Testing Additional Protective Functions With The CMC Test System
Testing Additional Protective Functions With The CMC Test System
Revision Table
1.1 Considerations
In grids with low impedance star point grounding, ground faults with relatively high impedances may occur.
Thereby the resulting fault currents can be below the pick-up values of the classical short circuit protection.
The distance protection function for example may not pick-up in this case. For this reason other physical
fault quantities have to be chosen, to ensure clear fault detection.
The protection function resulting from these criteria is the ground fault short circuit protection, also known as
high resistance ground fault protection. This protection function is based on the analysis of the zero
sequence quantities for the pick-up. Depending on the selected functionality it works directional or non-
directional.
Note: Depending on the relay type, the zero sequence voltage directional protection can also use the
negative sequence for direction determination.
However, the following example only uses the zero sequence voltage directional protection.
As standard characteristic a zero sequence dependent characteristic ( tTrip = f(V0) ) is selected for this
protection function. This characteristic is based on the fact that in meshed grids the zero sequence voltage
decreases with increasing distance of the fault.
tTrip / s
V0 / V
B C
Figure 1-1: Voltage dependent trip time of the zero sequence voltage protection (not true to scale!)
Because of this, the relay which is in forward direction the nearest to the fault, has the fastest trip time.
When setting this protection function it must be ensured, that the pick-up values are set according to the grid
configuration. The pick-up current has to be lower than the lowest ground fault short circuit current and the
pick-up voltage must not react to small unbalances in the grid.
The tripping characteristic depends on the manufacturer. In the following, two examples shall be displayed:
AREVA:
2s
t
VN-E
10 0.2
Vnom
0.6364 1.1
3
SIEMENS:
2s
t
0.25 V0 V V0min V
Furthermore, most of the manufacturers use an additional time delay, which delays either the pick-up time or
the trip time.
VA VC
VB VN
IB IN
IA IC
Start
Trip
Note: The AREVA P435 uses a pick-up delay as additional time delay. This has to be considered in
the step duration of the ramps.
Note: The AREVA P435 uses a pick-up delay as additional time delay. This has to be considered in
the step duration of the ramps.
12,00
10,00
8,00
Siemens 7SA6
6,00
Areva P435
4,00
2,00
0,00
-3 -2 -1 0 1 2 3 4 5 6 7 8 9 10
For the following test three values are chosen to test the forward direction and one test point for the reverse
trip time.
Note: The angles of the voltages and currents correspond to the methods, used by the
manufacturers. These methods will be explained more detailed in the next section.
Figure 1-2: Directional characteristic of the Siemens 7SA6 (Source: Manual 7SA6, Siemens) and of the Areva P435 (Source: Manual
P435, Areva)
In the Siemens relay, the neutral current is used as reference, while the polarizing voltage is used for the
direction determination. This polarizing voltage consists of the zero sequence voltage and (if measured) the
star point current of the transformer. In our example, only the zero sequence voltage is used for the
polarizing voltage.
In contrast, the Areva relay uses the neutral-ground voltage as reference. The neutral current is used
determine the fault direction.
Forward Reverse
V0
I0 V0
I0
Reverse Forward
Figure 1-3: Position of the test quantities for the Siemens 7SA6 and the Areva P435
The position of the test angles has to be set outside the tolerance of the directional limits.
2.1 Considerations
L1
L2
L3
CB close
L1 Distance L1
Protection Device
L2 L2
with Synchronism
L3 Check
N
Figure 2-1: Connecting the measurement voltage of a distance protection device with synchronism check
Synchronism check is used to prevent unauthorized equalizing currents when switching on the circuit
breaker. These equalizing currents occur if the voltages on both sides of the circuit breaker are not the
same. The frequency, amplitude and phase angle of the voltage are the criteria here. Only when all of these
factors are within the defined boundaries for a specific time is the CB close command issued.
If the voltage on one side is below the setting value V<, this is detected as de-energized. If the voltage is
higher than the setting value V>, this side is classed as "switched on".
Vn
switched on
V>
undefined
V<
de-energized
0
Due to the different logic employed in the relays of different manufacturers, the same input values can cause
different reactions. The parameter settings of SIEMENS and AREVA are, for example, compared in Figure
2-3 and Figure 2-4. Both relays should be activated if one of the two sides is de-energized while the other is
switched on or when both sides are de-energized.
Figure 2-3: Parameters for selecting the SIEMENS 7SA63 voltage test (source: DIGSI 4.82)
Figure 2-4 Parameters for selecting the AREVA P435 voltage test (source: MICOM S1 Studio)
Given the assumed parameter settings, it makes no difference whether the busbar side is de-energized and
the line side is undefined or vice versa.
Vn
V>
voltages on both
sides of the circuit
breaker
V<
0
Figure 2-5: Voltages for the situation: "one side de-energized, one side undefined"
> The frequencies on both sides of the circuit breaker must be the same.
1,5
0,5
V / p.u. ->
0 V1
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08
V2
-0,5
-1
-1,5
t / s ->
> The amplitudes of the voltages must NOT deviate significantly from one another.
1,5
0,5
V1
V / p.u. ->
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08 V2
-0,5
-1
-1,5
t / s ->
0,5
V / p.u. ->
V1
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08 V2
-0,5
-1
-1,5 t / s ->
If these conditions are met for a minimum time tmin = 0…5 s, the CB close command release is issued. If the
conditions cannot be met throughout the maximum synchronization time tsync max = 10…360 s, the CB close
command is aborted without success.
1,5
0,5
V / p.u. ->
V1
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08 V2
-0,5
-1
-1,5 t / s ->
Figure 2-9: Voltages at which all conditions for activation are met
The frequency deviation indicates how quickly the phase angle changes between the two voltages. For
example, if we take a frequency deviation of 1 Hz, the angular difference changes 360° within one
second. The following generally applies as the condition for the setting values of synchronism check:
2 max 360
fmax
tmin
The relay does not typically check whether the three parameters meet this inequality. A situation can, for
example, therefore occur in which fmax is set too high. This causes the angular difference to change too
fast. In this case, the permitted switching window of the angle condition elapses in too short a time, meaning
that the switch-on conditions cannot be met for the duration tmin (see Figure 2-10).
+10° -10°
f
+90° φ
-90°
180°
VG V1
IC
V2
Iload
VG
V2
V1
Δφ Δφmax
ΔVmax
ΔV
Figure 2-12: Illustration of the voltages from Error! Reference source not found.
Based on Figure 2-11 and Figure 2-12 we can see that the conditions of synchronism check cannot always
be met, even in a standard operating state. Both the amplitude and the angle condition fail to be met here.
To avoid this problem, the synchronism check function must be adjusted to a less sensitive setting. Should
this not be possible due to the increased equalizing currents, we can attempt to connect the line first on the
load side and then on the supply side. This allows the Ferranti effect to contribute to improving the
conditions at the point of activation. If the conditions are still not met, the line can only be connected at a
lower load current.
Timing:
tmin tmax
5s 10 s
L1 CB closed
L2 CB closed
L3 CB closed
CB CLOSE
Vn
voltages
on the line
V>
voltages
on the busbar
V<
0
The voltages on the line side (L1, L2 and L3) are to be set to the nominal values.
Attention must be paid with all voltages set to ensure that the angle of the voltages is always set the same.
To achieve a voltage triangle with a voltage phase angle V L1-E of 0°, a value of 30° must therefore be set
between phase 1 and phase 2 for a line-line voltage.
A similar test is set up to check the V< limit of the voltage inputs on the line.
SIEMENS AREVA
voltages
Vn Vn on the line
voltages
on the busbar
V> V> Vmax
voltages
on the busbar
The SIEMENS relay can be tested by leaving the voltage on the line side at 0 V and setting the voltage on
the busbar below and above the V> limit. Since the synchronization bypass is used here, the
synchronization conditions do not need to be met.
