2 Concrete Works MS
2 Concrete Works MS
Revision No. 0 A
Date 28-02-11 31-07-11
Revision History First Submission O/E comments incorporated
Prepared by Reviewed by Approved by
Approval By
(Section Head) (QA/QC In charge) (Project Manager)
Name CYN NKV NR
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 2 of 7
Method Statement
CONTENTS
1. Objective
2. Scope
3. Reference Documents
5. Responsibilities
6. Method / Procedure
7. Records
8. Attachments
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 3 of 7
Method Statement
1. Objective:
2. Scope:
This method statement is applicable for all activities related to the concrete works for
SEWA / TRANSCO Project, N-8033, New 132/33 kV Substation by LARSEN &
TOUBRO at Kalba.
3. Reference Documents:
4.3 Vibrators
4.9 Crane
5. Responsibilities:
5.1 Job Performer (Supervisor, Site Engineer & Construction Manager) shall be
responsible for the concrete works at site.
5.2 QA/QC Engineer shall be responsible for the QA/QC activities at site.
5.3 Safety Officer shall be responsible for the HSE activities at site.
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 4 of 7
Method Statement
6. Method / Procedure:
6.1 General
6.1.2 All materials identified / used for the permanent works shall be complied
with the approved documents by Owner / Engineer, prior to the
procurement.
6.1.3 All HSE activities related to concrete works shall be based on the Owner /
Engineer / Contractor HSE Management System Guidelines.
6.1.4 All quality assurance and quality control activities shall be in line with
contractor Civil Quality Management System and the specified
requirements of the contract, Project Quality Plan.
6.2.1 The Mix design and trial mix results of concrete grades as identified in the
specification / drawing shall be submitted to the Owner / Engineer for
approval. Upon approval, the approved mix design details shall be issued
to the concerned personnel / supplier for its production and supply. The
following is the list of grade of concrete which is identified as per the
specification.
6.2.2 The batching plant / supplier shall be also got approved by Owner /
Engineer.
6.2.4 Water tight formwork, true to the line, level, plumb and dimensions shall
be erected and the prefabricated re-bars shall be fixed in accordance with
the approved drawings. All the forms used shall be free from debris of
earlier concrete.
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 5 of 7
Method Statement
6.2.5 The formwork shall be made wet just before the commencement of
concreting and it shall be ensured that water is not pooling inside the
formwork area and all the reinforcement and embedded items are
adequately secured to prevent any movement during the concrete
placement.
6.2.7 Concrete shall be obtained only from the approved ready mix concrete
supplier and on receipt of concrete at site, it shall be discharged from the
transit mixer as rapidly as possible to its final position by approved
means. The concrete shall be placed and compacted within 90 minutes of
the water being added to the mix. Appropriate tools like concrete chute,
spout, skips and pumps shall be used for concrete placing.
6.2.8 Before placing the concrete, in-situ tests such as slump test and
temperature of concrete and ambient temperature shall be checked and
recorded for every concrete transit mixer. It shall be ensured that the
temperature of concrete does not exceed 30°C at the time of placing
concrete. Slump shall be above 175 mm for piling concrete and for all
other concrete generally not to exceed 100 mm to ensure proper
workability.
6.2.10 Concrete cubes casted at the point of placement shall be removed from
mould after 24 hrs and shifted to independent testing laboratory as soon
as possible. In case of any delay in shifting to laboratory, they shall be
stored in curing tank which is maintained at room temperature.
6.2.11 Concrete shall be placed in horizontal layers of not more than 300 mm
thickness each and shall not be allowed to fall freely over 2 m height. The
rate of delivery of concrete during concreting operations shall be such that
the intervals between the batches shall be minimized to avoid cold joints.
The concrete shall be compacted with sufficient mechanical vibrators to
get a compacted and dense concrete.
6.2.12 Top of concrete cast level shall be marked on the column reinforcement
bars / parapet reinforcement bars and the concrete shall be leveled to
match the levels marked. Concrete shall be leveled and finished as per
the levels indicated in the approved drawings and the fresh concrete shall
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 6 of 7
Method Statement
6.2.15 In case of horizontal / vertical joints, any excess water and laitance shall
be removed (chipped) from the surface before the concrete hardens in
order to make a suitable bond between the fresh and old one.
6.2.16 Once the concrete has stiffened, polythene sheet shall be replaced with
wet hessian cloth and water cured for the minimum of 7 days.
6.2.17 On completion of all concreting activities, the surplus materials and waste
materials shall be disposed at designated location.
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 7 of 7
Method Statement
7. Records:
8. Attachments
*******
Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR