Training PPT Earth Work
Training PPT Earth Work
EARTH WORK
By : QC Team
Date : 23.02.2019
Topics
Earthwork
Scope in Project
Method Statement at a Glance
Men
Material
Machinery
Methods
IRF Process
EARTHWORK
Earthwork is define as all operation involved in the Excavation, removal and
satisfactory filling (compaction) of earth, soil and rock.
Embankment is the bottom layer of Subgrade.
Refer to MORTH Section 300 for Embankment Filling Activity
Scope in Project
At Grade portion is 18 +930 to 20 +170
Approx. Filling material Qty is 1.5 – 2.0 Lakh cum
Height of embankment filling is upto 7 mt.
Men
Construction In Charge :
Over all in charge of Filling activity; included but not limited to
- Material laying and compaction
- IRF raising and closing
- Co ordination with GC Engineer , Sub contractor, Designer, other team
- All Records keeping
Quality In Charge :
- Implementation of Method Statement
- Testing of FDD and obtain approval
Survey In Charge :
- Taking level and maintain record
Safety Officer:
- Safety aspects during the activity
Material
The material used in Embankment shall be soil, murum, gravel, a mixture of
these .
It shall be free from logs, stumps, roots, rubbish & any other material
detrimental to the stability of structure
Size of coarse material should be less than 75 mm
Requirement of Soil Property tested as per IS 2720
Test Requirement
Free Swelling Index <50%
Liquid Limit (LL) <50 %
Plasticity Index (PI) <25
% % % % % % % % % % % % % % gm/cc % %
As per MORT&H Requirement
<50 - - - - - - - - - - <50 - <25 >1.65 - -
Soil/027/Pit Borrow
19+750 14 100 100 100 68.27 45.06 24.34 10.42 31.73 57.85 10.42 34.80 25.40 9.40 1.89 13.00 17.94 Embankment
No 01 Area Soil
Soil/027/Pit
19+755 8 100 100 100 65.42 42.61 26.40 16.41 34.58 49.01 16.41 37.50 28.60 8.90 1.830 12.00 15.99 Embankment
No 02
At Grade
Soil/027/Pit
22/12/2018 19+780 From 19+720 10 100 100 100 68.74 47.83 29.48 15.98 31.26 52.76 15.98 35.00 27.70 7.30 1.870 14.00 16.28 Embankment
No 03
to 19+920
Soil/027/Pit
19+800 18 100 100 100 79.48 51.70 25.06 11.66 20.52 67.82 11.66 39.90 29.30 10.60 1.780 13.00 4.09 Embankment
No 04
Soil/027/Pit
19+850 9 100 100 100 74.78 52.46 30.24 20.18 25.22 54.60 20.18 38.80 29.40 9.40 1.780 12.00 4.36 Embankment
No 05
Average of Results 12 100 100 100 71.34 47.93 27.10 14.93 28.66 56.41 14.93 37.20 28.08 9.12 1.83 12.80 11.73 Embankment
Machinery
Tripper
Dozer
Roller (At site, used15 Ton roller )
Water Tanker
Survey Instrument
Lab Equipment for FDD and Moisture test
Methods
1. Survey and Setting out Works :
• After site clearance, all the demarcations will be set out for Centre line , alignment line ,row
line
2. Clearing and Grubbing
• Cutting, removing and disposing all materials such as trees , bushes ,stumps, roots, unstable
rock ,organic soil which are not suitable for embankment
• After clearing and grubbing, the surface to be inspected by GC Engineer, if required
samples from ground level can be kept for any future test
3. OGL Level Inspection
• After clearing and grubbing, the surface to be inspected by GC Engineer
• Samples from ground level can be kept for any future test
• Level for the profile to be taken by surveyor and GC Engineer jointly
4. Laying of Material
• The limits of embankment may be marked by fixing batter pegs or lime spread lines on both
sides as regular intervals as guides before commencing the earthwork.
• The fill material will be delivered to site by tippers / dumpers from approved borrow area
• Initially pockets of undulations if any shall be filled in layer of 250 mm and will be compacted.
• Then materials shall be spread above the profile layer, in a layer of uniform thickness not
exceeding 250 mm compacted thickness over the entire width.
Methods
4. Laying of Material
• If any bolder more than 75 mm size, roots etc found shall be removed.
• Material shall be spread uniformly with the help of motor grader.
• Moisture to be maintained for Compaction should be with +1% to -2% of OMC.
• If material is too wet , it shall be dried by aeration and exposure to sunlight till the moisture is content is
acceptable for compaction to sunlight and dry before compaction
• If material is dry water shall be sprinkled from water tanker to apply uniformly with a controllable flow
rate.
o Speed of the roller shall be maintained uniformly (not exceeding 5KM/Hr.) during rolling.
Methods
4. Laying of Material
• After compaction , level to checked and recorded
• Density shall be checked for evaluation of compaction results. Requirement as
follows
• Field Density > 95% x Material Dry Density
• Minimum 10 Samples to be taken for 3000 Sq.mt area across the profile.
• All testing and records shall be maintain as per specification and as per ITP.
• If the desired compaction achieved , next layer shall be fill and test as per
above same work sequence and test frequency.
5. Drainage arrangement
• Suitable drainage arrangements shall be provided to the Embankment to
reduce the infiltration of water
• Aggregate Type B (Size 40 mm -20 mm) can be used
Methods
4. Laying of Material
• After compaction , level to checked and recorded
• Density shall be checked for evaluation of compaction results. Requirement as
follows
• Field Density > 95% x Material Dry Density
• Minimum 10 Samples to be taken for 3000 Sq.mt area across the profile.
• All testing and records shall be maintain as per specification and as per ITP.
• If the desired compaction achieved , next layer shall be fill and test as per
above same work sequence and test frequency.
5. Drainage arrangement
• Suitable drainage arrangements shall be provided to the Embankment to
reduce the infiltration of water
• Aggregate Type B (Size 40 mm -20 mm) can be used
FDD Test
Process Flow Chart: Embankment Filling Activity
Approved
Compaction
Level Checking
Compaction >95%
Next Layer
IRF Process
Sl No IRF Activity Document Required to Close the IRF
1 Inspection of OGL 1. Check the Clearing and Grubbing Pics of the Ground level
2. Collection of Rock /Soil Sample Sample card if sample taken
3. Take the Level at OGL Level Sheets/Records
2 Profile Preparation Profile prepare (if loose soil found) FDD measured sheet
3 Inspection of 1st Layer 1.Take the level of the Layer Level Sheets/Records
2 Check field Density FDD measured sheet
4 Same repeat for next layer Same as 1 st layer Same as 1 st layer
** IR will be raised by Execution team and will inform to Quality and Survey Team for
Testing and Level taking