Final Report
Final Report
net/publication/339746700
CITATIONS READS
0 672
1 author:
Buddhi Chamikara
Sri Lanka Institute of Information Technology
4 PUBLICATIONS 0 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Buddhi Chamikara on 06 March 2020.
Name: H. B. C. Jayasinghe
Registered No: EN17409056
Course: B. Sc. (Hons) in Engineering (UGC)
Field of Specialization: Electrical and Electronic Engineering
Period of Training: 4th November 2019 to 24th January 2020 (12 Weeks)
Abstract
I was interned at Venora Telecom (Pvt) Ltd. which was established under a subsidiary of the
Venora Group of Companies. Throughout the training period, I have gained understanding on the
earthing side of the telecommunication towers. And, I have obtained some practical experience
by assisting to the workshop works. Though I was a trainee from an engineering background, I
have performed some logistic tasks until a new officer was appointed attached with guidance of
the Accountant & the Marketing Executive except for the technical training.
i
Acknowledgement
I take this opportunity to express my profound gratitude and deep regard to the Sri Lanka
Institute of Information Technology for their exemplary guidance, monitoring and constant
encouragement throughout the training period. The blessing, assistance and guidance given by
them time to time, shall carry me a long way in the journey of life on which I am about to
embark.
I also take this opportunity to express a deep sense of gratitude to Venora Telecom (Pvt) Ltd. for
giving me the opportunity to carry out my industrial training. Specially to the CEO of the Venora
Telecom (Pvt) Ltd., Mr. Sanath Adhikari, who selected me for the training. And I am very
grateful to the Project Engineer of Earthing & Lightning Protection, Eng. Chinthana Wedamulla
who had given me the remarkable engineering project. And also, I like to thank to the Deputy
General Manager as well as to the Managers of Engineering Divisions, Engineers, Coordinators,
Quantity Surveyors etc. for their cordial support, valuable information and guidance, which were
very useful to me while completing the training successfully.
I am obliged to staff members of all the other departments in Venora; such as Site Engineers,
Technical Officers, Technicians and other minor staff for the information & assistance provided
by them in their respective fields.
I would also like to thank other trainees who were engaged with me during my industrial training
period for their kind cooperation specially to succeed the project.
At last, but not least, I would like to thank my parents for their tremendous contribution and
support, both morally and financially toward the completion of my training.
ii
List of Figures
iii
List of Tables
iv
Contents
Abstract ........................................................................................................................................ i
Acknowledgement ....................................................................................................................... ii
List of Figures ............................................................................................................................ iii
List of Tables .............................................................................................................................. iv
I have attached to the Venora Telecom (Pvt) Ltd. which was established under a subsidiary of
the Venora Group of Companies. Throughout the training period, a sample DCDU (Direct
Current Distribution Unit) was designed by me & other trainees of SLIIT as a reverse
engineering project. And, I have gained fair understanding on the earthing side of the
telecommunication towers. After attaching to the Telecom division, I was in the workshop in
my free time to learn the manufacturing processes. Though I was a trainee from an
engineering background, I have performed some logistic tasks until a new officer was
appointed attached with guidance of the Accountant & the Marketing Executive except for
the technical training.
1.1.1 Vision
Actively contribute to sustainable development of project rollout in telecommunication
engineering in Sri Lanka by utilizing capable & experienced personals with high standard
project management.
1.1.2 Mission
To lead Venora Telecom towards in strategic position telecommunication sector through our
enhanced service offerings.
1
1.2 Company Background/History
Venora Telecom stepping up to the international Telecommunication market from the year
2016 and formed a company in Myanmar as ‘Venora (Myanmar) International (Pvt) Ltd’ and
Venora Telecom expands the business with foreign exposure.
2
1.3 Management
3
2.0 TRAINING EXPERIENCE
At first, I have worked in the workshop of the Venora for one day. In there, my task was
assisting to the technicians, who were making power panels. After attaching to the Telecom
division, I was in the workshop in my free time to learn the manufacturing processes. While
working in it, everybody should aware on the below Safety Procedures.
