3 Risk Management
3 Risk Management
4.1 Introduction
4.2 Definitions
Risk:
-“The exposure to the chance of occurrence of events adversely or favorably
affecting project objectives as a consequence of uncertainty”.
-Most definitions of risk have focused only on the downside effects associated with
risk. Therefore, risk may be defined a: “Undesirable extra cost or delay due to
factors having uncertain future outcome”.
Risk Management:
“A formal ordering process for systematically identifying, analyzing, and responding to
risk events throughout the life of a project to obtain the optimum or acceptable degree of
risk elimination or control”.
Risk Event
A discrete occurrence that may affect the project for better or worse is a risk event. A risk
event will have an impact on one or several of the objectives of the project. An example
could be that a key team member is reassigned off the project before his/her work is
completed. The reassignment is a “risk event.”
Effective risk management is guided by a set of principles that represent current “best
practices.” Irrespective of the size or complexity of a project, the Risk Management Plan
should reflect these principles. The Risk Management Plan is part of the Project Work
Plan.
Global Perspective: View each phase of a project as a means to the overall project
success. View each project and its success in relationship to other projects.
Forward-Looking View: Look ahead to anticipate risks and their potential impacts.
More importantly, anticipate potential risks in time to successfully address them.
Continuous Process: Identify and manage risks routinely through all phases of the
life cycle of the project.
Teamwork: Pool talents, skills, and knowledge to work cooperatively to identify and
manage project risk.
The purpose of this subsection is to explain the risk management process. It is important
to note that the process itself is built on a general approach that:
Examines the identified risks to mitigate their probability and impact, or to build in
risk allowances.
Respond Analyze
Purpose: Search for and locate sources of risks before they become a problem and
provide a preliminary assessment of their consequences.
Tools:
- Affinity diagram
- Checklist of possible sources of risk
- Fishbone diagram
Category Examples
Administrative Delay in possesses of site
Limited working hours
Troubles with public services
Logistical Shortage or late supply of different resources
Site remoteness problems
Communications
Construction Ground problems
Limited work space
Equipment breakdown
Physical Placing fill in dry season
High tides, temperature, etc.
River diversion in time of low flow.
Design Incompleteness
Design changes
Design errors
Financial Inflation
Exchange rate fluctuation
Availability of funds
Delay payments by client
Management Space congestion
Scheduling errors
Estimating based on standards
Errors in B.O.Q.
Contractual Contract type
Liability to others
Co-ordination of work
Political Change in local laws
Import restrictions
Use of local resources
Disasters Floods, fire, landslip, earthquakes, etc.
Primary Secondar
y
Secondar
y
Primary
Primary
Secondar
1. Label the type of y
risk in the center of Type of
the wheel Risk
2. Identify the primary
consequences of a
related risk event
and place in the
first circle
3. For each primary Primary
consequence,
identify in the Primary
second circle
Secondar
additional
y
consequences that
are related
As the instructions in Fig. 4.1 suggest, begin by writing the name of the particular risk in
the center of the wheel. Then, brainstorm all of the potential consequences to the project
if this risk event occurred. These “primary” consequences become the first ring in the
wheel. Continue the analysis by taking each primary consequence and identifying the
At this point, the Project Team should have all the risks identified, as well as the
probability and impact each risk carries. These risks can be inserted into the Probability-
Impact Risk Analysis Matrix (Fig. 4.2) to get a global picture of the risks, and their
impact relative to each other. Planning worksheets for the Probability-Impact Risk
Analysis Matrix are only a planning tool and not included in the Risk Response Plan. The
Probability-Impact Risk Analysis Matrix and the Risk Management Log rank the risks
according to their impacts and probability and are to be included in the Risk Response
Plan.
-Procedure:
Three values of each risk variables are to be specified: a most likely, an
optimistic, and a pessimistic.
For each risk variable:
- Set all other risk variables at their most likely value.
- Determine a value for the performance criteria when risk variable under
consideration is set at its optimistic value.
- Determine another value for the performance criteria when risk variable
under consideration is set at its pessimistic value.
- The difference between the obtained two values of the performance criteria is
checked (subjectively).
Two cases can be encountered:
1. The difference corresponding to a risk variable has a little effect on the
performance criteria. Then, this risk variable can be eliminated from the
probability analysis. The most likely value for this risk variable can be
used throughout the analysis.
2. A significant difference is found, and consequently this risk variable
should be included in the probability analysis.
Probability Analysis
-The purpose is to determine the effect of those risk variables which have a significant
impact on the performance criteria.
-Procedure:
Consider the risk variables as random variables.
Purpose: To translate risk information into decisions and mitigating action plans. To
implement those action plans.
For each project, develop a Risk Response Plan. Risk responses can be made at two
stages:
First Stage:
Develop responses to avoid, reduce, or transfer risk (before risk analysis).
