BUILT-UP RATES

PROJECT: THE APPOINTMENT OF CONTRACTOR FOR ITEM :


CONSTRUCTION OF EARTHWORKS AND INFRASTRUCTURE
WORKS FOR CADANGAN PEMBANGUNAN KAWASAN CLOSED TURFING
PERINDUSTRIAN LEMBAH CHUPING (KPLC) / CHUPING
VALLEY INDUSTRIAL AREA (CVIA) PHASE 1, PERLIS FOR
NORTHEN CORRIDOR IMPLEMENTATION AUTHORITY
(NCIA)
DESCRIPTION UNIT RATE (RM)

Close turfing complete with top soil on sloping surface.


m² 7.95

OUTPUT(RM)
DATA

Cow Grass = RM 5.00 /m2


(Daywork Schedule for Material, item 32)

1.5 tonne Truck = RM 660.00 /day


(Daywork Schedule for Plant, item 33)

Backhoe CASE = RM 600.00 /day


(Daywork Schedule for Plant, item 14)

Labour required for installation = 1 Semi-skilled Labour


Labour required for installation = 1 Labour

Rate for Semi-skilled Labour = RM 120.00 /day


Rate for labour = RM 100.00 /day
Labour constant for installation = 0.05 hr/m²

A. MATERIAL COST

1) Cow Grass
Cow Grass = RM 5.00 / m²

Total material cost/m² RM 5.00 / m² 5.00 /m²

B. PLANT & MACHINERY COST

1) 1.5 tonne Truck = 0.01 hr /m² x RM 660.00 /day 0.83 /m²


8 hrs/day

2) Backhoe CASE = 0.01 hr /m² x RM 600.00 /day 0.75 /m²


8 hrs/day

C. LABOUR COST

1) Semi-skilled Labour = 0.05 hr /m² x RM 120.00 /day 0.75 /m²


(Daywork Schedule for Labour, item 22) 8 hrs/day

2) Labour = 0.05 hr /m² x RM 100.00 /day 0.63 /m²


(Daywork Schedule for Labour, item 20) 8 hrs/day

7.96 /m²

7.96 /m²
TOTAL COST
say 7.95 /m²

bur/closed turf./1