SAUDI ARAMCO CONTRACTOR INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Inspection of Support Foundation Prior to Structural or


SAIC-M-2006 03-Apr-22 MECH-
Equipment Installation
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME

SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. General Requirements

Location, orientation, elevation and conditions of support foundation 12-SAMSS-008


A1
conformed with Project plan drawings. (PIP STS05130, Par. 6.2.10) Sec. 1

The top of concrete foundation shall be a minimum of 150 mm above


SAES-Q-005, sect.
A2 finished grade. (Note: Not applicable to instrument stand pipe or
4.3.2 (a)
pedestals inside buildings not subjected to washdown water.)
Concrete foundation has reached the curing period up until the
SAES-Q-001
A3 compressive strength has reached 70% of the specified strength, but
Sec. 7.25.3
not less than 7 days after placement. Approved by Insp

All column base plates have a minimum of four anchor bolts. SAES-M-001, sect
A4
Note: This excludes posts that weigh less than 300 lbs/136 kg. 7.1.9(a)

Leveling shims are installed with a minimum top elevation of 25 mm


SAES-Q-005, Par.
A5 from the top of concrete foundation to bottom of steel base plate. This
4.3.2(c)
is to allow a minimum thickness of 25mm of non-shrink cement based
Top elevation of leveling shims conformed to construction drawing
A6 IFC Drawings
elevation plans. Hold Points are installed as necessary.

Top of concrete has been roughened (Std. Dwg. AA-036322-001) or


chipped with hammer to remove laitance, oil-soaked or damaged
concrete to the level of sound concrete or to a minimum of the top 1 SAES-Q-001,
A7
inch (25 mm) of concrete. (PIP STS-03600, Para. 6.2.1.1 for Non- Sec. 3
Shrink cement grout, & STS-03601, Para. 6.2.1.1 for epoxy grout)
Sharp concrete edges are ground down (proper bearing).
The top of bearing surfaces and the bottom of base plates shall be
12-SAMSS-008
A8 cleaned and shall set the shim column base plates to correct positions
Sec III B
elevation and locations as showm on erection drawings. (PIP
B. Dimensional Checks on Anchor Bolts

Anchor bolt diameter conforms with the Equipment/Structure detail


SAES-Q-005,
B1 drawing.The minimum anchor bolt diameter shall be 20 mm (¾"),
Para. 4.8.5
except when specified.
Thread length and bolt projection of anchor bolt comformed with the
dimensions indicated in Std. Dwg-AA-036322, Rev 08. SAES-Q-005,
B2
(Note: Actual projection length should allow for complete thread Para. 4.8.1
engagement after considering the thickness of grout & baseplate.)
Number of bolts matches the number holes on the equipment Equipment IFC
B3
/structure. Drawing

Anchor bolt spacing and bolt circle diameter matched the actual bolt Equipment IFC
B4
holes of the equipment/structure base plate. Drawing
Minimum clear distance from anchor rods or anchor rod sleeves to
edge of concrete shall be 100 mm. Additionally, the minimum edge
distance for design purposes measured from the centerline of the SAES-Q-005
B5
anchor rod to the edge of the concrete shall be as specified on Para 4.8.8
Mandatory Standard Drawing AA-036322-001. Metallic anchor rod
sleeves are not permitted

Saudi Aramco: Company General Use


Saudi Aramco: Company General Use
#
#

Variation in dimensions between the centers of any two anchor bolts


within an anchor bolt group shall be equal to or less than 1/8" (3mm). 12-SAMSS-008
B6
(AISC Code of Standard Practice for Steel Buildings and Bridges, Sec III B
Para. 7.5.1a and PIP STS05130, Para. 6.2.1)
Variation in elevation of the tops of anchor rods shall be equal to or
12-SAMSS-008
B7 less than plus or minus 1/2" (13mm). (AISC Code of Std Practice for
Sec III B
Steel Buildings & Bridges, Par. 7.5.1c & PIP STS05130, Para. 6.2.1)
C. EVALUATE ANCHOR & TEMPLATE CONDITION AFTER CONCRETE PLACEMENT (PROCEDURE ITEM ... CPI REQUIREMENT)
Setting and securement templates used to secure anchor bolts during
concrete pouring used sturdy, thick coated plywood templates
(Structural pedestals) & steel templates (Equip, Vessels)
A) Template restricted anchor movement (Hole clearance minimal).
BEST
B) Securement (template to anchor) was per nuts & washers.
PRACTICE
C) Anchor ends were fully taped (Concrete spatter prevention).
C1 Cost Savings
TEMPLATE CONDITION/DIMENSIONS CHECKED. OK TO REUSE.
& Good
FINAL RESULT = ANCHOR & ALL THREADS ARE UNDAMAGED.
Workmanship
1. Remove tape used that covered anchor threads during concrete.
2. Remove any concrete spatter that is stuck to threads & anchors.
3. Spin a nut to check anchors & suspect areas (damaged thds)
4. Perform req'd thread & galvanized coating repairs. See 3 Notes.
REMARKS:
' Support foundation is released for structural or equipment installation
' Support foundation is not released for structural or equipment installation.

NOTES: Use the Attachment for any Galvanized repairs


1. PERFORM ANY REQUIRED GALVANIZED COATING REPAIRS BEFORE INSTALLATION PER SAIC-M-2004 ATTACHMENT PROCEDURE.
2. THREAD DAMAGE (MASHED THREADS, ETC) IS CAREFULLY REPAIRED (MINIMIZE GALVANIZE REMOVAL) USING A KNIFE EDGE FILE.
3. NUTS SPIN FREELY & PROPERLY AFTER REPAIRS. PERFORM "COLD" COATING REPAIR OF REPAIRED THREADS. CURE. NUT TEST.
REFERENCE DOCUMENTS:
1- SAES-M-001 -- Structural Design Criteria for Non-Building Structures, 8 March 2017
2- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures,18 February 2018
3- SAES-Q-005 -- Concrete Foundations,01 January 2018
4- PIP STS03600 -- Nonshrink Cementitious Grout Specification, June 2002
5- PIP STS03601 -- Epoxy Grout Specification, October 2001
6-12-SAMSS-008 -- Erection of Structural and Miscellaneous Steel, 25 Dec 2014
7- PIP STS05130 -- Erection of Structural and Miscellaneous Steel Specification, February 2002
8- AISC -- Code of Standard Practice for Steel Buildings and Bridges, 7 March 2000
9- IFC Drawings (Plan Drawings and Structural or Equipment drawings)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED