Project: Proposed Two Story Residential Building With Roof Deck

This document provides a cost estimate for a proposed two-story residential building with a roof deck located in Purok 2, Poctol, Daraga, Albay. The total project cost is estimated to be PHP 2,425,350. This includes costs for the ground floor at PHP 1,839,700, second floor at PHP 1,917,900, roofing and roof deck at PHP 191,100, plus architectural and engineering fees and management fees. The approximate construction period is estimated to be 6 months or 180 calendar days.

Uploaded by

altavanoar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
180 views3 pages

Project: Proposed Two Story Residential Building With Roof Deck

This document provides a cost estimate for a proposed two-story residential building with a roof deck located in Purok 2, Poctol, Daraga, Albay. The total project cost is estimated to be PHP 2,425,350. This includes costs for the ground floor at PHP 1,839,700, second floor at PHP 1,917,900, roofing and roof deck at PHP 191,100, plus architectural and engineering fees and management fees. The approximate construction period is estimated to be 6 months or 180 calendar days.

Uploaded by

altavanoar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

PROJECT: PROPOSED TWO STORY RESIDENTIAL BUILDING WITH ROOF DECK

Location: PUROK 2, POCTOL, DARAGA, ALBAY


Owner: MR LESLIE & MRS DAISY LORINO
PARAMETRIC COSTING (RESIDENTIAL BLDG)
ITEM DESCRIPTION/LOCATION RM. # AREA (sq.m.) FACTOR UNIT AREA (UA) COST/UA UNIT COST ITEM COST
I. GROUND FLOOR 88.6
I.1 LIVING ROOM GF-01 25 1 25 18,000.00 450,000.00
I.2 DINING AREA & KITCHEN GF-02 15 1.25 18.75 18,000.00 337,500.00
I.3 SERVICE AREA GF-03 8.5 0.8 6.8 12,000.00 81,600.00
I.4 MASTER'S BEDROOM GF-04 20 1 17.9 18,000.00 250,600.00
I.5 WALK IN CLOSET GF-05 3 1.25 3.75 18,000.00 67,500.00
I.6 BEDROOM 1 GF-06 9.5 1 9.5 18,000.00 171,000.00
I.7 PORCH GF-07 7.5 1 7.5 18,000.00 135,000.00
I.8 CARPORT GF-08 12 1 12 18,000.00 216,000.00
I.9 MASTER'S BEDROOM T&B GF-09 3.1 1.25 3.875 18,000.00 69,750.00
I.10 T&B 1 GF-10 2.7 1.25 3.375 18,000.00 60,750.00
1,839,700.00
II. SECOND FLOOR 128
II.1 FAMILY AREA SF-01 23 1 23 18,000.00 414,000.00
II.2 MUSIC / ENTERTAINMENT AREA SF-02 15 1.25 18.75 18,000.00 337,500.00
II.3 BEDROOM 2 SF-03 16 1 16 18,000.00 288,000.00
II.4 BEDROOM 3 SF-04 15 1 15 18,000.00 270,000.00
II.5 T&B 1 SF-05 3 1.25 3.75 18,000.00 67,500.00
II.6 STAIRS SF-06 5 1.25 6.25 18,000.00 112,500.00
II.7 BALCONY SF-07 51 0.7 35.7 12,000.00 428,400.00
1,917,900.00
III ROOF DECK /ROOFING 91
III.1 DECK WITH WATERPROOFING RF-01 91 0.7 63.7 3,000.00 191,100.00
191,100.00
SUMMARY 1
ITEM I GROUND FLOOR PHP 1,839,700.00
ITEM II SECOND FLOOR PHP 1,917,900.00
ITEM III ROOFING & ROOF DECK PHP 191,100.00
GRAND TOTAL PHP 2,109,000.00
PHP. 2,109,000.00
BASIC ARCHITECTURAL &ENGINEERING SERVICES FEE 5% 105,450.00
MANAGEMENT FEE 10% 210,900.00
TOTAL PROJECT COST PHP 2,425,350.00
in words: TWO MILLION FOURHUNDRED TWENTY FIVETHOUSAND THREE HUNDRED FIFTY PESOS ONLY

