Loading, transportation and a) Fall of bricks causing 1. Bricks should be stacked in cross
unloading of bricks to site injury. tier in the truck/tractor/ trolley.
2. Speed limit should be observed. Mr.R.A.
3. Use safety shoe.
b) Cut injury due to Bricks should be handled carefully Guttedar.
edges of blocks with gloves to avoid injury.
Preparation of cement mortar a) Improper handling of Training for handling method should
cement bags. be imparted.