The AREVA relay, on the other hand, would always issue a CB close command release if one side has been
detected as de-energized. The voltage on the line side therefore cannot be left at 0 V. Instead of a
synchronization bypass, a complete synchronization check must be performed. The voltage on the line side
therefore needs to be set to a value slightly above V>. Voltages that are below and above V> are now set on
the line side. It is vital to ensure that the difference in the voltages between the line and busbar side are not
greater than Vmax here. If this condition is not observed, it is then not possible to determine whether a CB
close command release has been refused because synchronous conditions are not in place or because the
respective value is below the V> limit.
The only differences between SIEMENS and AREVA in terms of the settings are due to the value of the line-
side voltage.
> SIEMENS: V L1-L2 = 0 V
> AREVA: V L1-L2 = 87 V
However, this does not impair assessment of the test in the Measurement View:
A similar test is set up to check the V> limit of the voltage inputs on the line.
voltages
on the busbar
voltages +Vmax
on the line
Vn Vn
voltages
Vmax on the line
voltages
on the busbar
Since the circuit breaker is switched on during the test, it needs to be switched back off to be able to
continue the test. This is why the state "Switch off CB" requires user input.
When setting the angle, it is important to observe the difference between line-neutral and line-line values. If
the voltage L1-E has an angle of 0°, the angle of the voltage L1-L2 equals 30° during symmetrical operation
with no faults.
12.5°
VL1 Line
VL1 BB
VL1 BB VL1L2 BB
42.5°
VL2 BB
VL3 BB
tmin tmin
tmax tmax
tmin tmin
3.1 Considerations
If a generator is to be connected to the power system, it is important to ensure that the equalizing currents
are kept as low as possible. Equalizing currents flow when the voltages on both sides of the circuit breaker
are not the same at the switching time. These differences can affect the frequency (f), amplitude (V) and
phase angle (). During the synchronization process, the synchronizing device matches the generator
voltage to the power system voltage. The synchronizing device is capable of influencing the amplitude and
the frequency of the generator voltage via control commands. While these are being adjusted, the
synchronizing device continuously monitors whether the conditions for switching on the circuit breaker are
met. Once this is the case, the CB close command is issued. If the conditions are not met within the
maximum synchronization time, the process is aborted.
L1
L2
L3
CB- CLOSE
L1 L1
Synchronizing
L2 L2
device
L3 L3
V ↑↓
G
f ↑↓
T
Figure 3-1: Connecting a synchronizing device
The permitted amplitude, frequency and angle differences between the power system and the generator
need to be specified by the generator manufacturer here. It is also important to ensure that the resulting
equalizing current does not exceed the mechanical strength of the switchgear system. When setting the
parameters of the synchronizing device, it is important to ensure that the connection zone is within
manufacturer tolerances.
Manufacturer specification
Parameter of the
synchronizing device
Δff
As we can see from Figure 3-2, a difference in frequency between the two sides of the circuit breaker is also
permitted when connecting the circuit breaker. As the phase angle continuously changes with a constant
frequency difference (Figure 3-3), it is not possible to connect at all times.
1.2
1
0.8
0.6
V / p.u. ->
0.4
0.2 V1
0
-0.2 0 V2
0.02 0.04 0.06 0.08 0.1 0.12 0.14 0,16 0.18
-0.4
-0.6
-0.8
-1
-1.2
t / s ->
0° 0° 0°
f f
+90° -90° +90° -90° +90° -90°
f
0° 0°
180° 180° 180°
f
+90° -90° +90° -90°
f
180° 180°
Figure 3-3: Motion of the angular difference based on the frequency difference f
So that the equalizing current is kept as low as possible when switched on, the connection must be made
when the angular difference is 0°. To take the close time of the circuit breaker into account, the CB close
command is issued before the zero passage, so that the circuit breaker poles come together precisely at the
zero passage point. The principle becomes clear when viewing Figure 3-4. To be able to predetermine this
time, however, the close time of the circuit breaker must always be measured.