4
Figure 2.1 Ingress Protection Ratings [1]
5
2.3 Training Project
A sample DCDU (Direct Current Distribution Unit) was designed by me & other trainees of
SLIIT. This is a reverse engineering project as its market price is not cheap & it is an
imported device to Sri Lanka. At first, the DCDU was re-designed by removing its non-
critical parts. Then, its non-critical parts were replaced to practically available parts in Sri
Lankan market. Due to the re-designing process, the unit’s operational cost was minimized
than its half of the market price.
There are two main types of DCDUs which are imported to Sri Lanka.
1. MCB type (Trip switch included) - DCDU-03
2. Fuse type (A fuse is included in the terminal) - DCDU-12B
6
Figure 2.3 DCDU-03
The DCDU-12B provides ten -48 V DC outputs using same fuse configurations to meet the
power distribution requirements of different distributed base stations.
It uses the equipotential connection point and ground point in the following scenarios:
Scenario 1: The DCDU-12B is installed on an open sub rack. An equipotential cable
connects the equipotential connection point near the mounting ear of the DCDU-12B
to the ground bar of the open rack.
Scenario 2: The DCDU-12B is installed on a wall as a standalone power distribution
device. The ground point at the rear of the DCDU-12B is connected to the ground bar
in the cabinet.
7
Figure 2.6 30 A Fuse
DCDU-03 DCDU-12B
1. Has MCB with different configurations 1. Fuses with different configurations
(Trip switch) 2. Terminals slots are used. Only working
2. Since screw terminals are used can work with these ports
with any ports 3. Cost low
3. Cost High 4. Maintenance is easy
4. Maintenance is hard 5. Has a LED bulb which indicate which
5. No indication terminals are working
8
Figure 2.8 Inside Appearance of the Redesigned DCDU
The New DCDU, re-designed by us, has following specifications: -
November December
Week 2 Week 3 Week 4 Week 1
1
2
3
4
5
6
7
8
Table 2.2 Timeline of the Training Project
9
Task No. Task Description
1 Understanding of the Problems to Solve
2 List of Requirements
3 Planning
4 Analysis of Previous or Similar Solutions
5 Evaluation of Possible New Solutions
6 Rational Selection of Tools, Methods, Components, etc.
7 Implementation
8 Presentation of the Project
Table 2.3 Task Description of the Timeline
These are used to prevent the appliances from the high current or overload damage. If we use
a fuse, the electrical faults cannot happen in the wiring and it doesn’t damage the appliances
from the fire of wire burning. When the fuse gets break or damage, then an abrupt sparkle
happens which may direct to damage your appliances. That is the reason we require different
types of fuses to guard appliances against damage.
The working principle of the fuse is “heating consequence of the current”. It is fabricated
with a lean strip or thread of metallic wire. The connection of the Fuse in an electrical circuit
is always in series.
10
When the too much current is produced due to the heavy flow of current in the electrical
circuit, the fuse gets soften and it opens the circuit. The extreme flow of current may direct to
the collapse of the wire and prevents the supply.
The fuse can be changed by the new fuse with an appropriate rating. It can be designed with
the elements like Cu (copper), Zn (zinc), Al (aluminium) and Ag (silver). They also perform
like a circuit breaker for breaking the circuit while the abrupt fault happens in the circuit.
This works like a safety measure or protector for humans from risks. Like this, the fuse
works.
𝑷𝒐𝒘𝒆𝒓 (𝒘𝒂𝒕𝒕𝒔)
𝑭𝒖𝒔𝒆 𝒓𝒂𝒕𝒊𝒏𝒈 = × 𝟏. 𝟐𝟓
𝑽𝒐𝒍𝒕𝒂𝒈𝒆 (𝒗𝒐𝒍𝒕𝒔)
The selection of a fuse can be done by calculating the fuse rating by using the above formula.
