Guidance Part 3 Operational Phase of The Asset Life Cycle Edition 2
Guidance Part 3 Operational Phase of The Asset Life Cycle Edition 2
Edition 2
Published by
Editions
Edition 1 September 2020
Edition 2 February 2021 Updates include:
Major rewrite and extension of subjects covered
Nothing in this guidance constitutes legal advice or gives rise to a solicitor/client relationship. Specialist legal advice should be taken in
relation to specific circumstances.
The contents of this guidance are for general information purposes only.
Permission to reproduce extracts from the ISO 19650 series is granted by BSI Standards Limited (BSI) and the copyright in figures 2 and
3 used in this report belongs to BSI. No other use of this material is permitted.
British Standards can be obtained in PDF or hard copy formats from the BSI online shop: http://www.bsigroup.com/Shop or by contacting
BSI Customer Services for hardcopies only: Tel: +44 (0)20 8996 9001, Email: [email protected]
Any data or analysis from this guidance must be reported accurately and not used in a misleading context. If using any information
from this report, then its source and date of publication must be acknowledged.
Table of contents
Message from the UK BIM Alliance Chair 3
Acknowledgments4
About BS EN ISO 19650 5
About this guidance document 6
Abbreviations and acronyms 7
1.0 Introduction 8
2.0 The information management context for ISO 19650-3 9
2.1 Managing information during the operational phase of assets and facilities 9
2.2 H ow ISO 19650-3 reflects the concepts and principles of ISO 19650-1 12
3.0 Parties and responsibilities 14
3.1 Introduction 14
3.2 Parties 15
3.3 Responsibilities 18
3.3.1 Assessment and need for information 19
3.3.2 Tender stage and mobilization 20
3.3.3 Asset Information handover and aggregation 20
4.0 E xplaining the information management flowchart 21
4.1 The flowchart 21
4.2 Trigger events 23
4.3 Proportionality 24
5.0 Use cases for ISO 19650-3 25
6.0 E xample application of ISO 19650-3 to a specific trigger event 27
6.1 Target audience 27
6.2 D efinition and categorization of trigger events in the operational phase of an asset 27
6.3 Categories of Trigger Events in the asset lifecycle 29
6.4 Worked example: Commissioning a survey to determine the extent of a refurbishment 30
6.4.1 Scenario 30
6.4.2 A pplying the clauses of ISO 19650-3 31
7.0 Integrating information delivered through ISO 19650-3 into existing systems 33
8.0 ISO 19650-3 clause 5: insight 35
9.0 Information management process summary 48
10.0 Summary 58
2 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
List of figures
Figure 1: ISO 19650 guidance framework 6
Figure 2: Information management during the life-cycle of an asset
[SOURCE: ISO 19650-3 Figure 1] 10
Figure 3: Interfaces between parties and teams for information management 15
Figure 4(a): Simple party relationships/appointments 17
Figure 4(b): Multiple external appointed party relationships/appointments 17
Figure 4(c): Mixed internal/external appointed party relationships/appointments 17
Figure 5: Information management process flowchart from ISO 19650-3 21
Figure 6: Illustration of use cases for applying ISO 19650-3 process 26
Figure 7: Trigger events during the operational phase of the life cycle 28
Figure 8: Example trigger events grouped by theme 29
Figure 9: A staged approach to Integrating ISO 19650-3 into existing information systems 34
List of tables
Table 1: Abbreviations and acronyms 7
Table 2: New responsibilities in ISO 19650-3 compared to ISO 19650-2 18
Table 3: Survey trigger example of ISO 19650-3 activities 31
Table 4: Where to find insight text for ISO 19650-3 clauses 35
3 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
The UK BIM Framework provides the the “end in mind” and consideration from an
fundamental step towards digital organizational, whole life perspective. This
transformation of the UK’s built environment then informs the detailed requirements right
industry. The Framework is based on the ISO down to appointment level.
19650 series, which first developed out of the
UK’s former BIM Level 2, but incorporates The work behind developing this Guidance
and anticipates global and future digital has been considerable. I would like to thank
perspectives. Sarah Davidson and David Churcher for their
tireless commitment in continuing to bring this
The UK BIM Framework embraces and assists work together – I so enjoy working with you
in the implementation of the standards both. Secondly, I would like to thank the many
for managing information for the whole authors who have contributed so generously
life of assets of the built environment. The to the writing of the Guidance – and been so
Framework anticipates the potential for patient in the criticisms and changes that have
integration across portfolios. The Framework been required of them. Finally, I would like to
provides extensive Guidance which continues thank the many people who have spared time
to be developed, including the addition of to review and feedback on the Guidance – the
supplementary tools and materials to enable Focus Groups in particular, but also those who
a firm basis for the evolving National Digital have contacted us separately. Without this
Twin Programme. feedback we would not be able to incorporate
the wide-ranging experience and testing which
This Guidance has been developed to help is occurring around the industry.
industry to implement the concepts and
principles of the ISO 19650 series upon which We welcome your continued feedback and
the UK BIM Framework is based. It has shared experiences. You can provide this via
been continually updated to keep track of [email protected].
the publication of the different parts of ISO
19650, and to reflect lessons learnt as further
experience is gained in its implementation.