+90° Δf
+90°
180°
Timing:
tmax close time
60 s 0.1 s
VBB L1 VGen L1
VBB L2 VGen L2
CB CLOSE
V> (higher)
f> (higher)
V< (lower)
f< (lower)
Since the 7VE632 does not possess a defined zone in which no control commands are issued, both values
of the dead zone (1 and 2) must be set to 0.
In the tab Function, individual test points are then positioned at the V-f plane. The CMC test set does not
react to control commands from the synchronizing device here. As such, it is possible to test the limits of the
Attention: Due to the way the 7VE632 operates, it is not possible to test the Vmax limit with f = 0 using the
set of parameters defined.
For synchronization of generators, the function "Connection on synchronous power systems" has been
deactivated in the protection device, as it is only relevant for synchronization of power system sections.
However, deactivating this function causes the zone of synchronous power systems to be hidden from the
connection zone.
ΔV
Δf
The switchover limit between synchronous and asynchronous power systems can be set between 10 and
40 mHz.
As a consequence of the values set, no CB close command is issued when the test point lies within the zone
marked in red. An LED also indicates that the conditions have been met for synchronous power systems.
When starting the test, the outputted voltages and frequency now do NOT remain constant on the generator
side. The values of the CMC test set are adjusted in line with the duration of the control pulses and the rates
of change set. The gradient is displayed at the V-f plane.
4.1 Introduction
For external phase-to-phase or three-phase faults the transformer differential protection relays have no
problems measuring the short-circuit currents. This is not the case, however, with phase-to-earth faults.
Isc
protected zone
The zero sequence current flowing on the star side of the power transformer will not produce a current
outside the delta on the other side. Therefore the zero sequence must be eliminated from the currents seen
by the relay. The way the elimination is achieved is different for conventional and numerical relays.
Note: The elimination methods of conventional relays with interposing transformers is not part of this
document
arithmetical measured
üE
I'SL
Disadvantage, in analogy to 3I'0
Note: Digital relays, which use the numerical zero sequence elimination, have a sensibility reduced by
1/3. This effect is critical for power transformers with low-resistance or solid earthing.
Especially, if the fault is near the transformer star point.
87
Source
I Source
64
I Fault
Note: The fault current depends on the impedance between neutral and earth and on the fault point
voltage which corresponds to the fault location. The value of the current is directly proportional
to the location of the fault.
87
Source
I Source
64
I Fault
Note: The fault current depends on the leakage reactance of the winding when no arc resistance is
taken into consideration. The diagram shows that for the major part of the winding an operating
current for the differential relay exists. The REF alone provides more sensitivity for this network
than the differential protection.
Ynyn 0
160 MVA
231kV/115.5kV
400A/1A 600A/1A
800A/1A
87/64
The settings as well as the bias definition of this protection function depend on the manufacturer. For the
relays used in this example, the settings are:
You can see that two global Hardware Configurations are needed for this test. But as the binary signals do
not differ, only the analog outputs have to be adjusted.
Note: The following explanations focus on testing the restricted earth fault protection function with not
more than 6 current outputs.
This tool includes the tripping characteristics of the Siemens 7UT613 as well as the Areva P633. For testing
the stability against external faults, a fault outside the protected zone has to be entered. The resulting
currents are entered in the State Sequencer.
5.1 Preface
The test tool EnerLyzer offers extraordinary functions: Following prior configuration, the inputs otherwise
only used as binary can also be used as analog inputs. It can also be used in parallel with the test module
QuickCMC, allowing electrical variables to be measured and output at the same time.
