Modeling and Analysis of RBTS IEEE-6 BUS System Based On Markov Chain
Modeling and Analysis of RBTS IEEE-6 BUS System Based On Markov Chain
net/publication/284481941
Modeling and Analysis of RBTS IEEE-6 BUS System Based On Markov Chain.
CITATION READS
1 2,682
2 authors:
All content following this page was uploaded by Vijayalaxmi Dharwad on 24 November 2015.
Abstract— Modern facility is incredibly vast and extremely tough to keep up. The reliability evaluation of the ability system is
additionally very complex and extremely tedious task. Whole power grid is separated in to generation, transmission and distribution
systems. In this work we are concentrating solely on the reliability analysis of the generation system. There are various methods are
available to judge the reliability of the generation system. These methods are differing in time consumption and technology.
Compared to simulation method Markov method has more advantages. In Markov chain and Frequency and Duration of system,
transient and steady-state probabilities are calculated using RBTS IEEE-6 BUS System.
Keywords— Reliability, Adequacy, Generation model, Load model, Risk indices, Markov chain, Frequency and Duration of states,
De-rated states.
INTRODUCTION
The reliability evaluation of whole power system is very tedious task. The reliability evaluation of whole power system is sub divided
into system security and system adequacy. Security of the system deals, the response of the system to the dynamic perturbations which
are arising within the system. Adequacy of the system deals, the ability of sufficient energy from the generating units to meet the load
requirement.
In the practical, during dynamic perturbations, the response of the power system is not easy to identify. Therefore in this work we are
concentrating only on the adequacy assessment of the power system. The power system is sub divided in to three functional zones to
evaluate the reliability of the system. The functional zones are generation facility, transmission facility and distribution facility. Using
these functional zones the power system is again divided in to three hierarchical levels as shown in figure 1[1][2][3].
In figure 1 the HL-I deals, the reliability evaluation of only generation system. HL-II deals, the realibility evaluation of the both
generation and transmission sysytems. HL-III deals, the reliability evaluation of the generation, transmission and distribution systems.
In this work we are concentrating on the reliability evaluation of the generaion system (HL-I).
Adequacy assessment of the generation system deals, the performance of the generating units to meet the required load demand under
constraints. In the adequacy assessment the Generation system and the peak load demand is considered. The conductor line is ignored
during this assessment as shown in figure2 [1][2][3]
686 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
GENERATION MODEL
There are many methods to create generation model. Adequacy assessment is sub divided into deterministic approach and probabilistic
approach. The deterministic approach does not consider all kinds of perturbations in the analysis compared to probability approach
[4][5]. Probability approach is sub divided into Monte Carlo simulation and analytical method. Monte Carlo simulation requires more
time and it is slow convergences compared to analytical method [6][7]. Therefore during this work we have a tendency to
concentrating solely on analytical ways.
In conventional method adequacy assessment of the generation system is carried out by creating capacity outage probability table
(COPT). COPT is created by using generating capacity units and Forced Outage Rate (FOR) of generating units. In analytical method
Markov process is explained. It will be explained in section III [8].
LOAD MODEL
Load model is created by using daily or monthly or yearly peak loads with respect to time in seconds or minutes or hours as shown in
figure 4. Where Qk is the outage capacity and tk is the time at outage of unit k [1][2][5].
687 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
RISK MODEL
Risk model is to find the risk indices such as LOLE, LOEE, EENS, Frequency and duration of system etc. In this work we are
concentrating on the Frequency and Duration of states, transient and steady state probabilities.
Where,
m=MTTF=1/ λ
r=MTTR=1/ µ
T=MTBF=m+r=1/f
And
Availability=m/(m+r)=m/T=1/ λ T=f/ λ
Unavailability=r/(m+r)=r/T=1/T µ=f/ µ
MARKOV CHAIN
Markov chain is one of the analytical methods which are used measure the reliableness of the facility system. A Markov process has
simplest modeling approach, converges, applicable to modeling of complicated system.. Therefore In this work Markov chain is used
to appraise the reliableness of the generation system.
Markov chain is used to examine the future probabilities of the system. It does not depend on the past history data of the system or
memory less system. The probabilities of the system are carried out using the present data of the system. Using these results we can
predict the behavior of the system in future also used for extension of the power system. Therefore Markov chain is widely used in the
all engineering applications [10][12]
In markov chain the reliability is calculated using FOR (Forced Outage Rate), which is known as un-availability (U) and it is given by,
688 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
A=1-FOR
Where,
A= unit availability λ = unit failure rate
µ =unit repair rate U =unit unavailability.
Markov model is represented in terms of number of states and its state transitions. The two-state markov model is shown in figure 6.
Where state 1 represents the unit is in upstate and state 2 represents the unit in down state.
From figure 6 we can obtain the steady state values for probabilities of each state. Using these values we can predict the behavior of
the system. The steady state probabilities can be written as [11][13],
P1=Pup, P2=Pdown.
(eq-2)
Where,
A= unit availability
Qi= unit unavailability of unit i
Qp= unavailability of parallel units
λp =failure rate of parallel units.
The equations of state probabilities are, P1+P2+P3+P4=1
689 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
(eq-3)
In general,
Where
Using the transition matrix several reliability indexes is obtained like the chances of every state with relation to time, the system
steady state probability, and MTTFF are quickly obtained. These results will be used in the operation, maintenance and programming
of power grid in line with the various interval of Δt.
(eq-4)
Where,
ko, k1,k2… are coefficients depend on the equation and initial conditions.