The main function of the fuse is to protect the electrical circuits from the overflow of current.
In a real-time situation, the flow of current during the wires may not be consistent all the
times. In that situations, the device may get damage from overheat. While the equipment has
highly developed with the handling of a circuit breaker, these types of fuses are still
employed in various places like fundamental electrical components.
Amount (Rs.)
Components’ Cost Enclosure 3,500.00
Copper Bus Bar 1,200.00
Electrical Components 3,028.00
Transport Cost Bus 3,000.00
Three wheel 800.00
Total Cost 11,528.00
Profit Margin 3,458.40
Estimated Price of the Re-designed DCDU 14,986.40
Table 2.4 Budget of the Re-designed DCDU
Profit Margin was calculated as the 30% of the Total Cost according to the guidance of the
Project Engineer. And, charges for powder coating are not included.
11
2.3.7 Conclusion
In conclusion, the re-designed sample DCDU is cost effective when it is comparing with
Huawei DCDU-12B, which is the cheapest DCDU in the market (The market price of
Huawei DCDU-12B is Rs. 29,000.00). And, the operating cost can be minimized, if DCDUs
are manufactured in a large scale by using the above techniques and this will be resulted to
save the foreign exchange.
Surge protector or a proper earthing method was not manufactured for the product due to the
lack of knowledge. It will be added to the design in future developments as it should be in the
circuit. 30 A fuses were used in the design as an alternative for the trip switches. By doing
this project, necessary workshop operations and the functions of were learnt. Useful
Drawings were done by using AutoCAD 2017 package. The total budget for the whole
project was minimized because this DCDU was designed by using reverse engineering
concepts.
The fuses are classified into several types based on the application namely AC type fuse and
DC type fuse. Again these fuses are classified into several types. The following diagram
illustrates the electrical fuse types chart based on the AC fuse and DC fuse.
12
2.4.1 DC Fuses
DC fuses are available superior in size, and DC supply has a stable value over 0 volts. Thus,
it is tough to remove and deactivate the circuit. There will be a chance of generation of an
electric Arc between dissolved wires. Electrodes located at better distances to conquer this.
For this reason, the size of DC fuse gets amplified. [2]
2.4.2 AC Fuses
The AC fuse is slighter in size and oscillated 50 to 60 times in each and every second from
least to highest. As a result, there is no scope for Arc generation between the dissolved wires.
For this reason, they can be crammed in small size. Further, AC fuses are classified into two
parts namely HV fuses and LV fuses. LV& HV indicates the low voltage and high voltage.
Technology & knowledge have evolved since Franklin’s time, when the only method of
protection was a simple lightning rod. Today, electrical engineers know the need for full
facility lightning protection to defend everything from the structure, to personnel, to valuable
electronic equipment, from strikes.
Before implementing a lightning protection systems, it’s important to understand the risks
associated with lightning. Three types of lightning risks that can cause injury or facility
downtime.
While no system can completely ward off the lightning risks above, proper protection
systems can help safeguard your facility, personnel and electronic devices. [3]
13
2.6 Lightning Protection Systems (LPS)
In general, a lightning protection system must perform the following in order to be
considered effective:
Intercept lightning flashes
Conduct the lightning current to the earth
Dissipate the current to the earth
Create an equipotential bond to prevent potential differences between the system,
structure and internal circuits
The function of a lightning protection system is to protect structures from fire or mechanical
destruction and to prevent that persons in buildings are injured or even killed. An overall
lightning protection system consists of external lightning protection (lightning
protection/earthing) and internal lightning protection (surge protection).
Furthermore, a lightning protection system is categorized into two parts. The first is the
external lightning protection system, which intercepts, conducts and dissipates the lightning
flash to the earth. Second, the internal system that prevents flash over within the structure
using equipotential bonding.