The test tool EnerLyzer offers four different modes, with which the connected signals can be analyzed:
> Multimeter
> Transient recording
> Harmonic analysis
> Trend recording
You will need a license to be able to use the full scope of functions. Only the Multimeter function is available
in the basic version.
In the following, the CMC test device is to be connected to the public power network to highlight the
functionality of the four measurement modes.-
Since the CMC test device is not to output any signals, only the inputs need to be configured.- This is
selected in the line Function. Voltage and current are relevant for the functions of the test tool EnerLyzer.
If one of these is set, the Nominal range must be entered in the line beneath it. Currents can only be
measured using clip-on ammeters with voltage outputs. The transformer ratio must also be specified for this.
To be able to use the test tool EnerLyzer correctly, an Input configuration needs to be made. This setting
window is opened by clicking on a button directly next to the button Hardware configuration.- The
individual phase voltages or currents are assigned to three-phase systems by dragging and dropping the
icons from the top row of inputs to the desired field.- Power levels to be determined from a voltage and a
current can also be defined. This configuration is required, as automatic assignment of the signals often fails
to set this up correctly. The figure shows an example with three voltages and three currents. No input
configuration is required for our practical example, as we are only using one voltage.-
The same settings can essentially be made in this window as in the hardware configuration. However,
here you can also enter transformer ratios. This allows the display of the signals to be switched over from
secondary values to primary values.
In this operating mode, the measured variables are shown in a table. If three-phase systems have been
configured in the Input configuration, the symmetrical components are also displayed. All signals can be
displayed in vector diagrams.
In this operating mode, the connected signals can be recorded and saved as a "Comtrade" file. They can
then be analyzed using the test tool Trans-View.
A start time for the recording can be configured under Trigger setting.- A
criterion of power quality, for example a "notch" or a deviation from the
nominal frequency, can be defined as the start time. The transient recording
can also be started by a rising or falling edge of a signal.-
Since the recording takes place in the CMC test device and the files are only
transferred to the computer afterwards, the length of the recording is limited
by the available memory of the CMC test device.- This maximum recording length also depends on how
many signals are being recorded and at what sampling frequency. A higher sampling frequency allows
analysis of very high harmonics, but reduces the maximum recording length.-
In the mode Harmonic analysis, harmonics contained in the measured signal are displayed as bar graphs.
This makes it easy to read off the amplitudes of the individual harmonics. For more precise analyses, users
can switch over to the two table views Summary and Details.
In the Detail View, the proportions of harmonics in the measured signal, as well as the amplitudes and
phases of the respective harmonic, are displayed in a table.
The configuration of the harmonic analysis and the Snapshot View are called up using the highlighted
buttons.-
The following settings can only be made when Advanced >> has
been activated.
In the mode Trend recording, various parameters of the measured signals can be logged over long time
periods.
6.1 Preface
Recorded signals can be examined using the test tool TransView.
The test module Advanced TransPlay, on the other hand, is used to process and output recorded signals to
a test object. These might be fault reports exported from a protection device following a fault incident or
operations simulated with a program.
The test module Advanced TransPlay and the test tool TransView support various file formats here:
> COMTRADE format with three files:
- CFG: COMTRADE configuration file, used to describe fault report channels (signal names, sampling
frequency, etc.).
- DAT: COMTRADE file with the sample values of the fault report channels.
- HDR: "Header file", which contains any data-related text that is not used by the software.
> L4 format with a PL4 file.
> TRF format with a TRF file.
The test module Advanced TransPlay can be used as a standalone module or within an OCC test
document.-
Various views are available for assessing a fault report using the test tool TransView:
> The view Time signals shows the time response of the recorded signals in either current or effective
values.
> In the view Vector diagrams, the measured variables are displayed in vector diagrams at the current
cursor position.
> Response plots of complex variables, such as impedances, can also be displayed in an R-X diagram.
> The view Harmonics shows the amplitudes of the harmonics contained in the recorded signals.
> In the view Table, variables of the recorded signals, such as magnitude and phase, are displayed in a
table at the current cursor position.
