Risk Assessment Fitout Salon
Risk Assessment Fitout Salon
Risk Assessment Fitout Salon
RISK ASSESSMENT
For Fitout works
Reviewed & Approved By: MITHUN JOSEPH Signature: Review Date: 31/07/2022
Catastrop
Insignificant Minor Moderate Major
Description Consequence (Table 1 – Area Impacted) hic
(1) (2) (3) (4)
(5)
Likelihood Insignificant Minor Moderate Major Catastrophic Minor injuries, Injuries requiring Serious injuries Single Multiple
(1) (2) (3) (4) (5) which may on-site treatment requiring off-site fatality fatalities
Rare (1) 1 2 3 4 5 require self- by medical treatment by medical
administered practitioner. practitioner or
Possible (2) 2 4 6 8 10 first aid. Personnel unable to immediate evacuation
Injured continue to perform to hospital. Potential
Likely (3) 3 6 9 12 15
personnel can duties. long-term or
continue to permanently disabling
Often (4) 4 8 12 16 20 perform effects.
normal duties
Frequent (5) 5 10 15 20 25 Consequence (Table 1 – Area Impacted)
15-25 Extreme Risk Activity or industry should not proceed in current form.
Activity or industry should be modified to include Rare Possible Likely Often Frequent
8-12 High Risk
remedial planning and action. (1) (2) (3) (4) (5)
Moderate Activity or industry can operate subject to management Never Has occurred Has occurred more Occurs Occurs
4-6
Risk and / or modification. occurred than once several frequently
No immediate action required, unless escalation of risk is times
1-3 Low Risk
possible. per year
Risk Rating Likelihood
Risk Rating Code: E - Extreme Risk, H – High Risk, M – Moderate Risk and L – Low Risk
Routine (R)/ Groups Exposed Residual
Hazards Risk Rating
Non-Routine (Including Numbers Existing Control Measures Additional Controls Required Risk Rating
(N) And Patterns) L C RL L C RL
HEALTH & SAFETY RISK
Delivery & ASSESSMENT
unloading of Persons handling Supervisors & operators are there to 4 3 12 Special emphasis on strict 1 3 3
civil materials, paint, removal & ensure that there is suitable number adherence to PPE
tools, joineries & disposal, workers of persons to carry out loading. H Proper communication L
accessories at the site are at Material is to be stored in a between the employees
risk. suitable area of the shop.
Ensure required PPE is worn
Severe
by the engaged personnel to
Shifting of materials using personnel
prevent any injury.
trolley injury or
Toolbox talk to be conducted
Fatality
before starting each project
Hit by falling Property
& recorded by the site
object -Slip/trip & damage
fall supervisor to ensure all
Fracture &
Fall of materials & tools safety precautions have been
Musculo
during transportation addressed to the work force.
skeletal
Use trolleys or other
disorders
mechanical aids for
affecting
transporting debris
back,
Ensure the capacity to carry
neck,
out the task.
shoulders,
arms &
hands
Cut bruise
hand
injury due
to sharp
edges.
Transportation of Persons Supervisors & 4 3 12 Special emphasis on strict 1 3 3
Materials to the required responsible for operators are there adherence to PPE
area. removal of to ensure that there H Proper communication L
HEALTH & SAFETY RISK ASSESSMENT is suitable number of between the employees
materials to the
persons to carry out Supervision
site are at risk. unloading. Inspection & Audit
Personnel injury,
Material is to be
Fatality or
stored in a suitable
Property damage area. Electrical pipes
are to be stacked on
its long edge if
possible a maximum
of 10 pieces in each
stack.
Toolbox talk to be
conducted &
recorded by the site
supervisor to ensure
all safety precautions
have been addressed
to the work force.