Also note that while lightning protection systems are generally implemented via a network of
bonded air terminals and down conductors, alternative systems that capture the strike and
conduct the discharge through an insulated conductor to the ground are available.
14
2.6.5 Classes of Lightning Protection System (LPS)
Classes of Lightning Protection System (LPS) I, II, III and IV are defined as a set of
construction rules based on the corresponding Lightning Protection Level (LPL). Each set
comprises level-dependent (e.g. radius of the rolling sphere, mesh size) and level-independent
construction rules (e.g. cross-sections, materials).
To ensure permanent availability of complex data and information technology systems even
in case of a direct lightning strike, additional measures are required to protect electronic
devices and systems against surges. [4]
In a nutshell, there are three main types of lightning protection/prevention methods for
protecting structures and human being against lightning.
15
Three types of lightning air terminals:
1. Static Early Streamer Emitting Terminal
2. Electronic Early Streamer Emitting Terminal
3. Franklin Rod (Conventional Lightning Rod) [5]
Residual Current Circuit Breakers are aimed at protecting an individual from the risks of
electrical shocks, electrocution and fires that are caused due to faulty wiring or earth faults.
RCCB is particularly useful in situations where there is a sudden earth fault occurring in the
circuit. e.g. A person accidentally comes in contact with an open live wire in the circuit.
In such situation, in absence of an RCCB in the circuit, an earth fault may occur and the
person is at the risk of receiving an electrical shock.
However, if the same circuit is protected with RCCB, it will trip the circuit in fraction of a
second thus preventing the person from receiving an electrical shock. Therefore, it is a good
and safe practice to install RCCB in your electrical circuit.
As explained above, RCCB is meant for protection from earth faults and associated risk to
human life such as electrical shocks.
The underlying fundamental principle behind operation of RCCB is that in ideal situations
the current flowing in to the circuit through live (hot) wire should be same as the returning
current from the neutral.
In case of an earth fault, the current finds a passage to earth through accidental means (such
as accidental contact with an open wire etc.). As a result, the returning current from neutral is
reduced. This differential in the current is also known as “Residual Current”.
RCCB is designed such way that it continuously senses and compares for difference (residual
current value) in current values between the live and neutral wires. Any small change in the
current value on account of such event would trigger the RCCB to trip off the circuit.
Types of RCCBs:
2 Pole RCCB: It is used in case of a single phase supply that involves only a live and
neutral wire. It is as displayed in image below. It contains two ends where the live and
neutral wires are connected. A Rotary switch is used to switch the RCCB back to ON
or OFF positions. A test button helps to periodically test the RCCB functionality.
4 Pole RCCB: It is used in cases of a three phase supply connection involving three
phase wires and a neutral. It is as displayed in image below. It consists of two ends
where the three phases and neutral wire is connected. Besides this it is similar in
construction and operation as 2 Pole RCCB.
16
RCCBs come in different ratings like: 30 mA, 100 mA, 300 mA.
The most widely used are 30 mA (milliamp) and 100 mA devices. A current flow of 30 mA
(or 0.03 amps) is sufficiently small that it makes it very difficult to receive a dangerous
shock. Even 100 mA is a relatively small figure when compared to the current that may flow
in an earth fault without such protection (hundreds of amps).
A 300/500 mA RCCB may be used where only fire protection is required. E.g., on lighting
circuits, where the risk of electric shock is small. [6]
It is possible to get a combined MCB (Miniature Circuit Breaker) and RCCB in one device
(Residual Current Breaker with Overload RCBO), the principals are the same, but more
styles of disconnection are fitted into one package
RCCB is primarily designed for protection from earth fault and its consequence to human life
such as electrical shocks.
As per studies, a person is able to sustain electrical shocks only to the magnitude of 30 mA.
Thus, RCCBs in low voltage protection are designed such a way that they will trip off the
circuit even for small change in residual current value of up to 30 mA. The response time is
usually within 40 milliseconds, thus ensuring that the person is fully protected from electrical
shocks at all times.
