MAS Overview and Cost Concepts Questionaires
MAS Overview and Cost Concepts Questionaires
(Prelim_Week 1_08-18-22)
Numbers 36 to 38
Machine hours and electricity costs for Britney Industries for 2021 were as follows:
Months Machine Hours Utility Costs
January 4,800 22,080
February 5,568 25,200
March 3,648 16,200
April 5,952 27,600
May 7,296 33,900
June 6,336 26,400
July 7,872 29,700
August 6,720 27,300
September 3,840 18,600
October 7,104 31,200
November 9,024 37,200
December 8,064 33,300
36. Using the high-low method, determine the variable electricity cost per machine
hour
a) 3.87
b) 3.48
c) 3.91
d) 3.51
37. Using the high-low method, determine the estimated fixed electricity costs per
month
a) 2,277.12
b) 5,796.48
c) 1,9167.16
d) 5,525.76
38. Using the high-low method, estimate the electricity costs for a month in which
5,000 machine hours are worked
a) 23,075.76
b) 21,466.16
c) 23,296.48
d) 21,627.12