is defined as one
o When there is plenty of work available and workers are Pricing Indirect Items
scarce, less trained craft persons are accepted. These less-
Indirect Items
trained persons will require more time or labor hours to
complete the required task, and a productivity factor o Overhead And Supervision
greater than one is used.
o SSS / ECC / MC / VL / SL
o Conversely, when construction projects are scarce,
workers may become motivated, and the contractor can o Bond Premium
be selective and hire only the most qualified workers. This
o Contingencies And Miscellaneous
will result in producing more work per labor hour, and a
productivity factor less than one is used. o Contractor’s Tax
- cold, hot, winds, rain, snow and combinations of these all affect the – to be computed on the estimated manpower requirement as prescribed
amount of work that can be produced in an hour. Typically, any weather in the contract conditions
extremes will slow down the work pace and may require additional
Bond Premium
precautions that add labor hours to the project.
(i.e., the given Bid Amount is PHP 5,000,000.00)
• Working conditions
o Bid bond (based on surety bond)
- the job site working conditions can have a great effect on the rate of
work. A project being built in the city with little working space, limited ▪ Bid bond = 10% x PHP 5,000,000.00 = PHP
storage space and difficult delivery situations typically has less work 500,000.00
accomplished per labor hour just due to the difficulty of managing the
resources. o Contractor’s All Risk
To price labor, first the estimator must estimate the labor hours required to ▪ Bid amount x 3% = amount of premium
do the work. These labor hours can then be multiplied by the hourly wage ▪ Php 5,000,000.00 x 0.003 = PHP 15,000.00
rate to develop the labor costs.
o Performance bond (20% of Bid Amount)
Labor cost = Adjusted Labor Hours x Hourly Wage Rate
▪ 20% x PHP 5,000,000.00 = PHP 1,000,000.00