01 - Method Statement For WTG Foundation
01 - Method Statement For WTG Foundation
WTG FOUNDATION
THIS DOCUMENT IS INTENDED FOR USE BY GUL AHMED ELECTRIC PVT LIMITED AND ITS
NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND SUPPLIERS.
ORIGINATOR:
HYDROCHINA INTERNATIONAL ENGINEERING COMPANY LIMITED
Page 1 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
REV. DATE ORIGINATOR REVIEWED APPROVED DESCRIPTION
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 2 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
3. RESPONSIBILITIES
4. PROCEDURE
4.4 Curing
4.5 Backfilling
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 3 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
1. SCOPE
The object of this method statement is to provide guidelines for WTG foundation
construction work and to define the inspection activities. The construction method might be
adjusted if necessary.
2. DEFINITIONS
• ACI American Concrete Institute
• HSE Health, Safety and Environment
• SM Site Manager
• CM Construction Manager
• SE Site Engineer
• PPE Personal Protective Equipment
• QIP Quality Inspection Plan
• AASHTO American Association of State Highway and Transportation Officials
• ASTM American Society for Testing and Materials
• BS British Standards
3. RESPONSIBILITIES
It is the overall responsibility of SM to organize resources to perform construction
activities as per project specification, in compliance with quality, schedule & safety
requirements.
It is the responsibility of CM that construction activities are executed according to the
relevant project specification, in compliance with quality, schedule & safety requirements.
The relevant SE and supervisor shall ensure that all the work, conducted in accordance
with this method statement and project specification.
The QC Engineer shall ensure that all work is executed according to IFC Drawing &
Specification and check the quality of work also the documents shall be prepared and
signed as per QIP protocol.
4. PROCEDURE
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 4 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
I. Quality Inspection Plan
Quality Inspection Plan (QIP) with project requirements shall be made and inspection
activities shall be recorded on the formats as per approved QIP.
II. Inspection with protocol of (Witness) will be sign by OE/Client and with protocol of
(Reviews and Surveillance) will be sign by EPC.
Page 5 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
Hydraulic jack capacity will not be less than 500Kpa.
Maximum settlement should not be more than 10% of diameter of loading plate.
Embedded items will be installed as per IFC drawing. Embedded items installed before
lean concrete or shall be designated by Engineer.
Levels and co-ordinates will be checked with the help of Dumpy level machine and Total
Station whichever is suitable.
Lean concrete will be placed with required thickness and levelled.
Three days water curing of the lean concrete will start after final set of the lean concrete
or approved curing compound will be applied.
Embedded Items/Anchor Cage /Base Ring installation will be done according to
designer's instruction and IFC drawings.
Layout will be done on lean concrete.
Rebar will be protected from rust by rebar placed on top of a raised non-metallic platform,
such as wooden planks because the ground and concrete items absorb moisture and can
lead to rusting. Cover the rebar with a thick protective tarp and secure it with cinder
blocks (or something similarly heavy) at the corners and edges.
Bottom rebar fixing will be done as per IFC drawing.
Earth strip which will within foundation will be arranged and laid according to IFC
drawings.
Top reinforcement and other reinforcement will be fixed as per IFC drawings.
Cable conduit pipe will be arranged according to IFC drawings in during top layer rebar
fixing.
Other reinforcement will be laid according to IFC drawing.
During rebar work, formwork will start and will be completed after all rebar work
complete.
Before formwork fixing releasing, agent will be applied.
If some minor gapes appear between two steel plates that will be filled by using foams.
Gaps in shutter must be closed out to minimize the loss of concrete grout.
Temperature sensors will be fixed in foundation at position as mentioned in drawing.
Brace the end adequately support all forms so as to maintain the desired position during
and after the placing of concrete and build sufficiently tight to prevent from mortar
leakage.
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 6 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
Before pouring the concrete, a final survey for Embedded Items/Anchor Cage/Base Ring
(level and alignment) and foundation will be done and approved by Client.
After written approval of RIT (request for inspection & testing), concrete pouring will be
started from one side with a concrete layer not exceeding than 300 mm properly
compacted (vibrated) and will be completed in one go (monolithic).
The concrete shall be transported to site in transit mixers immediately after mixing and
shall be placed within 90 minutes of the water being added.
After placing, compaction shall be done thoroughly around all reinforcement, embedded
fixtures and internal corners and forms with internal vibrators according to the procedure
conforming to project specifications or codes. The personals using vibrators for
compaction should be skilled.
Concrete shall not be dropped freely from a height of more than 2 meters, In case where
an excessive drop is inevitable the contractor shall provide spouts, down pipes, chutes, or
side part to forms with pockets which will protect concrete from segregation.
Concrete temperature will be measured and maintained to as low as possible, however
shall not higher than 32 degree as per ACI requirement.
Concrete placing slump will be as per specified 180±30 mm for pump concrete.
For all concrete sampling & testing please refer QIP. 2 cubes will be casted from each
25m3 concrete.
Great care will be taken while pouring of concrete for pedestal so that Anchor cage level
and alignment should not be disturbed.
Concrete finished surface will be levelled with steel trowel to get surface condition as per
specified.
After 48 hrs. of concrete placement, stripping of formwork will be done.
Bitumen compound coating will apply right after removal of formwork.
If some major damage or defect exists, conduct inspection of the location jointly with
Client and submit the proposed method statement for performance of repairs and get it
approved in written before commencing such repairs.
Earthling strips around the foundation should be correctly connected and arranged as per
IFC drawings.
V. Curing
Surface will be properly cleaned with hand brush and repaired before applying of
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 7 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
Bitumen Compound.
Water Curing will be continuing for 7 days.
Approved Bitumen basis curing compound will be applied immediately after final set and
make sure the surface in not dry before application.
Concrete samples will be transferred from site to QA/QC lab within 24 hours.
Concrete samples will be cured with water and covered with hessian to prevent from dust.
Concrete cubes will be cured in dedicated water tank of sufficient capacity near QA/QC Lab
V1. Backfilling
Backfilling will be started after 7 days of pouring of the foundation. Backfilling material
will be approved by the Client. Backfilling will be done layer by layer, with each
compacted layer of 150 mm thickness and achieved the designed compaction ratio.
Backfilling can be started after satisfactory cube crushing results are achieved in site lab
and approved by Client/OE.
5. Equipment
1. Two Concrete pumps
2. 7 Vibrators (including 2 for standby)
3. 6 to 10 Transit Mixers
4. Chiller Plant of sufficient capacity
5. 2 batching plant, each of 30 m3 capacity
6. Crane & Bucket/Pump (Standby)
7. Lab Tools for sampling & testing
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 8 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020
Bitumen Coating BS 6949
Curing Compound ASTM C309
Steel Rebar ASTM 615A/615M
Concrete Mix Designs ACI 211.1
Slump Test ASTM C143/ BS 1881
Making, curing and compressive strength of concrete specimens
BS 1881.
Soil classification AASHTO M145
PI of Soil AASHTO T89, T90
MDD (Proctor Test) ASTM D1557
Field density Test ASTM D1556
Plate Load Test ASTM D1194 / AASHTO T135
DOCUMENT TITLE
PROJECT No.
Method Statement for WTG Foundation PKGL
Page 9 of 9
DOC No. PKGL-Q-MS-001 PROJECT NO. PKGL REV.01 DATE: 10-Oct-2020