(eq-5)
CASE STUDY
The adequacy assessment is carried out by using RBTS IEEE-6 BUS SYSTEM. The single line diagram of RBTS system is shown in
figure 7. The generation system data is shown in table 1 and load demand is shown in figure 8 and figure 9 [9].
690 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
SIMULATION RESULTS
The Markov model for IEEE 6–BUS SYTEM is shown in figure 8. In this system we are considering one component at bus 1
and second component at bus 2. Therefore IEEE 6-BUS SYSTEM is represented as TWO-COMPONENT MODEL. Failure rates of
the two components are λ1 and λ2. Repair rates of the two components are µ1 and µ2. Using (eq-2) the values of failure and repair
rates are calculated and is given below,
λ 1= 2.3182e-4/hr µ1=2.3214/hr
λ2=1.141609e-4/hr µ2=38.0517/hr
691 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
Substituting all these values in eq-4, we obtain probability of each state with respect to time, are TRANSIENT PROBABILITIES or
SHORT TERM PROBABILITIES.
P1= 0.9995
P2=9.985e-5
P3=2.98e-6
P4=2.98e-10
692 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
OR
Frequency and duration of the each state is calculated from (eq-1) as shown in table 4 and table 5
Table 4: Frequency and Duration of states
693 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
DE-RATED STATES
There are six-units in Two-components, therefore there will be 2^6= 64 states. The Markov model is obtained by considering de-rated
states. It is shown in figure 13 all the state transitions have not shown in the figure13.
Fig 13: Markov Model of the generaion system by considering De-rated states.
The Steady-State Probabilities of each state of Markov Model of the generation system by considering De-rated states are,
STATE PROBABILI STATE PROBABILIT
NO TY NO Y
694 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
CONCLUSION
The modeling and analysis of IEEE-6 bus system using Markov model has resulted that the probability of acceptable states is
decreasing as time scale is increases and probability of unacceptable state is increasing as time scale is increases in figure 9-12.
Frequency and duration values of each state has resulted that, frequency and duration values are decreases as state increases. The
frequency and duration of state-1 is highest. Complexity has increased by considering de-rated states but it gives same results of
Two-component model values by neglecting very low values.
REFERENCES:
[1] Roy Billington, ―Reliability Assessment of Large Electric Power Systems‖, Kluwer academic Press/springer india, 2008
[2] R.Billington and a.N.allen, ―Reliability Evaluation of Engineering Systems; Concepts and Techniques‖, springer, 1992.
[3] R.Billington and R.N.Allen,―Reliability Evaluation Of Power System‖, second edition, 1996.
[4] Yaw-Juen Wang, ―A Method Integrating Deterministic and Stochastic Approaches for the Simulation of Voltage Unbalance
in Electric Power Distribution Systems‖, IEEE Member, IEEE Transactions On Power Systems, Vol. 16, No. 2, May 2001.
[5] L. S. Low L. Goel ―Incorporating Deterministic Criteria in the Probabilistic Framework for Composite Generation and
Transmission Systems,‖ Senior Member, IEEE, School of Electrical and Electronic Engineering Nanyang Technological
University, Singapore, 2000.
[6] Asim Kaygusuz, Baris Baykant Alagoz, Murat Akcin, Cemal Keles , Abdulkerim Karabiber, Ozan Gul ―Monte Carlo
Simulation-Based Planning Method For Overload Safe Electrical Power Systems,‖ Inonu University, Bingol University,
Department of Electrical and Electronics Engineering, Turkey Journal of Electrical Engineering.
[7] A. Sankarakrishnan R. Billinton ―Effective Techniques For Reliability Worth Assessment In Composite Power System
Networks Using Monte Carlo Simulation‖, Power Systems Research Group University of Saskatchewan Saskatoon, Canada,
IEEE Transactions on Power Systems, Vol. 11, No. 3, August 1996
[8] Lovleen gupta, Nittin Narang, Thesis on ―Composite System Reliability Evaluation‖, power systems and electric drives,
Tharapur University, 2009.
[9] R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L. Goel, E. Khan, P. Kos, G. Nourbakhsh, J. Oteng-Adjei, ―A
Reliability Test System For Educational Purposes - Basic Data,‖ Power Systems Research Group University of Saskatchewan
Saskatoon, Saskatchewan CANADA, IEEE Transactions on Power Systems, Vol. 4, No. 3, August 1989.
[10] Dr. Attila Csenki, ―The Number of Working Periods of a Repairable Markov System during a Finite Time Interval‖, Aston
University; Aston Triangle; Birmingham, IEEE Transactions on Reliability, Vol. 43, NO. 1, March 1994.
695 www.ijergs.org
International Journal of Engineering Research and General Science Volume 3, Issue 2, Part 2, March-April, 2015
ISSN 2091-2730
[11] Wenchen LI, Lu Sun, Weimei Zou, Chunqing Luo, ―Power System Reliability Analysis of System Based on PSASP and
Fault Enumeration Method and Applications‖, China Electric Power Research Institute-China, China International
Conference on Electricity Distribution (CICED), Shenzhen, 23-26 Sep. 2014.
[12] Aleksandamr. Stankovi, Edwina . Marengo ―A Dynamic Characterization of Power System Harmonics Using Markov
Chains‖, Northeasternu Niversity Boston, IEEE Transactions on Power Systems, Vol. 13, No. 2, May 1998
[13] Qinru Qiu, Massoud Pedram, Qing Wu, ―Stochastic Modeling of a Power-Managed System—Construction and
Optimization‖, IEEETransactions On Computer-Aided Design Of Integrated Circuits And Systems, VOL. 20, NO. 10,
OCTOBER 2001
696 www.ijergs.org