Acknowledgments
This guidance represents the collaborative efforts of
the following people and organizations
Editors
David Churcher Hitherwood Consulting Ltd
Sarah Davidson University of Nottingham
Anne Kemp Atkins
Author
David Churcher Hitherwood Consulting Ltd
Sarah Davidson University of Nottingham
Javed Edahtally Public Health England
Andy Green Atkins
Stephen Holmes CADventure
Chloe Obi Bouygues UK
Shahida Rajabdeen Faithful+Gould
Julian Schwarzenbach DPA Data Advantage
Graeme Tappenden Lingwell Consulting Ltd
Ryan Tennyson Scottish Futures Trust
Jarek Wityk Winters Electrical Services Ltd
Contributors to section 6
Neil Chatfield Defra
Martin Geach Atkins
Louise Hynes Government Property Agency
David May Sententia Consulting Ltd
Gary Rogers Faithful+Gould
Graeme Tappenden Lingwell Consulting Ltd
Mark Thorneloe HMRC
Paul Waterson DIO
Reviewer
Craig Wootton University of Sheffield
Production
Centre for Digital Built Britain
5 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
The BS EN ISO 19650 series of standards Standards within the ISO 19650 series are
(herein after referred to as the ISO 19650 available at www.bsigroup.com.
series) is an international standard of good Visit www.ukbimframework.org to see how the
practice. It defines information management ISO 19650 standards plus other standards
principles and requirements within a within the UK BIM Framework map to the
broader context of digital transformation design, build, operate and integrate process.
in the disciplines and sectors of the built
environment (including construction and asset
management industries). Its implementation
in the UK is supported by UK National
Forewords in ISO 19650 Parts 1, 2, and 3, and
a UK National Annex in ISO 19650 Part 2.
The guidance framework supports the UK As with all guidance supporting the UK
implementation of the ISO 19650 series. BIM Framework, we invite comment and
This guidance document (guidance part 3) feedback on this guidance part 3 at
sits within an overall guidance framework as [email protected]
shown in Figure 1.
ISO 19650
Guidance Part 1
Concepts
ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650
Guidance A Guidance B Guidance C Guidance D Guidance E Guidance F
The Open data, Facilitating the Developing Tendering and Information
information buildingSMART CDE (workflow information appointments delivery
management and COBie and technical requirements planning
function & solutions)
resources
Guidance part 3 is written to support the applied, and the different organizational roles
implementation of BS EN ISO 19650-3, which involved in implementing the ISO. It explains
sets out the information management process the flowchart of process steps, describes
for the operational phase of the asset life- an example of applying the process to a
cycle. particular trigger event (survey) and explains
how information delivered as a result of the
This guidance is designed to be read by process can be incorporated into existing
those responsible for owning, operating and information systems. There is some insight to
maintaining infrastructure and building assets. certain ISO 19650 Part 3 clauses, focusing on
Much of the content is standalone but some those that are completely new compared to
elements refer to Guidance part 2. There are ISO 19650 Part 2, and detailed flowcharts of
also some references to the Guidance parts A the ISO 19650 Part 3 process.
to F.
Accompanying this guidance document is a
In particular, the guidance explains different separate flowchart of the whole process that
use cases when the ISO 19650 Part 3 can be printed on a single sheet at A3.
information management process can be
7 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
This guidance includes a number of abbreviations and acronyms as set out in Table 1.
Table 1: Abbreviations and acronyms
1.0 Introduction
This document is the second edition of ISO 19650-3 is written in the form of a
guidance for BS EN ISO 19650-3 (referred to specification and its main clauses set out
here as ISO 19650-3) and is part of the UK things that have to be done or achieved.
BIM Framework Guidance suite. It provides The text uses the word “shall” to convey each
guidance on the roles and responsibilities requirement. In line with many specifications
involved in implementing ISO 19650-3, the there is very little guidance in the standard on
situations when it can be applied and the how the requirements could be satisfied – that
details of the information management is left up to each organization implementing
process. It also gives some detailed guidance the standard. However, this is where the UK
on applying the process to a particular trigger BIM Framework Guidance comes in, to provide
event (maintenance) and on incorporating a baseline for users of the standard when
information delivered through ISO 19650-3 putting it into practice.
into existing information systems.
Transition from PAS 1192-3
Now that ISO 19650-3 has been published,
it means there is a wholly international In the UK, ISO 19650-3 has replaced PAS
set of standards defining the information 1192-3, which had been available since 2014.
management process throughout the life-cycle Many asset owners/operators have become
of an asset (delivery phase and operational familiar with its requirements and they should
phase). be reassured that all the key principles from
the PAS have been brought forward into the
ISO 19650-3 sets out the requirements for ISO.
information management using building
information modelling (BIM) during the BSI has published a short transition document
operational phase of an asset’s life. This to help organizations make the change
means it is designed to be applied during the from PAS 1192-3 to ISO 19650-3 and it is
period an asset is in use and when an asset not the intention of this guidance document
needs to be managed even if it is not being to replicate that transition guidance. It is
used, for example if it has been mothballed. recommended that the BSI transition guidance
The primary users of ISO 19650-3 are is read alongside this document.
therefore expected to be asset managers
and facilities managers, and the teams and
contractors that work for them. The standard
will also be helpful to those delivering capital
projects to design and construct new assets,
as it will help them understand why they are
asked to produce operational information as
part of their work.
9 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
2.0 T
he information management
context for ISO 19650-3
2.1 M
anaging information during the operational phase of assets
and facilities
Information in the context of asset The ISO 19650 series supports asset
management requires the specification, management and defines the approaches
production, exchanging, checking and to information that comprise both project
approval of information. Information should activities in part 2 and, in part 3, operational
be structured and consistent and, where phase activities of assets. ISO 19650-3 Figure
possible, support predictable and repeatable 1 illustrates the relationship between the
outcomes. Information should be seen as a two sets of standards and the relationship
valuable asset in its own right, and with its between delivery phase activities (defined in
own performance criteria. Performance can ISO 19650-2) and operational phase activities
be economic by measuring its link to a return (defined in ISO 19650-3). This is shown in
on investment or reduction of liability, and Figure 2 below.
can also relate to its relevance to support the
asset management process.