APPROX CONSTRUCTION PERIOD: 6 .0 MONTHS OR 180 calendar days


BRIEF SPECIFICATION FOR RESIDENCE
CONSTRUCTION OF STRUCTURAL FRAMES NOTE:
STEEL BARS TO BE USED 20 mm DIAMETER STRUCTURAL GRADE, CORRUGATED BARS ELEVATION HT. OF GR. FLOOR
10 mm. DIAMETER STIRRUPS & TIES FROM STREET LEVEL 0.6 M.
16 mm DIAMETER COR. STEEL BARS FOR FOOTING TIE BEAMS & COLUMNS FOR APARTMENT UNITS CEILING HT. 2.8 M.
20 mm DIAMETER COR. STEEL BARS FOR COLUMN FOOTINGS (FOR RESIDENCE) FIN. GR. FLR. LINE
20 mm DIAMETER COR. STEEL BARS FOR BEAMS TO FIN. SECOND FLR 3.5 M.
10 MM. DIAMETER AND 10 MM. DIAMETERS FOR SLAB ON FILL & 12 MM, FOR RC SLAB 2ND FLOOR
6" THK. CONC. HOLLOW BLOCKS FOR EXTERIOR WALLS & FENCING CEILING HT. 2.7 M.
4" THK. CONC. HOLLOW BLOCKS FOR INTERIOR WALLS FIN. 2ND. FLR. LINE
GLASS AND VENTILATION FOR MAIN STAIRWAY WALL & STAINLESS STEEL RAILING TO FIN. ROOF DECK 3 M.
GLASS ON Upvc FRAMING FOR EXTERIOR GLAZING ROOF DECK
SOLID PANEL DOORS FOR ALL EXTERIOR AND MAIN DOORS CEILING HT. 2.5 M.
PAINTING FOR EXTERIOR WALL BOYSEN & SPECIAL FININSHING EXTERIOR TILES HT. OF ROOF APEX 3 M.
WATER PROOFING FOR ALL CONCRETE SLABS TOTAL BUILDING HT. 10.1 M.
WATER SUPPLY PIPING SYSTEM SHALL USE PPR PIPES AND STAINLESS ACCESSORIES
CLASS A FIXTURES (AS DESIRED BY THE OWNER) FOR APARTMENT UNITS
SANITARY LINE PIPING SYSTEM BY EMERALD OR APPROVED EQUAL NOTE:
CEILING WORKS SHALL USE LIGHTWEIGHT METAL FOR FRAMES AND APPROVED CEILING BOARDS ELEVATION HT. OF GR. FLOOR
LIGHTING AND POWER LINES SHALL BE OF MATERIALS IN COMPLIANCE TO PEC STANDARDS AND INTERNATIONAL ADAPTABILITY FROM STREET LEVEL 0.4 M.
LIGHTING FIXTURES shall SHALL USE LED LIGHTS OR AS DESIRED BY OWNER CEILING HT. 2.5 M.
KITCHEN SINK AND COUNTERS SHALL BE STAINLESS STEEL AND GRANITE SLABS OR AS DESIRED BY THE OWNER FIN. GR. FLR. LINE
FLOOR TILES FOR LIVING ROOM AND OTHER ADJACENT AREAS SHALL BE 800 mm x 800 mm TILES TO FIN. SECOND FLR 3 M.
FOR BEDROOMS SHALL BE LAMINATED WOOD PLANKS OR OWNER'S DESIRED MATERIALS 2ND FLOOR
BEDROOM DOORS SHALL BE SOLID PANELS WITH CLASS A LOCKING SYSTEM AND HINGES CEILING HT. 2.7 M.
FOR APARTMENT UNITS USE 300 X 300 MM FLOOR TILES FIN. 2ND. FLR. LINE
ROOFING SHALL BE BY SCG Concrete Roof for Residence & CONCRETE GUTTER TO FIN. ROOF DECK 3 M.
STEEL DECKING FOR STRUCTURAL SLABS (2ND FLR. TO ROOF DECK FLR.) TOTAL BLDG. HT 6.4 M.
NOTE: CHANGES ON THE SPECIFICATION WILL BE APPARENT AS PLANS AND DRAWINGS
WILL BE IN DETAIL AS PER AGREEMENT BETWEEN THE OWNER AND THE PREPARED BY:
ARCHITECT AT THE DESIGN DEVELOPMENT STAGE/PHASE ARCHITECT JOSEPH MANILA ESPINAS
PRINCIPAL ARCHITECT JME ARCHITECTS & ASSOCIATES