Unit Rate Analysis of Adisu
Unit Rate Analysis of Adisu
I. Material cost
Material requirement
Excavation moderately
13 hard rock per m3 3
Fill and compaction
14 per m3 1.3
4 Cart away - M3 1 - - 80 80
G-32 CIS Pcs 0.7 140.00 98
5 CIS walling (roofing) Nail Kg 0.5 40.00 20
perlin m 8 12.00 96
Poles (dia8) m 4 12.00 48
Total 262 101 363
6 Pointing Sand M3 0.02 542.16 10.843125
Cement Bag
0.15 133.94 20.090438
Total 30.9335625 46 77
7 Stone pavement Stone M3 0.34 240.51 81.77425
7 Stone pavement
Sand M3 0.02 542.16 10.843125
Cement Bag
0.15 133.94 20.090438
Total 112.707813 415 528
8 Plastering Sand M3 0.039 542.16 21.14
Cement Bag 0.33 133.94 44.20
Total 65.34 46 111
9 Hard core Stone M3 1.86 240.51 447.35325
sand m3 0.2 542.16 108.43125
cement bag 2 133.94 267.8725
Total 823.657 230 1054
10 RCC (1:2:4) Aggregate M3 0.98 1215.51 1191.20
Sand M3 0.49 542.16 265.66
Cement Bag 6.28 133.94 841.12
R. Bar Kg 156 5.00 780.00
Total 3077.98 920 3998 1.05
12 Lean concrete (1:2:4) Aggregate M3 0.98 1215.51 1191.20 0.2
Sand M3 0.49 542.16 265.66 0.2205
Cement Bag 6.28 133.94 841.12 footing 2
Total 2297.98 696 2994
13 Masonry (in 1:3 mortar) Stone M3 1.32 240.51 317.4765 column 4
Sand M3 0.36 542.16 195.17625 0.25
Cement
Bag 2.3 133.94 308.05338 0.25
Total 820.706125 780 1601 0.25
14 Rip- rap Stone M 2
0.46 240.51 110.63575 115 226 2.3
15 Form works Euc poles m 24 20.00 480 F&c 4.2
Timber m2 1.5 50.00 75 slab 8.25
nail Kg 1 40.00 40 t/concrete 12.5
Total 595 460 1055 cement 78.40
Note: Rate for stone Rip- rap in m3 =232/0.2=1160Birr 66,642.26
Eucalpts 4
5
10 L/No
12.5 1
4 62.5 31.25 let say 40 2
36 Birr 5,800.00 3
33 Timber 40 pcs 4
15 birr 20,800.00 5
84 masonary 30 6
420 35 15 19.8 7
0.2 birr 18,473.40 8
0.8 sand 5.4 9
1 birr 5,038.20
cement 34.50
L/No
1
2
3
4
5
6
7
11 Rebar for 11 55 275
5 slab 5 25 300
0.15 T/Length 575
8.25 T/Berga 47.92
57.75 55,343.75
57,500.00
rebar for 9
column 4.3 38.7 3.225
38.7 12.9
154.8 60.82 T/Berga of slab & footing
23994 81,494.00
4 83,774.00
20 Birr 85,401.50 BIRR
Rebar fo 180
stirrups 180
15
Birr 2280
Rebar for 1.4
footing 14
126
10.5 71.32 T/Berga of Dia12 rebar
Birr 1627.5 85 T/Berga of Dia6 rebar
0.2
1.8
150 82500
Total Birr
cement 78.40266 112.90
sand 6.117405 11.5 10,745.74
21.59734 18,357.74 Agregate 12.23481 12.2 11,415.08
Stone 19.8 19.8 18,473.40
Timber 40 40 20,000.00
Eculpts 40 40 5,800.00
Total rebarDia6 15 2,325.00
Total rebar dia6 85 98,600.00 98,600.00
Rebar Total Birr 100,925.00
Total Cement 112.90 Total Birr 101,612.39 2325
Total Birr 95,967.26 Let, Excav 100,000.00 100,925.00
Total Stone Birr 18,473.40 368,971.61
Material List Qty Unit Rate Amount
Stone 15 M 3
933 13,995.00
Cement 110 Bags 900 99,000.00
Aggregate 12 M3 933 11,196.00
Sand 12 M3 933 11,196.00
Rebar/12 81 Berga 1160 93,960.00
Rebar/6 35 Berga 160 5,600.00
Timber 40 No 510 20,400.00
Eculpyts 35 No 150 5,250.00
Nail 6 KG 150 900.00
Total Amount 261,497.00