Key
AIM asset information model
PIM project information model
A start of delivery phase — transfer of relevant information from AIM to PIM
B start of operational phase — transfer of relevant information from PIM to AIM
C post-occupancy/implementation evaluation or performance review
D trigger events during the operational phase
NOTE Information can be transferred between PIM and AIM during the delivery phase as well as
at points A and B
The ISO 55000 series defines a management Information about assets will be required
system for the management of assets and for at least as long as the life of an asset
portfolios of assets over the life of those or facility. For example, design information
assets. In managing assets, a variety of developed prior to asset construction may
activities take place where asset information be essential to the refurbishment or safe
is a critical enabler. ISO 55001 clause 7.5 demolition of the asset many years in the
c) states “the organization shall specify, future. Therefore, information needs to be
implement and maintain processes for available, accessible and readable in the
managing its information” but the standard future. The ISO 8000 series of standards
does not define the approaches to achieve specifies a range of approaches to support
this outcome. Developing a Strategic Asset the effective management of data quality by
Management Plan (SAMP) with its long-term an organization.
intervention plan is an activity that is highly
reliant on data since it will not be realistic to
survey every asset each time the plan is being
developed or revised.
11 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
2.2 H
ow ISO 19650-3 reflects the concepts and principles of ISO
19650-1
ISO 19650-3 defines the information 6. Information deliverables are collated into
management process through a series of information models that are exchanged
eight steps with loops and branches defined between delivery teams (asset/facility
by questions and decisions. Figure 5 in this contractors) and the appointing party
guidance reproduces the process flowchart (asset owner/operator), and may then be
and some of the details in it are explained in passed on to other stakeholders such as a
section 4. regulator
The process as a whole reflects the concepts 7. Information production and review,
and principles from ISO 19650-1. This means including authorization and acceptance,
that it includes the following features: uses the common data environment
(CDE) workflow and whatever CDE
he information management process
1. T solutions the various parties wish to apply
is to be applied in a way that is
proportionate to the scale and complexity 8. Information models from various delivery
of the asset owner/operator, the asset(s) teams are federated to generate the
in question, the trigger events that occur asset information model, that can
in relation to the asset, the works required then be used throughout the asset’s
to respond to the trigger events, and the operational life for analysis, reporting
information required as a result of the or other uses that satisfy the information
work done. purposes
3.1 Introduction
Effective information management is
central to any asset management strategy;
therefore, to manage and operate their assets
successfully, owners/ operators need to clearly
understand and specify what their exact
information requirements are and the delivery
of those.
3.2 Parties
ISO 19650-3, section 0.5, Figure 3 (below)
shows the principal parties and their relational
interfaces in the operational phase. This is
consistent with the organizational diagram
within ISO 19650-2 (Figure 2) which indicates
the same parties, relationships, and interfaces
during the project delivery phase.
Key:
A appointing party
B lead appointed party
C appointed party
... variable amount
1 asset management and
operation team
2 illustration of delivery team
3 task teams
information requirements
and information exchange
information coordination
between lead appointed
parties if required by
appointing party
Appointment Appointment
m ent
int Appointed party
po
Ap Service contractor
Appointment (does most the work)
Appointed party
Specialist asbestos surveyor
nt
t me Appointed party
p o in
Ap In-house survey team
Appointment (does most the work)
Appointed party
Specialist asbestos surveyor
3.3 Responsibilities
The UK BIM Framework Guidance part 2,
sections 1.3, 1.4 and 1.5 explain the activities
and outputs which each appointing party, lead
appointed party and appointed party should
fulfil when adopting ISO 19650-2, the delivery
phase of assets. Many of these activities
and outputs are repeated and relevant in
ISO 19650-3, the operational phase of the
asset lifecycle. However, there are several
principal differences and responsibilities which
are summarized in Table 2 and the following
subsections. Detailed insights for each of the
clauses in Table 2 are given in section 8.
3.3.1 A
ssessment and need for information
The appointing party is responsible for Further OIR and AIR guidance is available in
defining their organizational information section 8 (insight for clauses 5.1.2 and 5.1.4)
requirements (OIR) which identify what and in Guidance Part D.
information is needed to satisfy and support
the delivery of agreed strategic objectives Through the establishment and upkeep of the
within the organization. For example, an AIR, an appointing party can identify and
estates department could have OIR regarding collate a series of foreseeable trigger events
the completeness of statutory compliance which will occur over an asset’s lifecycle. Each
records for risk analysis or insurance purposes. trigger can represent a single or repeating
planned event with associated actionable
Identification of OIR will enable an asset task(s) and new or updated information
owner/ operator to identify their priority requirements. For example, following a
assets and what associated information is boiler service an actionable task could be the
required and needs to be managed. This update of the logbook, or during a period
will inform the establishment of the asset of mothballing or building vacancy the
information requirements (AIR) which the actionable task could be to perform legionella
asset owner/operator/departments or other tests on a school water system. Further
stakeholders will need to operate, monitor, trigger event guidance is available in sections
and manage specific systems and assets. For 4.2, 6 and 8 (insight for clause 5.1.5).
example, an in-house asset management team
may require assets and spatial locations to be ISO19650-3 is applicable to assets of all
named or tagged using a unique identification sizes and all levels of complexity, many of
code or naming convention, for onward which will be existing buildings and pieces
linking or importing into an existing enterprise of infrastructure. It is likely many existing
management system (e.g., EDMS, CAFM). assets will be using existing enterprise systems
to store and manage asset information,
The AIR will change and refresh as parts of and it may not be feasible to set up a new
the physical asset and their systems adapt, or centralized information management
update, or are replaced during the operational system when adopting this standard. It is the
lifecycle. For example, replacing a gas-fired appointing party’s responsibility to ensure any
heating system with a mixture of renewable new or continued use of existing systems can
technologies will affect the information that support the requirements of ISO 19650-3, and
is required to manage the new systems and can be maintained accordingly. This is critical
this will lead to a replacement set of AIR. The to establish the asset information model and
appointing party is responsible for ensuring ensure its long-term integrity across one or
the OIR and AIR are fully aligned and kept many enterprise information systems. Further
up to date in line with their needs. The AIR guidance is available in sections 7 and 8
should be structured in a way which is easily (insight for clauses 5.1.10).
