Operational Management Assignment
Operational Management Assignment
Question 3:
3. The company wants to implement the new project. The following are the
activities required to complete the project, the precedence relationship of
the activities and the activity estimates (in weeks) also given as below.
Draw the network diagram; determine the earliest and latest activity times,
the expected time of completion, standard deviation, and the probability
that the project will be completed in 40 weeks or less.
Answer:
M 1 2.5 7 3 1 1
G 1 1 1 1 0 0
H 2 2 2 2 0 0
K 5 8 11 8 1 1
Note:
Te = (to+4tm+tp)
6
2
Vt = Tp-to
1. Network diagram
C
2 4
A
1 D 9
11
3 F,1
A
5 6
E
7 8 10
G H
3
3,12,15
A completes C completes
5,8,17
4,7,10 B&D completes
Starts
F & I completes
1,1,1,
Calculation of Variance
4 1
26.6
13.17 C 7 26.67 D 37
13 26.6
13.17 .50 7 26.67 10.33 37
4
13.1
0 A 7 1
13.1
0 13.17 7 37 I 45.5
9 37 8.5 45.5
27.3
13.17 B 3
22.83 14.17 37 1
45.5 M 49.33
0 0 1
Variance = 11weeks
Then,
Z = D + te
SD
S=(40-49.33)/3.31
=-9.33/3.31
=-2.82
=>0.24%
************
Question 8:
Operations times of servicing of Washing Machines are given below. The first
operation involves cleaning in Machine 1 and the second operation involves
oiling in Machine 2.
a. Determine a sequence that will minimize the total completion time for
this group of jobs, following Johnson’s Rule.
b. Construct a chart of the operations of the jobs at the two work centers
and determine idle time of each line, assuming no other activities are
involved. Processing times (Hrs.) is as follows:
JOBS :A B C D E F
Machine 1 : 5 4 8 2 6 12
Machine 2 : 5 3 9 7 8 15
6
Answer:
Johnson’s Rule:
The object of this method is to minimize the total elapses time by n jobs.
a. Finding sequence that will minimize the total completion time for
this group of jobs, following Johnson’s Rule.
Step 1 :
Select the minimum processing time out of all the available values of
processing times, break the tie habitability and Select them.
Step 2:
Step 3:
Now eliminate the job which has already been assigned from further
consideration and repeat step 1 and 2 until an optimal sequence is found.
D A C E F B
b. Construct a chart of the operations of the jobs at the two work centers and
determine idle time of each line, assuming no other activities are involved.
Processing times (Hrs.) is as follows:
JOBS :A B C D E F
Machine 1 : 5 4 8 2 6 12
Machine 2 : 5 3 9 7 8 15
8
*******************************************************