Higher values of 300 mA are used in cases where a protection from fire hazard is sought.
This is useful in places where a lot of flammable material is stored.
In conclusion, RCCB is an essential protective device in your electrical circuit that helps to
prevent electrical hazards in cases of earth faults. A properly set RCCB will ensure that there
is no fatal injury caused to human being in case of an accidental touch to live wires. [7]
The Surge Protection Device (SPD) is a component of the electrical installation protection
system. Surge Protection Devices (SPD) are used for electric power supply networks,
telephone networks, and communication and automatic control buses.
17
This device is connected in parallel on the power supply circuit of the loads that it has to
protect. It can also be used at all levels of the power supply network.
This is the most commonly used and most efficient type of overvoltage protection. SPD
connected in parallel has a high impedance. Once the transient overvoltage appears in the
system, the impedance of the device decreases so surge current is driven through the SPD,
bypassing the sensitive equipment.
SPD is designed to limit transient over-voltages of atmospheric origin and divert current
waves to earth, so as to limit the amplitude of this overvoltage to a value that is not hazardous
for the electrical installation and electric switchgear and control-gear.
The most enhanced range of surge protection devices for power, data and communication
lines:
1. Type 1 SPD
2. Type II SPD
3. Type III SPD
1. Telephone Lines
2. Data Lines
3. Computer Lines
4. Coaxial Lines [9]
Digital Earth Tester was used measure the resistance of the tower legs. At first, three colour
(green, yellow & red) cables were connected to the Digital Earth Tester via their probes.
Then, the tester was set to 20 Ω by using its rotary selector. After that, the green cable was
connected to a bus-bar/down conductor of one tower leg. Before connecting, the bus-
bar/down conductor was scrapped by using the crocodile probe of the cable to avoid
receiving wrong values due the oxide layer. Then, the yellow & red cables were carried to the
18
longest distance, which they could carried, to the direction, which was showed by the
engineer. They were connected to Cu Testing Rods via their crocodile probes & those Rods
were connected to soil which hadn’t stones. Finally, the orange colour button was press to
obtain the values.
Tower legs are earthed by using galvanized Cu bus-bars. But one tower leg in every telecom
tower has a down conductor except for a bus-bar.
The resistance of the tower legs must be less than 10 Ω. But it can be changed due to some
reasons; especially the soil condition in the area. Therefore, Cu Testing Rods were connected
to the places which hadn’t stones in the soil. The soil in these sites were affected by the
lightning which was happened on previous day.
19
2.8 Summary of Duties
After attaching to the Telecom division, I have assisted to manufacture HRC Fuse Boxes,
ACDBs, ECBs, SPDs & one ATS in the workshop in my free time to gain the practical
experience. Before the manufacturing processes, everyone must get familiar with the
drawings, tools and installation procedure.
Socket wrench
Adjustable wrench
Hex key
Crimping tool Used to crimp cord end
terminals.
20
2.8.1 Assisted to Manufacture an ACDB
Main purpose of ACDB (Alternative Current Distribution Board) is to distribute the
alternative power which was given by the Ceylon Electricity Board. It supplies power mainly
to the Rectifier inside the cabin. Except that, it supplies power to,
i. 15A socket outlet
ii. 13A socket outlet
iii. 5A socket outlet
iv. 5W bulb
The ACDB was constructed in a metal enclosure. Several types of MCBs and one RCCB
were used to manufacture it. for distribution of power. A photo of a previously prepared
ACDB was sent via WhatsApp as the guidance & a copy of the Material Request Note was
given to collect the materials from the stores.