apportioned and assignable to the relevant
lead appointed party at each invitation to However, where the assets are relatively
tender stage. This ensures there is clarity of simple and the appointing party’s
scope in terms of: requirements are relatively straightforward,
it need not be complicated or expensive to
• information required
establish the different sets of information
• how it is delivered / exchanged (exchange requirements, to incorporate the exchange
information requirements) information requirements into relevant
• the ability to procure a more accurate and contracts and to configure existing information
comparable tender cost returns from the systems to be able to hold any new pieces of
prospective contractors information that are deemed necessary. A
• helping to avoid the risk of downstream simple approach can satisfy the requirements
duplication or overlap of information during of ISO 19650-3 – complexity is certainly not a
production. requirement.
20 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
3.3.2 Tender stage and mobilization 3.3.3 Asset Information handover and
aggregation
The appointing party (asset owner/ operator)
is responsible for appointing a lead appointed The appointing party (asset owner/
party in relation to one or more trigger events. operator) is responsible for the final review
This may be through a formal tender process, and acceptance of all asset information
especially where external contractors are delivered by each lead appointed party,
involved, but may also be through internal and the onward update or replacement of
appointments such as through works orders or existing asset information content within
instructions. It is also possible to make term- the relevant enterprise system(s). The
appointments with call-off arrangements for precise legal responsibilities and liabilities
each discrete piece of work. It is important around acceptance of information need to
to note if in-house teams are appointed or be explained in the contract governing the
assigned to provide trigger related services appointment, including what happens if
the same level of responsibilities and process information appears to be complete but later
should be applied. turns out not to be. ISO 19650-3 requires
that an information protocol is incorporated
Where trigger events are foreseeable, the into all appointments to cover these aspects.
information management process and asset The same requirement in ISO 19650-2 has
information requirements can be pre-defined given rise to the publication of a standard
and lead appointed party(s) appointed in information protocol that is appropriate
advance of the needed works. The frequency for design and construction contracts. No
of trigger events may vary according to asset, equivalent protocol for Part 3 has been
work order type, or contractual/ statutory written as yet, but the Part 2 protocol could be
requirements. During long or inactive periods, consulted to give an indication of what might
the lead appointed parties should either be needed.
remain mobilized or provide assurance of their
ability to mobilize when required, and have The appointing party is responsible for
the necessary resources in place to complete the central or linked enterprise system(s)
scheduled or planned trigger events. which support/host the AIM. The system(s)
must enable the AIM to be structured and
In instances where unforeseen or unplanned maintained properly, and to continue to
trigger event occur, the appointing party fulfil its overall purpose. Further guidance is
will need to instigate a process to appoint available in section 8 (insight for clauses 5.8.1
an appropriate lead appointed party(s). and 5.8.2).
Again, it is important to note if in-house
teams are appointed or assigned to provide
trigger related services the same level of
responsibilities and process still should be
applied. Further guidance is available in
section 8 (insight for clause 5.2.1).
21 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
4.0 E
xplaining the information
management flowchart
(ISO 19650-3 Figure 4)
Pathway D:
acquisition
of asset
Trigger
event
The key elements of the flowchart are as • Within the pathways B and C, the process is
follows: broken into 3 sub-groups labelled E, F and
G.
• The process comprises eight steps, • Sub-group E is about procurement – of
numbered 1 to 8, and the requirements a tier 1 contractor or an in-house team
at each step are contained in the to be responsible for some information
corresponding sub-clause of ISO 19650-3 deliverables (lead appointed party).
clause 5 (for example, step 1 is covered by ISO 19650-3 covers information
clause 5.1) procurement activities in clauses 5.2
and 5.3
• Step 1 of the process is where the • Sub-group F is about planning –
appointing party (asset owner/operator) the mobilization of the appointed
prepares for the rest of the information contractor or in-house team and the
management process. This includes appointment of any further parties
assessing what information they need within the delivery team (appointed
parties). ISO 19650-3 covers
at organizational and asset levels, and
information planning activities in
preparing all the supporting resources for clauses 5.4 and 5.5
the process such as the asset information
• Sub-group G is about production
standard and establishing the common data – when information is produced by
environment appointed parties, reviewed by a
lead appointed party and ultimately
• Step 1 leads to three different pathways, accepted by the asset owner/operator
shown as shaded boxes labelled B, C and D. (appointing party). ISO 19650-3 covers
information production activities in
• W hich of these pathways is followed clauses 5.6 and 5.7
depends on the nature of each life-
• These sub-groups of activities reflect
cycle event giving rise to new or
the overall philosophy described in
updated asset information.
ISO 19650 Part 1 and mirrors the
• These events are called trigger events approach taken in ISO 19650 Part 2 for
and are depicted in pathways B and C information management on projects
by a circle enclosing a pentagon.
• The process has feedback loops at points K
• The pathways are split because there and L.
are fundamental differences in the
approach to information management, • Point K tests whether the appointment
primarily around whether procurement will continue following acceptance
and mobilization can be done ahead of of a particular set of information
the trigger event taking place or not deliverables from the supplier (lead
appointed party/delivery team). This
could be because a trigger event is
complex enough to involve a series of
information exchange points (such as
the design and then installation of an
emergency roof). Or because it is a
call-off appointment responding to a
repeated trigger event where each has
its own information exchange (such as
a 5-year contract to conduct yearly
inspections).