Installation of water Support Staff Trained, experienced 3 2 6 Special emphasis on strict 1 2 2
proof, screeding, tiles, &Workers & competent adherence to PPE
gypsum wall claddings & handling the workers to be M Proper communication L
HEALTH & SAFETY RISK ASSESSMENT assigned for the task. between the employees
ceiling materials & tools
Supervision
are at risk Inspection & Audit
Use of power tools Portable compound
(DRILLING MACHINE) power tools are
regularly maintained
Exposure to to help minimise the
Rotating or risk of exposures to
hazards.
moving parts:
Engineering controls
such as mandatory
machinery guarding
or any protective
safety screens &
enclosures are in
place in all
workspaces & all in
good working
condition.
Good lightings is
provided to minimise
these hazards.
All approved
protective
equipments (PPE) is
used where required.
Vacuumed to be
used with all
machines while
HEALTH & SAFETY RISK ASSESSMENT producing dust.
Introduce a system of
periodic inspection of ladder
dependent on use & keep
records of inspection. A
peruse checklist & monthly
inspection checklist shall be
maintained.
All ladders to be positioned
HEALTH & SAFETY RISK ASSESSMENT on the even surface with
sufficient free space. Inspect
the ladder for defects before
use.
Do not use a ladder if a ring is
missing or defective.
Site made or homemade
ladder shall not be used.
Slope of the straight ladder
shall not be less than 75
degree
Tie the ladder on top &
bottom.
One person should hold the
ladder at all times.
Avoid straight ladders, only
step ladders to be used along
with scaffolding.
Do not use last 2 steps of the
ladder.
More than one person shall
not use a ladder at the same
time.
Lock the ‘A’ frame ladder
before use & don’t over
reach.
Scaffolding is inspected Inspection & Audit 1 2 2
HEALTH & SAFETY RISK ASSESSMENT during construction and once Supervision
Use of scaffolding Fall from height complete by an individual 3 2 6 L
with a scaffolding licence Wear appropriate PPE (
Working at height Falls of materials Maximum weight of M Helmet, Goggles, Gloves,filter
scaffolding is agreed upon mask)
Manual handling
prior to set-up of scaffold
Full or partial Scaffolding to be secured to
collapse/ prevent unauthorised access
structural failure Scaffolding is inspected for
defects or damage prior to
Overloading of use
scaffold Scaffolding is inspected after
repairs have been made
Scaffolding is inspected every
seven days
Scaffolding to be erected and
dismantled by a contractor
with a scaffolding licence
Agree weight/strength
specification of scaffolding
with scaffolding contractors
before engaging them to
erect scaffolding on site
Maintain awareness of total
weight on scaffold, including
employees
Under no circumstances are
employees to alter
scaffolding erected by
contractors
Employees to use the correct
HEALTH & SAFETY RISK ASSESSMENT manual handling techniques
at all times
Scaffold construction area to
be isolated and cleared of all
persons
Use Personal Protective
Equipment (PPE) such as
appropriate gloves, head
protection and safety
footwear
Employees have completed
Work Safely at Heights
Training Course
An emergency rescue plan
has been established
Manual handling training for
all employees (eLearning)
Use fall arrest equipment
(harness)attached at all times
to the scaffold when working
Inspection & Audit 1 3 3
HEALTH & SAFETY RISK ASSESSMENT Supervision
Trained, competent &
Water proofing works Hazards 2 3 6 L
physically fit personnel to be Wear appropriate PPE (
associated with engaged in water proofing &
Tile cutting while tile H Helmet, Goggles, Gloves,
toxicity and painting works
installation filter mask)
flammability Ensure that the proper
Painting works including wearing of PPE specially filter
spray painting Skin problems mask
Restrict employee access to
Respiratory areas where spray painting is
problems being carried out
Clean-up kits should be at
hand to quickly deal with any
spillages, and should include
absorbent granules to soak
up liquid.
Keep the paint drums closed
when not in use
Ensure adequate ventilation
at the time of spray painting
Use filter mask while mixing,
application & disposal
2 3 6