MATERIAL AMOUNT
I gang I way switch Kevilton 01
Bulk head light fittings with CFL bulb 01
Colour cap 2 mm 08
Colour cap 8 mm 20
Cable duct casing 33W × 45H mm 01
Earth cable 2.5 mm Sierra 3m
Earth link 12 way 01
MCB 16A 1P 6KA 01
MCB 6A 1P 10KA 01
MCB 16A 2P 10KA 02
MCB 32A 4P 10KA 02
Metal enclosure with cover 01
PVC distribution box surface type 16W 01
RCCB 40A 2P 3mA 01
Switchgear cable 1.5 mm 2m
Bolt 6 mm × 15 mm 20
Bolt 6 mm × 25 mm 04
Nut 6 mm 24
5A switched socket outlet orange 01
13A switched socket outlet orange 01
15A switched socket outlet orange 01
Switch sunk box single 04
Switchgear cable 6 mm 5m
Table 2.6 Used Materials with Their Quantities
The objects to be mounded such as the PVC distribution box, the earth link, bulk head light
fitting, sun boxes and duct were kept on the panel plate and adjusted specifically. Then, the
drilling positions were marked out by using markers. After that, the drilling positions were
drilled by using 6 mm drill thread. Then, the drum, created by the drilling, was smoothened
by using a higher drill thread as 8 mm. After that, the objects were kept on the panel plate and
fixed to the plate by using 6 mm nut and bolt. A PVC distribution box was mounded, inside
the metal enclosure on the panel plate, to hold the breakers. Cable duct casing was mounded
to place wires inside.
21
Figure 2.14 The Photo of Previously Prepared ACDB
After the mounding process, the breakers were fixed on the aluminium rail inside the PVC
enclosure. Then, then wiring of the beakers were done with the assistance of the technicians.
Power from the CEB comes as three phases, from those three, one phase and neutral were
taken into distribution of power through the breakers. And, a three-phase current was taken to
the Rectifier inside the cabin from the panel.
A four core cable was used as the main cable, which supplies power to the Distribution
Board, was 3 phase. This cable consists of four wires. Including the earth cable there were
five wires. These cables have the following colours /colour caps.
Phase 1 - Brown
Phase 2 - Black
Phase 3 - Grey
Neutral - Blue
Earth - Green
The earth cable was set along the common area on the cable tray. And, it was connected to
each component through the sleeve. After of all, the power was distributed to the socket
outlets and the 5W bulb. The cables were taken through the cable duct.
Channel cable tray was used to hold the main cable. The Insulation Test was done to check
the current leakages. 500 V was supplied & measure the resistance. Better insulation can be
obtained for the high resistance.
Before the panel plate was fitted into the metal enclosure box, it was cleaned with air vacuum
gun. Then, it is fitted inside the metal box. After that, the door of the metal box was also
earthed. Finally, the ACDB was wrapped with cellophane paper & load into the truck to
transport to the site.
22
Venora Telecom returns the damaged telecom devices of the telecom towers after
disassembling them from the towers. Then, they were stored in the yard until their owners
order to return them.
One ACDB’s inside components were lost/misplaced when it was stored in the yard. Then, it
could not be returned. Therefore, another engineer was requested to fix/arrange the
components of the ACDB properly. Some new components/materials were used to this task
since they were unable to find in the yard.
As this task was given few weeks later, it could finish in a small time.
23
2.8.3 Assisted to Prepare an ECBs
ECB are very essential when it comes to earthing scenarios. ECBs are commonly called as
‘bus-bar’ at the industry. These bars are used to provide a convenient common earthing point
for electrical installations. Usually they are produced from Copper, Aluminium or Stainless
steel. Copper is a good conductor compared to Aluminium & it is cheap than Stainless steel.
Venora can produced ECBs (Earth Connecting Bars) depending on their requirement. At first,
required copper bar size was marked on the long copper bars. Then, the marked copper bars
were cut by using Hydraulic Bus-bar Cutting Machine. After that, the required number of
holes were drilled at the workshop. Holes were marked with the help the digital Vernier
caliper screw gauge and ruler. Digital Vernier caliper was used to measure the width of the
ECB to find its mid-point. After marking at least three mid-points by using a pencil, a line
was drawn through them.
The length of the ECB was divided according the number of holes needed and also concern
on the diameter of the hole’s. The dimensions of the ECB and the number of holes on it
depends upon the task.
Then, lines were drawn vertically against the length. At crossing points, the pointer was kept
and taped by hammering to mark a small dot as cavity. After that, the bar was taken to the
drilling machine to drill out the holes by using 8 mm drill thread. After drilling the holes, 10
mm drill thread was used to remove the drums which were created by drilling. Finally, they
were galvanized to avoid the corrosion & protect them from thieves by indicating that they
were not made by Copper.
24
2.8.4 Performed Logistic Tasks
Before 20th of December 2019, Venora Group has not a Logistic Officer. Therefore, the
logistic tasks were done by other officers. One day the Marketing Executive was requested to
buy plastic dc tape clips from Rotax (Pvt) Ltd. I have accepted that task as a help & our
Training Supervisor was permitted me to leave. The Accountant was given Rs. 10,000/- to
buy the required item & pay for buses.
At first, a photo of a plastic dc tape clip was shown & sent to me by the Marketing Executive
as I was not familiar about it. Then, the location of the company was shown by using the
Google Map. I could find buses to the location & relevant buses were selected from them by
me as I was familiar with Google Maps & the location.
Due to the traffic, I was late to return the bought items. Therefore, the Marketing Executive
ordered to handover them to the guardroom with the invoice.
After nearly a one week ago, another engineer requested to buy a Meter Board & hand over it
to Mobitel site at Homagama. Its dimensions should be 1 Ft. & 11 inches in both length &
width. Its thickness can be 1 or 1.5 inches. But it should be handed over to the site on or
before 3.00 p.m. However, it must be cost around Rs. 2,000 & the material isn’t concerned. A
Crew Cab & a driver was provided.
It has taken lot of time as most of saw-mills were not opened on Monday morning & some
low quality timber boards had not the enough thickness. Finally, a board could be found,
which has 1inches thickness, & it was handed over before 3.00 p.m. to the site.
Except for the above tasks, I have accepted to perform several logistic works & gain the
knowledge from such activities. Some of them were done when the newly recruited Logistic
Officer was doing another task at that time.
25
3.0 CONCLUTION
It is obvious that I had a great experience during my industrial training period at Venora
Telecom (Pvt) Ltd., as this was my second industrial training experience. Throughout the
training I have got vital knowledge and experience in this field. Also, I determined to deploy
my theoretical knowledge and skills, to put into practice.
26
References
[1] R. Bohn, “IP Ratings Explained,” Nema Enclosures, 02 08 2013. [Online]. Available:
https://www.nemaenclosures.com/blog/ingress-protection-ratings/.[Accessed 2019 11 27].
[2] “Different Types of Fuses and Its Applications,” Elprocus, 2020. [Online]. Available:
https://www.elprocus.com/what-is-fuse-different-types-of-fuses-and-applications/.
[Accessed 28 11 2019].
[3] “A Beginner’s Guide to Lightning Risks and Protection Methods,” Nvent, 23 02 2018.
[Online]. Available: https://blog.nvent.com/erico/erico-a-beginners-guide-to-lightning-
risks-and-protection-methods/. [Accessed 15 11 2019 ].
[5] “Lightning Air Terminals,” Dhruva Technologies (Pvt) Ltd. , 2020. [Online]. Available:
https://www.dhruvatec.com/lightning-air-terminals.html. [Accessed 07 01 2020].
[6] Jiguparmar, “What is the difference between MCB, MCCB, ELCB, and RCCB,” 2020 01
19. [Online]. Available: https://electrical-engineering-portal.com/what-is-the-difference-
between-mcb-mccb-elcb-and-rccb. [Accessed 25 10 2011].
[9] “Surge Protection Devices,” Dhruva Technologies (Pvt) Ltd. , 2020. [Online]. Available:
https://www.dhruvatec.com/surge-protection.html#1. [Accessed 28 12 2019].
27