> A Fault locator is also integrated for distance protection. Once relevant variables such as the
impedance coating of the line have been defined, the fault locator can be used to determine the distance
to the fault based on the recorded currents and voltages.
Users can switch between display of primary and secondary values in all views.
The button Assign signals can be used to add signals, for example of symmetrical components, to
individual views.
The test module Advanced TransPlay can be added to the test report in the OCC.
Via Import... in the File menu, the recorded signals can be imported from their storage location into the test
module Advanced TransPlay.
Once the transient data has been loaded, a predefined profile can be selected. This is, however, not
necessary to play the incident. Profiles of this nature contain a set of test settings. These settings include
assignment of the binary and analog signals in the Detail View, as well as their properties displayed in the
test module Advanced TransPlay, the various measurement conditions, the positions and names of state
markers and the number of signal repetitions (settings made by right-clicking in the Time Signal View). You
can save these settings in a profile and then use this on an imported fault report.
In the Measurement View, time assessments can be performed for the freely selectable binary inputs.
> Original mode: In this mode, the Signal View of the imported incident is kept open.
> Expanded mode: When adjustments have been made, for example to alter the scaling of the values,
these can be seen in this mode.
> Test results: When playback is started, the measured signals are recorded and displayed in this
screen.
To be able to differentiate the signals of the two fault reports from one
another later on, an Additional index for signal name is entered here.
The button Add is used to add the fault report of the undervoltage side
and also attach an Additional index for signal name.
At the time at which the fault occurs, we can clearly see that the recorded signals of the overvoltage and
undervoltage side are not synchronous.
The setting window Synchronize fault reports is then opened by hitting the button Edit. This setting
window can be confirmed by hitting "OK" without making any further changes. The two fault reports are now
synchronous.
The further processing and editing of this fault report take place in the test module Advanced TransPlay.
In the test module Advanced TransPlay the local hardware configuration is first adjusted. 6 currents are
required. A trigger signal and a Trip-command are also to be issued on the binary inputs of the CMC test set
for the incident analysis.
The fault report previously created can then be imported into the test module Advanced TransPlay and the
individual signals assigned to the outputs of the CMC test set.
The signals used here are primary currents. These need to be converted to secondary values using
corresponding scaling. The current transformer of the overvoltage side has a transformer ratio of 400 A/1 A.
The secondary current therefore corresponds to 0.25% of the primary current. A 600 A/1 A current
transformer is used on the undervoltage side. The secondary current is therefore 0.167% of the primary
current.
The time at which playback is to start is then specified by clicking on << Cursor 1. Alternatively, the start
time can be entered manually.
A repetition is then added via the menu item Edit. In the setting window Data markers that opens, the
number of repetitions to be added can be specified. A prefault state of approximately 2 s is to be generated
here, so 100 repetitions are set.
The test can then be started. Here, the signals are played back and the binary inputs defined in the
7.1 Preface
The tool Harmonics allows signals with superimposed harmonics to be generated both quickly and easily.
In the Test View, all parameters (amplitude, phase and frequency) of the fundamental component are
defined.
The Pre-signal time and Post-signal time are set in the section Signal Definition. Only the fundamental
component is output during these time ranges without any harmonics. A signal with superimposed
harmonics is only output during the Signal time.
Should a protective function of the protection device to be tested trip during the signal time, the system is
switched over to the post-signal immediately. For this to happen, the trigger condition must be configured
and the corresponding binary input be specified in the hardware configuration.
The desired proportion of harmonics can be defined in the table in the lower part of the window. Whether
entry of the harmonics is made in relation to the fundamental component or in absolute values, it is specified
in the settings section Harmonic input.
When entering harmonics, the desired harmonic is first entered in the column Order. The individual
amplitudes and phases can then be set. In this example, a current with 2nd and 5th order harmonics is being
generated. The voltage output contains the 7th order harmonic.