VSM Basics For Capacity

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

Value Stream Mapping

for Capacity Planning and


Verification

Ford Production System 1


Key Elements of Value Stream Map
• Process Flow
• Material Flow
• Information Flow
• Process Metrics Data
• Customer Requirements
• In-Process Inventory (WIP)
• Lead Times for Each Process Step

Value Stream Mapping is a visual means of outlining the limiting factors of


a manufacturing operation, highlighting the restrictions, bottlenecks and
contributors to inefficiencies in a complex manufacturing system.
Ford Production System 2
Process Metrics Data
• Cycle Time (C/T)
• Changeover Time (C/O) & Frequency
• First Time Through (FTT)
• No. of Product Variations
• No. of Operators
• Uptime or Availability
• Overall Equipment Effectiveness
• Operating Pattern
When utilizing surrogate process data in capacity planning, historical data
from stable manufacturing sources must be adjusted based on unique design
& process complexity and re- validated as soon more data is available
Ford Production System 3
How to build

Value Stream Mapping


4
How to build

Value Stream Mapping


How to build

Value Stream Mapping


How to build

Value Stream Mapping


How to build

Value Stream Mapping


8
How to build

Value Stream Mapping


9
How to build

Value Stream Mapping


10
How to build

Value Stream Mapping 11


How to Calculate Takt Time
• Ten Steps to create a Value Stream Map (continued)
10. Calculate takt time for the process
– Seconds available per day / Daily customer demand
Takt Time is the time in which a finished part or
product is demanded by the customer. Noted in
sec/part.
• Determine the rate at which product or services must be
delivered in order to meet customer demand
• Jobs Per Hour or Capacity Planning Volumes (CPV) can be
converted into takt time.
 APW – Average Production Weekly ( 5 days operation)
 MPW – Maximum Production Weekly (6 days operation)
 Annual Volumes to Weekly Volumes – divide by 47.2 weeks/year

Value Stream Mapping


12
How to Calculate Takt Time

The goal is to match production rate with customer demand.


• Synchronize the pace of production to match the pace of
sales
Total Available Operating Time
Takt Time =
Customer Demand
calculated for a given time period

• Example: Customer needs 1800 pieces per week and the


supplier is running Two -10 hour shifts with 2 - 15 minutes
paid break per shift: How often is a part required?
342,000 sec / 1800 pcs = 190 sec or 3.18 min Takt Time
(19 hrs × 5 days x 60 min × 60 sec = 342,000)

Value Stream Mapping


13
Capacity Planning & Verification Value Stream Map

Value Stream Mapping


14
Linkage of Subtier to Tier 1
Capacity Planning & Verification

Tier 1 Value Streams Subtier Value Chain

Sub Tier
Capacity
Planning &
Verification

Tier 1 Supplier’s submission of Capacity Planning & Verification Capacity


Analysis Report (CAR) must include Subtier Capacity Confirmation
Value Stream Mapping
15
Linkage of Value Stream Map to
Capacity Analysis Report (CAR)

Value Stream Mapping


16
Sources of OEE Degradation
Recognizing Key Contributors

Ford Production System 17


Contributors to OEE Degradation

OVER PRODUCTION
 Labor and Overhead Measurables driving utilization of
people and equipment

 Losses from out of stock conditions

 Losses from blocked and starved conditions

 Material produced to speculative demand

18
Ford Production System
Contributors to OEE Degradation

MOTION

 Poor workstation configuration and


organization

 Work imbalance

 Visual Factory not implemented

 Standardized Work not implemented

Ford Production System 19


Contributors to OEE Degradation

CONVEYANCE
 Long distances from operation to operation

 Material Handlers not on scheduled routes

 Warehouse on or off site

 Distance between receiving and point of use

 Handling excess inventory

Ford Production System 20


Contributors to OEE Degradation

CORRECTION
 Poor, slow quality feedback

 Incremental inspection done outside process


station

 Repair operations are viewed as acceptable

 Few effective Error Proofing devices in use

 Standardized work not in place

 Product/process incompatibility

 Product over-complexity

Ford Production System 21


Contributors to OEE Degradation

INVENTORY (EXCESS)
 Mass Production mindset, batch and queue

 Unpredictable productivity

 Infrequent delivery / shipment of materials internally and


externally

 Schedules not linked between processes

 Visual Factory not in use to control

 Large containers / batch sizes

Ford Production System 22


Contributors to OEE Degradation

WAITING
 Waiting for support, information, and/or materials

 Low Overall Equipment Effectiveness and high machine


downtime

 Unbalanced operations

 Long and inconsistent lead times

 Continual production schedule fluctuations

 Watching automated machines

 Undisciplined meetings

Ford Production System 23


Contributors to OEE Degradation

OVERPROCESSING
 Standards unknown / unclear to operators

 Customer specifications are vague or fluctuate

 Product testing and re-testing occurs

 Functional departments have misaligned goals and poor


communication

 Concept that more is better

Ford Production System 24


Achieving Sustainable Manufacturing
Five Growth Phases
• Production schedule smoothing,
Level volume and mix distributed
Production evenly over time
• Steady workload

• Marketplace based pull replenishment (linked


Pull System to customer withdrawal)
• Inventory management/discipline (JIT)

• All operations and work stations synchronized to pace of


Synchronous customer demand rate (TARGET TIME)
Production • All work stations balanced (standardized work)

• Improved product flow, ideally single piece (batch of 1)


Continuous • Flow from value-add station to value-add station
Flow • Where flow is not possible, reduce batch sizes and work in process (WIP)

• Process is under control and predictable output


Stability • Basic workplace organization in place (to recognize abnormalities)
• Begin the elimination of waste using FPS tools

Ford Production System 25


Value Stream Mapping Capacity Threshold Analysis
Focus Elements
Potential
Focus Elements Threshold Assessment
Mitigation Actions
• Subtier Value Chain • OEE Improvement
Value Stream Constraints • Bottleneck Operation • Rebalancing Operation

• Validity of OEE and Changeover


assumptions for multiple part • Banking Plan
Equipment Shared variants • Qualify Back-Up Manufacturing
• Impact of Launch Ramp Up Plan Sources
Loading Robustness to Capacity Availability • Rebalancing Operation
• Impact of OEE shortfalls & • OEE Improvement
Degradation

Process & Quality • Process Capability Corrective


• Process Capability and resupply
Actions – Design, Tooling &
Stability impact on OEE
Process Improvement
• Alignment of Industrialization • Establish Robust Capacity Prove-
timing with Ford Launch Ramp Up Out plan utilizing lessons learned
Industrialization Ramp Up Schedule • Bank Planning for parts requiring
Lead Times • Support of Increased Premium mix long lead industrialization ramp up
beyond tooled capacity during • Add resources to compress
launch ramp up industrialization timing

Back Up Equipment & • Contingency planning for launch, • Qualify back up sources for
Resources bottleneck and unstable operations constraint operations

Value Stream Mapping


26

You might also like