2 Concrete Works MS

This document provides a method statement for concrete works for a new substation project. It outlines the objectives, scope, responsibilities, procedures, and references for the concrete works. The procedures describe preparing formwork, reinforcement, obtaining approved concrete mixes, transporting and placing concrete using pumps and other tools, conducting tests, and curing. The document is intended to describe the logical sequence of activities for the concrete works portion of the project.

Uploaded by

Ganesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
163 views7 pages

2 Concrete Works MS

This document provides a method statement for concrete works for a new substation project. It outlines the objectives, scope, responsibilities, procedures, and references for the concrete works. The procedures describe preparing formwork, reinforcement, obtaining approved concrete mixes, transporting and placing concrete using pumps and other tools, conducting tests, and curing. The document is intended to describe the logical sequence of activities for the concrete works portion of the project.

Uploaded by

Ganesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Larsen and Toubro Limited – ECC Division

New 132/33 kV Substation at Kalba


Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 1 of 7
Method Statement

Larsen and Toubro Limited


New 132/33 kV Substation at Kalba
Title: Concrete Works Method Statement
Procedure No.: MS/N-8033/C03

Revision No. 0 A
Date 28-02-11 31-07-11
Revision History First Submission O/E comments incorporated
Prepared by Reviewed by Approved by
Approval By
(Section Head) (QA/QC In charge) (Project Manager)
Name CYN NKV NR

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 2 of 7
Method Statement

CONTENTS

METHOD STATEMENT FOR CONCRETE WORKS

1. Objective

2. Scope

3. Reference Documents

4. Tools, Tackles, Equipments and Materials

5. Responsibilities

6. Method / Procedure

7. Records

8. Attachments

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 3 of 7
Method Statement

1. Objective:

The purpose of this Method Statement is to describe the logical sequence of


activities involved in the concrete works.

2. Scope:

This method statement is applicable for all activities related to the concrete works for
SEWA / TRANSCO Project, N-8033, New 132/33 kV Substation by LARSEN &
TOUBRO at Kalba.

3. Reference Documents:

TRANSCO Standard S-TR-CIVIL-CONCRETE (Rev. 0-2009), LARSEN & TOUBRO


Inspection & Test Plan and relevant drawings.

4. Tools, Tackles, Equipments and Materials:

4.1 Concrete pump

4.2 Transit mixer

4.3 Vibrators

4.4 Curing Pump

4.5 Masonry Tools (Straightedge, Float, Mason Trowel, Spirit Level)

4.6 Water tank

4.7 Air compressor

4.8 Laboratory Equipments (Cube Moulds, Tamping Rod, Slump Cone,


Thermometer)

4.9 Crane

4.10 Light in case of night work

5. Responsibilities:

5.1 Job Performer (Supervisor, Site Engineer & Construction Manager) shall be
responsible for the concrete works at site.

5.2 QA/QC Engineer shall be responsible for the QA/QC activities at site.

5.3 Safety Officer shall be responsible for the HSE activities at site.

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 4 of 7
Method Statement

6. Method / Procedure:

6.1 General

6.1.1 Prior to the commencement of all construction activities, necessary work


permit, if applicable shall be obtained.

6.1.2 All materials identified / used for the permanent works shall be complied
with the approved documents by Owner / Engineer, prior to the
procurement.
6.1.3 All HSE activities related to concrete works shall be based on the Owner /
Engineer / Contractor HSE Management System Guidelines.

6.1.4 All quality assurance and quality control activities shall be in line with
contractor Civil Quality Management System and the specified
requirements of the contract, Project Quality Plan.

6.2 Concrete Works

6.2.1 The Mix design and trial mix results of concrete grades as identified in the
specification / drawing shall be submitted to the Owner / Engineer for
approval. Upon approval, the approved mix design details shall be issued
to the concerned personnel / supplier for its production and supply. The
following is the list of grade of concrete which is identified as per the
specification.

Concrete for blinding Concrete Grade 20 (i.e. C28 = 20 N/mm2)


Flooring screed in case of no tiling Concrete Grade 35 (i.e. C28 =35 N/ mm2)
Concrete for piling Concrete Grade 40 (i.e. C28 = 40 N/mm2)
Concrete for foundations and pile caps Concrete Grade 40 (i.e. C28 = 40 N/mm2)
Protection/sloping cement screed Concrete Grade 20 (i.e. C28 = 20 N/mm2)
Beams, slabs, columns Concrete Grade 40 (i.e. C28 = 40 N/mm2)
Prefabricated units Concrete Grade 40 (i.e. C28 = 40 N/mm2)
Hollow Core Units Concrete Grade 50 (i.e. C28 = 50 N/mm2)

6.2.2 The batching plant / supplier shall be also got approved by Owner /
Engineer.

6.2.3 All the ingredients of concrete, including admixtures shall be approved by


the Owner / Engineer prior to trial mix.

6.2.4 Water tight formwork, true to the line, level, plumb and dimensions shall
be erected and the prefabricated re-bars shall be fixed in accordance with
the approved drawings. All the forms used shall be free from debris of
earlier concrete.

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 5 of 7
Method Statement

6.2.5 The formwork shall be made wet just before the commencement of
concreting and it shall be ensured that water is not pooling inside the
formwork area and all the reinforcement and embedded items are
adequately secured to prevent any movement during the concrete
placement.

6.2.6 On completion of inspection and subsequent approval by the Owner /


Engineer, concreting shall be carried with the specified grade of concrete
as indicated in the drawings / specification.

6.2.7 Concrete shall be obtained only from the approved ready mix concrete
supplier and on receipt of concrete at site, it shall be discharged from the
transit mixer as rapidly as possible to its final position by approved
means. The concrete shall be placed and compacted within 90 minutes of
the water being added to the mix. Appropriate tools like concrete chute,
spout, skips and pumps shall be used for concrete placing.

6.2.8 Before placing the concrete, in-situ tests such as slump test and
temperature of concrete and ambient temperature shall be checked and
recorded for every concrete transit mixer. It shall be ensured that the
temperature of concrete does not exceed 30°C at the time of placing
concrete. Slump shall be above 175 mm for piling concrete and for all
other concrete generally not to exceed 100 mm to ensure proper
workability.

6.2.9 Samples on each day of concreting at the point of placement shall be


taken. One set of six (6) test cubes for every 100m³ or every daily pour of
concrete shall be taken for each grade of concrete for conducting
compressive strength tests. Bimonthly or for every 750 m³ of concrete
cast, 12 test cubes shall be taken for conducting the durability tests. (1 no.
for rapid test for chlorides, 1 no. for rapid test for sulphates, 3 nos for
water absorption test, 3 nos for water penetration test and 4 nos. for rapid
chloride permeability test.)

6.2.10 Concrete cubes casted at the point of placement shall be removed from
mould after 24 hrs and shifted to independent testing laboratory as soon
as possible. In case of any delay in shifting to laboratory, they shall be
stored in curing tank which is maintained at room temperature.

6.2.11 Concrete shall be placed in horizontal layers of not more than 300 mm
thickness each and shall not be allowed to fall freely over 2 m height. The
rate of delivery of concrete during concreting operations shall be such that
the intervals between the batches shall be minimized to avoid cold joints.
The concrete shall be compacted with sufficient mechanical vibrators to
get a compacted and dense concrete.

6.2.12 Top of concrete cast level shall be marked on the column reinforcement
bars / parapet reinforcement bars and the concrete shall be leveled to
match the levels marked. Concrete shall be leveled and finished as per
the levels indicated in the approved drawings and the fresh concrete shall

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 6 of 7
Method Statement

be covered immediately after pouring with a polythene sheet to avoid the


loss of moisture.

6.2.13 In case of concreting in hot weather, the hot weather concreting


recommendations shall be followed to lower the temperature of concrete
such as:

6.2.13.1 Cooling coarse aggregate with water by sprinkling and shading

6.2.13.2 Using chilled water

6.2.13.3 Using crushed ice

6.2.13.4 Avoiding the use of hot cement

6.2.13.5 Shading mixer drums, facilities and material by use of


permanent wet burlap coverings

6.2.13.6 Adequately watering of sub grade, form work and


reinforcement

6.2.13.7 Insulating water supply lines and tanks and or painting


exposed portions white

6.2.13.8 Working only at cooler daytime

6.2.13.9 Covering freshly poured concrete with polythene sheets

6.2.13.10 Intensive moist curing with potable water of the concrete


placed

6.2.14 If any construction / expansion joint are to be introduced, concreting shall


be carried out continuously up to the construction / expansion joints.

6.2.15 In case of horizontal / vertical joints, any excess water and laitance shall
be removed (chipped) from the surface before the concrete hardens in
order to make a suitable bond between the fresh and old one.

6.2.16 Once the concrete has stiffened, polythene sheet shall be replaced with
wet hessian cloth and water cured for the minimum of 7 days.

6.2.17 On completion of all concreting activities, the surplus materials and waste
materials shall be disposed at designated location.

6.2.18 Removal of formwork shall be as approved by TRANSCO at site, and


shall be effected in such a manner that no damage is caused to the fresh
concrete. The minimum duration for removal of form work shall be as
follows:

6.2.18.1 Beams, Walls, Columns, beams (Vertical faces): 24 hours

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Concrete Works
MS/N-8033/C03 Page 7 of 7
Method Statement

6.2.18.2 Soffits to slabs: 7 days

6.2.18.3 Props to slabs, etc.: 14 Days

6.2.18.4 Soffits to beams, frames, etc.: 14 days

6.2.18.5 Props under beams, frames, etc.: 21 days

7. Records:

7.1 Request for Inspection

7.2 Checklist for Concrete Works

7.3 Concrete Batch Ticket Report

7.4 Concrete Placement Record

7.5 Summary of Concrete Test Results

8. Attachments

8.1 Concrete Works Inspection Test Plan

8.2 Concrete Works Checklist

8.3 Concrete Works Hazard Identification, Risk Assessment

*******

Revision No. 0 A
Date 28-02-11 31-07-11
Approved by NR NR