• Point L tests whether the asset owner/
operator still has an interest in the
asset and therefore whether the whole
information management process
should continue.
23 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
4.3 Proportionality
Although the flowchart in Figure 5 looks Some of the specific tasks in ISO 19650-3,
complicated, and each of the process steps such as the lead appointed party preparing
contains a series of required actions, the ISO the delivery team’s BIM execution plan,
19650-3 information management process is are deliberately scaled down from their
to be applied in a way that is proportionate equivalents in ISO 19650 Part 2. If more
and appropriate to the scale and complexity detail is warranted by the situation then this
of the asset portfolio as well as the scale can either be specified by the appointing
and complexity of the asset management party in their acceptance criteria for the
responses to trigger events. Proportionality is tender response or volunteered by the
demonstrated through the following examples: prospective contractor/in-house team (lead
appointed party) in their pre-appointment
Example 1 :In preparing for their overall BEP.
approach to information management in step
1, an appointing party (asset owner/operator) Proportionality also needs to be applied to
might decide only to apply ISO 19650-3 to the organizational and asset information
its most critical assets, such as only to its requirements that are developed by the asset
production and warehouse facilities and not to owner/operator (appointing party). Each
its administrative offices, or only to life safety information requirement must be able to
systems rather than all systems in a building. be traced back to a purpose, so that the
This would be part of the considerations in appointing party is clear that it is only asking
response to ISO 19650-3 clause 5.1.3. for information to be produced that it really
does need. This is part of the lean thinking
Example 2: In procuring a new lead that underpins a systematic approach to
appointed party (asset contractor) to carry information management, and the result
out a condition survey, an appointing party should be sets of exchange information
(asset owner/operator) could conclude that requirements for each lead appointed party
none of its existing reference information or that focus on the information that really
resources are relevant and do not need to be has value to the appointing party. Different
included in the tender pack compiled for this asset owners/operators will have different
appointment. This simplifies the paperwork of ideas of what information is of value to them
the procurement process. – there is no single set of right or wrong
answers to this question because the idea
Example 3: An in-house asset manager of value can mean such different things to
acting as appointing party and appointing different organizations. Even if a particular
an in-house works team to do small-scale asset owner/operator draws on the work of
work and information delivery will still similar types of organization (such as one
need to go through the same information local authority learning from others), they
management process steps. But at each should still approach the development of their
step the details that need to be defined or information requirements with a critical eye.
the resources that need to be created will be
much simpler or might not be relevant and Much more explanation about determining
so can be legitimately excluded. The cost of appropriate information requirements is given
implementing the process will ultimately have in Guidance D.
to be balanced against the benefit of having
the intended information. Unless there is a
statutory requirement to be met, this balance
of cost versus value has to be made by the
appointing party (asset owner/operator).
25 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
This section illustrates three out of the Use Case 2. For portfolios of assets,
potentially infinite number of Use Cases that progressively moving to follow UK BIM
could be used across different asset owners Framework principles on a site-by-site basis.
triggered by different situations. Adoption
and use of ISO 19650-3 allows the appointing This is triggered when projects/interventions
party (asset owner/operator) to adopt a are undertaken on more than a predefined
proportionate approach based upon the costs proportion of the assets on the site. This
and benefits of implementation. prevents ‘small’ projects/interventions, such
as replacement of windows, requiring the
Use Case 1. A single asset/building/facility digitization and surveying of a whole building.
that moves from the project phase (defined
in ISO 19650-2) to the operational phase Where the above threshold is passed, this
(defined in ISO 19650-3). use case would involve digitizing all assets,
documents and information for the site based
This begins before the project is started, with on the Asset Information Requirements (AIR).
definition of what information is needed to In addition to the benefits detailed in Use
manage and maintain the asset/building/ Case 1 above, further benefits would be:
facility. This information is collected during
the project delivery where it forms part of the • Increasing the proportion of digital
project information model (PIM). Effective information across an organization’s asset
transfer of this information from the PIM into stock faster than if digital information
the asset information model (AIM) without about assets was only collected through Use
loss of meaning or accessibility provides a Case 1;
range of benefits: • Increased understanding of the extent to
which assets across whole sites/ facilities are
• Reduced uncertainty about actual assets following UK BIM framework principles;
and systems enabling more effective
• Easier and closer relationship with facilities
intervention planning;
management activities facilitated through,
• Reduced safety risks due to staff making for example, asset tagging and information
unwelcome ‘discoveries’, such as previous maintenance linked to FM contracts.
alterations to assets that had not been
recorded, whilst undertaking asset
interventions;
• Quicker and more effective development of
planned maintenance schedules to ensure
that they are active on asset handover.
This would reduce the risk of failures and
the risk of reducing asset life through
insufficient or incorrect early maintenance.
This would also reduce the risk of
invalidating a warranty by not following the
manufacturer’s requirements;
• More effective and quicker planning and
response to unplanned incidents, such as
fire/ flood/ damage through availability of
more reliable information.
26 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Use Case 3. For portfolios of assets, applying • Enables change in process/ maintenance
UK BIM Framework principles to selected regimes for a complete asset/ site type
asset/site types by surveying existing assets, perhaps including standardized planning
digitizing drawings and records. and activities, common tooling, optimized
training and reduced variability in approach
For example, digitizing all air handling units or leading to greater efficiencies and improved
digitizing all sub-station sites >50kV. This Use asset outcomes.
Case could be applied alongside Use Case 2
or independently. In addition to the benefits These Use Cases are illustrated in Figure 6.
detailed in Use Case 1 above, further benefits In the figure, assets on six different sites are
would be: represented by geometrical shapes. Those
that are subject to work following trigger
• Increasing the proportion of digital events have a bold outline. In Use Case 2,
information across an organization’s asset on Sites A, D and F some assets are subject
stock faster than if digital information to projects/work that is above the predefined
about assets was only collected through Use proportion for digitizing the whole site. In Use
Case 1; Case 3 the pentagon asset has been selected
• Increased understanding of the extent to for survey and digitization. This affects sites
which assets across whole sites/ facilities are A, B and D but only that specific asset on
following UK BIM framework principles; each site is digitized.
Use Case 1
Site A Key
• Shapes represent different asset types
• Blue fill represents digitized assets
• Grey fill represents assets not digitized
• B
old outline represents assets with
planned interventions
Use Case 2
Site A Site B Site C Site D Site E Site F
Use Case 3
Site A Site B Site C Site D Site E Site F
Figure 6: Illustration of use cases for applying ISO 19650-3 process
27 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Figure 7: Trigger events during the operational phase of the life cycle
29 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
• Inspections
CTION
N
o H&S inspection
AC
TA
construct phase to in-use o Planned: scheduled
o Fire safety
IN
INSPE
tasks
Y
NS
RV
o Onboarding: Asset IO
o Reactive -
o Defects/warranty
SU
o Topography
EN
o Utilities survey
EW
D
o Decontamination F replacements
L
N o FM validation survey
O
LI
o Deconstruction FE RE o Space utilisation
o Improvements/
o Demolition upgrades
o Transfer of ownership • Operations (e.g. energy
o Cleaning reductions)
o Utilities o Redecoration
o Waste management • Refurbishment and
o Catering adaption
o Hospitality
o Major refurbishment
o Helpdesk
o Change of use
o Post room
o Alterations or churns
o Security
6.4 W
orked example: 6.4.1 Scenario
Commissioning a survey to • Organization X has a large asset
determine the extent of a portfolio consisting of both buildings and
refurbishment infrastructure.
• Organization X is keen to digitize their built
he section highlights the information
T asset portfolio in a staggered manner and
management process associated with survey utilize the organization’s central repository
activities in preparation to refurbish the asset (CDE) embracing ISO 19650 principles.
within the context of the scenario outlined • Previous survey work has highlighted that
below. This particular trigger is classed as investment is required in the strategic
an unforeseeable trigger, as it is not part of regional centre. The anticipated remaining
a long-term schedule of asset activities. It is building life of the regional centre is 30
hoped to include an example of a foreseeable years. The outline business case to refurbish
trigger (such as a regular maintenance the regional centre has been approved with
activity) in a future update of this guidance. an objective to continue using the building
as a regional centre.
• Organization X now needs to procure
a single supplier to undertake detailed
surveys to support the full business case for
the refurbishment of the existing building.
These surveys will include building services,
structural integrity, asset condition, and
point cloud. The principal deliverable will
be an information model that incorporates
survey information. Due to poor existing
legacy asset data, survey outputs will
provide accurate validated data to inform
the briefing stage of the refurbishment.
• The regional centre is currently occupied
and staff decant commences 8 weeks prior
to the start of refurbishment works.
• Organization X has an asset management
system and computer aided facilities
management system (CAFM) for managing
their asset portfolio.
31 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
6.4.2 A
pplying the clauses of ISO
19650-3
5.1.3 (Relevant Identify critical assets in the regional centre based on existing information held by
assets) the operations team.
5.1.4 (AIR) Specify the information required for each critical asset to support the OIR. Note:
clearly identify that the survey is non-intrusive and there will be limited data
collection for elements with restricted access (such as behind walls). Identify the
methodology for assets with limited information availability.
5.1.5 (Triggers) The foreseeable trigger event is the refurbishment of a regional centre.
Information collected as part of the survey will be managed during subsequent
trigger events including maintenance, fabric/equipment repair, room
reconfiguration.
5.1.6, 5.1.10 Highlight the use of survey information collected: information about system/
(Information component assets that require renewal will be used by the design team to inform
standard and new design strategies while information on existing system/components assets
Enterprise that will remain in situ will be used by maintenance and operations teams. State
systems) the building services survey, structural survey, measured survey, utilities and asset
condition information is to be incorporated in an information model and aligned
to the defined level of information need.
Capture existing enterprise system requirements (CDE, CAFM, etc.) to specify the
asset taxonomies, location hierarchy, classifications to inform the asset information
standard. The information standard should also set out survey accuracy bands,
tolerances, coordinate grid and datum requirements and format of deliverables.
5.1.7, 5.1.8 Clearly identify that there is poor quality legacy information about the regional
(Methods and centre and validation of legacy information is therefore required. Where
procedures, information does not exist within legacy, the survey team will be required to
and Reference collect information in line with the specification in the information standard. One
information) key area for consideration is the interoperability of outputs for onward use such
as exchange between survey packages, so the information production procedures
will encourage use of open standards where possible. Data collection templates,
object library definition to be shared with prospective surveying tenderers.
5.1.11 (Establish Clearly state that survey outputs will be federated to create the refurbishment
AIM) information model (where existing system/component assets are retained as part
of the refurbishment). Methodology for aggregating the information into any
existing AIM needs to be defined.
32 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
5.4 5.4.6 (Complete Consider any changes to the asset information standard and the information
Appointment appointment) production methods and procedures that have been proposed by the selected
survey organization. Incorporate any agreed updates to these in the appointment
documents.
5.5 Make sure that the appointment of the surveyor is finalized so that there is
Mobilization enough time for mobilization activities before the survey work itself needs to start.
5.6 Production This clause has no specific activities or commentary for the appointing party.
of information However, it is essential that the information standard (see 5.1.6) and the EIR
(see 5.2.2) are specific on the data requirements for each type of object to be
collected by the survey and the exchange format expected. Ideally this should
be through the provision of detailed data collection templates and object library
definitions and in a recognized open standard such as BS1192-4. .
