Labor Format

The document contains labor cost calculations for rebars, formworks, and CHB wall construction of a building with floors from 2F to 5F and a roof deck. It lists the number of days, labor rates, and resulting labor costs for installing rebars and formworks on each floor. It also provides calculations for the labor costs of CHB laying and plastering on each floor, including number of required masons and helpers based on total number of days and target duration. The total labor costs calculated are ₱369,000 for rebars, ₱594,000 for formworks, and ₱555,300 for CHB walls.

Uploaded by

John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views2 pages

Labor Format

The document contains labor cost calculations for rebars, formworks, and CHB wall construction of a building with floors from 2F to 5F and a roof deck. It lists the number of days, labor rates, and resulting labor costs for installing rebars and formworks on each floor. It also provides calculations for the labor costs of CHB laying and plastering on each floor, including number of required masons and helpers based on total number of days and target duration. The total labor costs calculated are ₱369,000 for rebars, ₱594,000 for formworks, and ₱555,300 for CHB walls.

Uploaded by

John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

REBARS

Labor Cost = Total No. of Days x Rate per Day


Rate
Floor Structure Total No. of Days Labor Cost
per day
Column 62.997 = 63 600.00 ₱ 37,800.00
2F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
3F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
4F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
5F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
RD Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
TOTAL ₱ 369,000.00

FORMWORKS
a.) Labor Cost = No. of Manpower x Rate x Duration

Area No. of Rate Duration


Floor Labor Cost
(sq.m.) Manpower per day (days)

2F 331.9 33 600.00 6 ₱ 118,800.00


3F 331.9 33 600.00 6 ₱ 118,800.00
4F 331.9 33 600.00 6 ₱ 118,800.00
5F 331.9 33 600.00 6 ₱ 118,800.00
RD 331.9 33 600.00 6 ₱ 118,800.00
TOTAL ₱ 594,000.00
CHB WALL
a.) Labor Cost = No. of Manpower x Rate x Duration
Rate Duration
Floor Activity Manpower No. of Manpower Labor Cost
per day (days)
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
2F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
3F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
4F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
5F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 10 600.00 2 ₱ 12,000.00
CHB Laying
Helper 3 500.00 2 ₱ 3,000.00
RD
Mason 13 600.00 3 ₱ 23,400.00
Plastering
Helper 3 500.00 3 ₱ 4,500.00
Subtotal 5 ₱ 42,900.00
TOTAL ₱ 555,300.00

Computation

b.) Total No. of Days = Area x Accomplishment/day


Area Accomplishment per
Floor Activity Total No. of Days
(sq.m.) day
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
2F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
3F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
4F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
5F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 144.2 8 sq.m./day 18.03 = 19 days
RD
Plastering 377.2 10 sq.m./day 37.72 = 38 days

c.) Total No. of Mason = Total No. of Days / Target Duration


Total No. of Helper
Floor Activity Target Duration Total No. of Masons
Days (for bagger mixer)
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
2F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
3F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
4F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
5F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 19 days 2 days 9.50 = 10 masons + 3 helpers
RD
Plastering 38 days 3 days 12.67 = 13 masons + 3 helpers
49 days