Tawazun Industrial Park Tawazun Industrial Park Abu Dhabi, U.A.E
Tawazun Industrial Park Tawazun Industrial Park Abu Dhabi, U.A.E
Tawazun Industrial Park Tawazun Industrial Park Abu Dhabi, U.A.E
Inspection/
Verifying Documents/
Activity No.
Verification
Demonstrated Evidence
Activity/Description Frequency Specification Criteria
CAPITAL
Report Checklist
KABRI
(Reference Number)
1 Approval/Preliminaries
Preparation of: H H
Material approval Via MA
1. Material Approval
1.1
2. Drawing Approval
Prior to starting the work Approved for construction H H Via DS
Quality control procedure H H Via QCP
3. Quality Document
2 Material Inspections
Material inspection at site Upon Arrival of the material in Approved Material Submital H R MIR - Material Inspection
2.1
Storage the Site Project Specification section H S Report
3 Installation
5 Documents Review
sign and approved H R
Test certificates ( if applicable)
Upon submission of From third parties H R Via IR
5.1 Inspection Test report
Documents sign and approved H R Via IR
Electrical Identification
sign and approved H R
Legend: H- HOLD FOR INSPECTION / W- WITNESS INSPECTION / S-SURVELLANCE INSPECTION / R- REVIEW / CL-CHECKLIST
Note: Particular ITPs to be prepared and submitted along with Method Statements ahead of site activities.