5.7 5.7.2 (Accept It is essential to undertake quality assurance checks on each information
Information information container and the object data provided. Assurance checks could use automated
model model) computerized verification against the information standard and EIR and should
acceptance take place before the information exchange is contractually accepted. Utilize the
review comment and accept workflow within the CDE to aid quality assurance
checks.
5.8 AIM 5.8.1 (Aggregate Given poor quality legacy information, survey outputs serve as the most up to
aggregation AIM) date validated data set for the regional centre. Update enterprise systems with
the survey deliverables to ensure any updates are federated within the new
information model for the regional centre.
5.8.2 (Review Compile an AIM maintenance methodology that would support the future
AIM) activities associated with the refurbishment of the regional centre.
33 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Contract Program
Line AIM & PIM Integration Management
Inventory &
Immutable Assured Automated Planning
Information Automated
Container Structured System
Exchange Verification
(File) Store Repository Integration
Cost & Carbon
Reporting
Asset
Performance
Enterprise Systems
Figure 9: A staged approach to Integrating ISO 19650-3 into existing information systems
35 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Example 2: A water and sewerage utility would have separate AIR for its different
asset classes (pumping stations, treatment works, pipeline networks, reservoirs,
administrative offices, etc).
The difference between OIR and AIR is that OIR are focused on the overall
organization whereas AIR are focused on a specific asset or group of assets.
Note: There may be a number of common elements across all the sets of AIR, but also some elements that are
specific to one particular asset
40 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Clause: 5.1.5 Identify foreseeable trigger events for which information shall be managed
The primary party active Insight:
within the clause:
Once the AIR have been established the next activity is to consider foreseeable
Appointing party trigger events.
Contributing parties to
the clause: A trigger event is one that occurs to an asset or affects it in some way. It triggers
n/a the requirement for new or updated information relating to the asset, in line with
its AIR. A foreseeable trigger event is one which can be planned in advance (and
When the activity within which it is sensible to plan for, based on its likelihood of occurring and impact on the
the clause should be organization).
carried out:
Before tendering the first It is sensible to consider separate trigger events as they are likely to instigate an
lead appointed party appointment (and many of the ISO 19650-3 requirements apply at the appointment
appointment level). A trigger event might be a series of separate actions, such as regular
The level of the activity: maintenance of a component during its lifetime, or it could represent a one-off action
such as initial condition survey after acquiring an asset from its former owner.
Asset or portfolio
Example 1: Yearly lift inspections and maintenance. This could be across a whole
building/asset or could be for a sub-set of all lifts (such as passenger lifts) if other
lifts are inspected at different frequency.
Example 2: Flood response survey. For a retail chain, this trigger event would only
apply to the stores (assets) that are in a known flood-risk area. The timing of any
particular flood cannot be known, but the asset owner has judged that it is sufficiently
likely that the planning and on-boarding of an appropriate survey team is worthwhile,
given the rapid turnaround that would be needed in the event of an actual flood
occurring.
Some examples of trigger events are given in ISO 19650-3 Annex A.3, but these are
quite high-level and it is likely that a much more detailed breakdown of trigger events
would be needed.
Summary of activities within the clause (as appropriate):
• Define or obtain a list of commonplace trigger events, that will or are likely to apply to each asset from clause
5.1.3.
• T
hink about particular trigger events that apply to specific assets, perhaps because of where they are located,
what function they fulfil, or what components they contain.
• D
ocument the trigger events and decide which of them will be planned for in advance, and which will be
responded to only when they arise.
41 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
There are some examples of enterprise systems that might exist prior to the
appointing party implementing ISO 19650-3 in Annex A.5. Of course, the precise
nature of which systems exist for a particular asset owner/operator will depend on
their development history as well as which industry sector(s) they operate in.
The workflows for getting new or updated information into the AIM are governed
by the CDE workflow and the details in ISO 19650-3 clauses 5.6 and 5.7. Any specific
requirements around the structure or procedures associated with the AIM should be
explained to the lead appointed parties and their delivery teams through the asset
information standard and the asset information production methods and procedures.
This clause in ISO 19650-3 includes a list of 10 mandatory areas that the AIM
maintenance processes have to cover. These include making sure the AIM continues to
satisfy security requirements, and that AIM ownership and maintenance responsibility
is transferred when there is a change of ownership of the corresponding asset.
The period for which the AIM needs to be maintained is not specified directly in ISO
19650-3. Instead, the clause talks about this being done for “as long as is appropriate”.
Note 1 to this clause explains how this can be interpreted to reflect the period over
which the appointing party has an interest in the asset, including that it can be
affected by legislation or contractual agreements.
Summary of activities within the clause (as appropriate):
• Document the maintenance processes for the AIM, following the topics listed in this ISO 19650-3 clause.
• D
etermine the permissible time lag between alignment of the asset information model with the state of the
physical asset.
44 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Clause: 5.8.1 Aggregate an accepted information model into the asset information model
The primary party active Insight:
within the clause:
This clause is where the appointing party takes active ownership of the information
Appointing party that has been delivered by a lead appointed party and their delivery team, by
Contributing parties to incorporating it into the asset information model.
the clause:
n/a The lead appointed party has authorized the submission of information deliverables,
in the form of an information model, to the appointing party. The appointing party
When the activity within has reviewed the information model and accepted it. The deliverables are therefore
the clause should be deemed to satisfy the exchange information requirements (EIR (ISO 19650-3)). At this
carried out: point the appointing party can then incorporate the information model into the asset
After an information model information model (AIM).
has been accepted by the
appointing party Aggregating the information model involves the asset owner/operator (appointing
The level of the activity: party) incorporating the information containers into the AIM. This may require adding
the information containers into the appropriate enterprise systems or using the
Appointment information containers to update existing contents in the enterprise systems.
