Method Statement For GI
Method Statement For GI
1. Purpose
Procedure will ensure that all concerned persons are familiar with the
sequence of activities, utilization of resources, and execution of the
works in compliance with applicable project safety and quality
procedural requirements, project legal documents and specifications.
4. Reference
Contract Specifications
Approved Drawings
Project Quality Plan
Project HSE Plan
5. Definitions
PVC: Polyvinylchloride
6. Resources
Bending machine
Die sets
Measuring tape
Screw driver
Chalk mate thread
Oil
Drill machine
Screw driver
Necessary measures will be taken for the safety of the equipment and
any other works affected by the works covered in this document.
The works covered under this document require that the PPE must be
used as required.
First Aid
The contractor’s vehicle assigned to the job site will be used for
transporting the injured person to the first aid station and to the
nearest hospital when required.
Architectural Drawing
Identify the circuit start point and end points to mark the conduit
route as per approved drawings.
Make hole in wall/concrete using drill machine for rawal plug, fix
rawal plug inside hole and then fix base of saddle by screw at every 2
meter span.
Install conduits and all accessories as per approved shop drawing and
tight with saddle and screw, make joints using threaded fittings.
Installation of GI conduits shall be checked by internal quality
engineer as per drawings and quality of installation before offering
consultant/client for inspection.
Maximum spacing of
supports for different
conduit sizes to be clarified.
Method statement for conduit installation (GI Box & GI/PVC Conduit in Walls)
Executed works in areas where other works are still being carried out
shall be protected as per the contract requirements.
An inspection request for the PVC & GI conduits and boxes shall be
submitted one day prior to the consultant.
Attachments