Second stage:
To deal with residual risks, one of the two following approaches can be adopted:
1. Residual risks can be transferred through contractual arrangements and/or
insurance policies.
2. Cover retained risk impact by time and/or cost contingency.
Acceptance: Deciding to not change the project plan to deal with a risk or are unable to
identify any other suitable response strategy. In other words, recognize the risk, but do
not take any action because the impact or probability is small.
- Passive Acceptance – Accept the risk, and plan no action. Deal with the risks as
they occur.
Avoidance: Changing the project plan to eliminate the risk or to protect the project
objectives from its impacts.
- Modify the project plan in such a way as to reduce the probability of the threat or
its impact (or both).
Transference: Shifting the consequence of a risk to another party together with the
ownership of the risk. Does not eliminate the risk, just transfers it.
Develop a sense of whether the potential risk is “triggered” by a particular event. For
example, the risk of not having sufficient staff at a critical point in a project is frequently
the result of one or several instances when key staff members were “temporarily”
redirected to help with other projects. Triggering events like these help to identify when it
is time to take action. That is, “What will need to be seen?” in the way of circumstances
to know that action is needed. Triggering events are recorded in the Risk Response Plan
and must be shared with the team members who will be responsible for monitoring the
onset of such events.
Purpose: To correct for deviations from the Risk Mitigation Plans and to provide
information on risk activities, current risks, and emerging risks. Risk control also
includes monitoring risk indicators and the effectiveness of mitigating actions. Risk
control could be done through:
The following questions can help determine the status of current risk activities and the
potential of emerging risks.
- Were the resulting response actions effective? Were they recorded (to capture the
learning experience)?
- To what extent has the risk exposure changed since the last review?
Tools:
- Standing agenda for project review meetings to discuss the Risk Management
Plan and the above-mentioned questions.
- Various existing project status reports that can be part of an “early warning”
system against the onset of a risk event.
The Risk Management Process varies over the course of Capital Project Management
Cycle. The risk management process evolves through three full cycles between Project
Planning (Phase “0”) and Project Closeout.
Both CPM and PERT were introduced at approximately the same time and share many
similarities. Both require identification of project activities, dependency relationships,
and time estimates for each activity.
Contrary to CPM, PERT introduces uncertainty into the estimates for activity and project
durations. It is well suited for those situations where there is either insufficient
background information to specify accurately utility data (time and cost) or where project
activities require research and development.
The primary assumption of PERT can be summarized as follows:
1. Any PERT path must have enough activities to make the central limit theorem valid.
2. The mean of the distribution of the path with the greatest duration, from the initial
node to a given node, is given by the maximum mean of the duration distribution of
the paths entering the node.
3. PERT critical path is longer enough than any other path in the network.
PERT uses three time estimates for each activity. Optimistic duration (a) is the minimum
time required for an activity if exceptionally good luck is experienced. Most likely or
modal time (m) is the time required if the activity is repeated a number of times under
essentially the same conditions. Pessimistic duration (b) is the maximum time required if
unusually bad luck is experienced. The beta distribution is mostly fit construction
activities.
Using beta distribution, the expected mean time (te) is derived using Eq.1. Then, te is
used as the best available time approximation for the activity in question. The standard
deviation is given by Eq.2, and standard deviation is the square root of the variance; (ν)
(i.e., ν = σ2).
a 4m b
te (4.1)
6
ba
(4.2)
6
The procedure for hand probability computations using PERT can be summarized
in the following steps:
1. Make the usual forward and backward pass computations based on a single estimate
(mean) for each activity.
2. Obtain estimates for a, m, and b for only critical activities. If necessary, adjust the
length of the critical path as dictated by the new te values based on a, m, and b.
3. Compute the variance for event x (νX) by summing the variances for the critical
activities leading to event x.
4. Compute Z using Eq.2.4 and look up the corresponding probability in the normal
curve table (Fig. 4.1 and Table 4.1).
Table 4.1: Area under the normal curve measured from the center
since the longest or critical path through the network may change as activity durations
change.
The disadvantage of Monte Carlo simulation results from the additional information
about activity durations that is required and the computational effort involved in
numerous scheduling applications for each set of simulated durations. For each activity,
the distribution of possible durations as well as the parameters of this distribution must be
specified.
The iterative procedure of Monte Carlo Simulation can be summarized in the following
steps and flowchart
1. Consider each risk variable as a random variable, and specify a suitable probability
distribution to represent each risk variable.
2. For each risk variable affecting activities’ durations, generate a Random Number
(RN),
3. Allocate the RN to the Cumulative Probability Distribution (CPD) curve of the risk
variable, and then determine the corresponding duration of all activities affected by
that risk variable,
4. Using new durations, perform network and resource analysis,
5. For each risk variable affecting activities or resources costs, generate a RN,
6. Allocate the RN to CPD curve of the risk variable, and then determine the
corresponding costs of all activities or resources affected by that risk variable,
-Risk contingency is an allowance decided based on the risk analysis to overcome any
unforeseen events that may increase time and/or cost. This can be easily calculated
after specifying the probability distribution of the performance criteria (Cumulative
Probability Distribution; CPD.)
-Procedure:
Choose p; acceptable probability of project cost (time) overrun.
Allocate p on the Cumulative Probability Distribution curve, and determine the
corresponding value; A.
Contingency = A – B, where B is the base estimate (time, cost)
CPD
p
50%
D J M
A C G L
B E H
F I
Project Data:
Duration Risk Variables
Activity te σ
a m b Min. % Max. % No.
A 6 12 30 14 4 -50 150 1
B 8 10 20 11.33 2 -20 100 2
C 3 21 40 21.17 6.17 -86 90 3
D 6 11 40 15 5.67 -46 163 4
E 12 15 20 15.33 1.33 -20 33 5
F 6 17 21 15.83 2.50 -65 24 6
G 6 12 25 13.17 3.17 -50 100 7
H 7 14 21 14 2.33 -50 50 8
I 25 30 40 30.83 2.50 -17 33 9
J 3 12 16 11.17 2.17 -75 33 10
K 1 1 1 1 --- --- --- ---
L 7 9 12 9.17 0.83 -22 33 11
M 6 9 11 8.83 0.83 -33 32 12
Sensitivity Analysis:
Risk Variable Project Duration Sensitivity
No. Lower Limit Upper Limit Index
1 57 81 24
2 63 67 4
3 57 82 25
4 63 63 0
5 63 63 0
6 63 63 0
7 63 66 3
8 63 63 0
9 58 73 15
10 63 63 0
11 63 63 0
12 63 63 0
14 29 29 40.17 30 38.83
D (15) J (11.17) M (8.83)
30.21 45.21 45.21 56.38 56.72 65.55
Network Example
Then the probability that a project ends in a specific time (t) equals number of times the
project finished in less than or Equal to t divided by the total number of replications. For
example, the probability that the project ends in 20 weeks or less is:
P( ≤ 20 ) = 13 / 50 = 26%.
Criticality Index
4.11 EXERCISES
1. All of the following are factors in the assessment of project risk EXCEPT:\
a. Risk event.
b. Risk probability.
c. Amount at stake.
d. Insurance premiums.
3. If a risk event has a 90% chance of occurring, and the consequences will be
LE10,000, what does LE9,000 represent?
a. Risk value.
b. Present value.
c. Expected monetary value.
d. Contingency budget.
4. All of the following are ALWAYS input to the risk management process
EXCEPT:
a. Historical information.
b. Lessons learned.
c. Work breakdown structure.
d. Project status reports.
10. Which of the following MUST be an agenda item at all team meeting?
11. Assuming that the ends of a range of estimate +/- 3ơ from the mean, which of the
following range estimates involves the LEAST risk?
a. 30 days, plus or minus 5 days.
b. 22 – 30 days.
c. Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days.
d. Mean of 28 days.
19. During project executing, a team member identifies a risk that I not in the risk
register. What should you do?
a. Get further information on how the team member identified the risk, because
you already performed a detailed analysis and did not identify the risk.
b. Disregard the risk, because risks were identified during project planning.
c. Inform the customer about the risk.
20. You identified a technical risk in your project and assigned a contingency for that.
Planning contingency reserves is part of which risk response strategy?
a. Active risk mitigation
b. Passive risk avoidance
c. Passive risk acceptance
d. Active risk acceptance
21. Recently, you were assigned to manage a project for your company. You have
constructed a network diagram depicting various activities in the project. In
addition, you asked various managers and subordinates to estimate the amount of
time they would expect each activity to take. Their responses (in days) were as
follows:
Duration (days)
Activity Optimistic Most likely Pessimistic
(a) (m) (b)
A 4 7 10
B 8 10 14
C 3 6 7
D 2 4 6
E 7 8 9
10
A C
D 40
5
B E
35
22. Consider the project given in the next table. Find the probability that the project
will be completed within 70 and 80 days. What is the project expected duration
corresponding to 70% assurance.
Duration (days)
Activity Optimistic Most likely Pessimistic Dependencies
(a) (m) (b)
A 10 16 22 -
B 24 32 42 -
C 22 32 40 A
D 12 16 21 B
E 20 25 35 C, D
F 13 16 19 A, B
23. The opposite Table shows the summary of a 10-simulation runs for a given
project. The run number, the critical path and the project completion time are
shown in the table below. Determine:
The probability of completing the project in 30 days.
The probability of completing the project in 23 days.
Draw the cumulative probability distribution curve of the project duration.
What is the criticality index of activities A and D.