It is helpful if as much of this work can be automated as possible, but there might
still be manual tasks to be completed. ISO 19650-3 presumes that these activities are
carried out correctly and the necessary checks are in place to ensure this. It does not
specify what processes and checks have to be applied.
Clause: 5.8.2 Review and continue maintenance of the asset information model
The primary party active Insight:
within the clause:
This clause represents the end of one pass through the information management
Appointing party process at an appointment level. It is the opportunity for the appointing party to ask
themselves whether the AIM is still fulfilling its purpose(s) and is being maintained
Contributing parties to
in accordance with the agreed procedures. If either of these is not the case, then
the clause:
mitigation measures need to be put in place.
n/a
When the activity within
the clause should be Example 1: This clause could trigger a reassessment of the asset information
carried out: requirements (AIR). If new AIR are now identified then this could lead to changes
As part of the close-out of in the EIR (ISO 19650-3) that have been used to appoint existing lead appointed
accepted information being parties. These changes would have knock-on effects on the structure of the AIM
incorporated into the AIM
The level of the activity: Example 2: This clause could trigger an assessment of the maintenance processes,
Appointment and it might be concluded that the alignment frequency of the AIM to the state of
the asset is either too high (more expensive than necessary) or too low (leading to use
of outdated information).
Key:
Activity to be undertaken
Decision point
Information exchange
Sequence flow
*5
.6.5 - See ISO 19650 Guidance C
to understand the CDE in detail
49
Appointing party Lead appointed party Appointed party
Start
Assessment and Need 5.1.1
(19650-3 clause 5.1) 5.1.2
(Establishing the information
framework) 5.1.3 5.1.4 5.1.5
5.1.9 5.1.10
5.1.11 5.1.12
5.1.13
New appointment
Invitation to Tender
(19650-3 clause 5.2) 5.2.1
(Creating information for 5.2.2
tender (for a prospective
lead appointed party)) 5.2.3 5.2.4
5.2.5
5.3.5 5.3.6
Tender response
5.3.7
Selection
Appointment
(19650-3 clause 5.4) 5.4.1 5.4.1 5.4.1
(Finalization and
confirmation of 5.4.2 5.4.3
appointments)
5.4.5 5.4.4
5.4.6 5.4.7
Appointment executed Appointment executed
Mobilization
(19650-3 clause 5.5) 5.5.1 5.5.1
(Getting the delivery team
ready to go) 5.5.2 5.5.2 5.5.2
5.5.3 5.5.3
5.5.4 5.5.4
Production of
Continuation of this appointment
Information 5.6.1
(19650-3 clause 5.6)
(Work in progress and shared 5.6.2
information) Information Information
model rejected model rejected 5.6.3
Shared
information
5.6.5* 5.6.4
5.6.5
5.6.6 Next Information iteration
Information Milestone
Information Model
Acceptance 5.7.1
(19650-3 clause 5.7)
(Reviewing and accepting the 5.7.2
information model)
Appointing party
Start
5.1.1
Appoint individuals to
undertake the information
management function
5.1.2
Establish organizational
information requirements
5.1.9 5.1.10
Establish the common data Establish links to enterprise
environment systems
5.1.11 5.1.12
Establish the asset Establish processes to
information model maintain the AIM
5.1.13
Establish the asset
information protocol
51 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Appointing party
New appointment
5.2.1
Decide the type of activity
providing information
5.2.2
Establish the appointing
party’s exchange
information requirements
5.2.3 5.2.4
Assemble reference Establish response
information and shared requirements and
resources evaluation criteria
5.2.5
Compile information for
the invitation to tender/
request to provide a
service
52 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Invitation
to tender
5.3.1
Nominate individuals
to undertake
the information
management function
5.3.2
Establish the
delivery team’s (pre-
appointment) BIM
execution plan
5.3.4 5.3.3
Establish the delivery Assess task team
team’s capability and Selection
capability and
capacity capacity
5.3.5 5.3.6
Establish the delivery Establish the
team’s mobilization delivery team’s risk
plan register
5.3.7
Compile the delivery
team’s response
Tender
response
Selection
53 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
5.4.2 5.4.3
Establish Establish the
the delivery lead appointed
team’s detailed party’s EIR (ISO
responsibility 19650-3)
matrix
5.4.5 5.4.4
Establish the master Establish the task
information delivery plan information delivery
plan(s)
5.4.6 5.4.7
Complete lead appointed Complete appointed
party’s appointment party’s appointment
5.5.1 5.5.1
Mobilize resources Mobilize resources
5.5.3 5.5.3
Test the project’s Test the project’s
information information
production methods production methods
and procedures and procedures
5.5.4 5.5.4
Maintain resources Maintain resources
in readiness for a in readiness for a
trigger event trigger event
55 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Production of information
(ISO 19650-3 clause 5.6)
(Work in progress and shared information)
5.6.1
Check availability of
reference information and
shared resources
5.6.2
Information
Generate information
model rejected
5.6.3
Undertake
quality assurance
check
Shared
information 5.6.4
5.6.5*
Information model Review information
review and approve for
sharing
Next Information
iteration
5.6.6
Authorize
information model 5.6.5
for delivery to the Review information
appointing model
party
Information
To 5.6.1 Milestone
Information
model rejected
5.7.1
Submit information model
for appointing party
acceptance
5.7.2
Review and accept
the information
model
57 | Guidance Part 3 Edition 2 - February 2021
Operational phase of the asset life-cycle
Continued interest in
To 5.1.1
the asset
Continuation of this
To 5.6.1
appointment
10.0 Summary
The Centre for Digital Built Britain is part of the Construction Innovation Hub programme,
funded by UK Research and Innovation through the Industrial Strategy Challenge Fund.