50 MCQs SAMPLE For Project Management
50 MCQs SAMPLE For Project Management
Course MMS
Semester IV
Subject-Project Management
1. Which one of the following is captured in the Work Breakdown Structure (WBS)?
A.The life cycle phases
B.The logical order of tasks
C.The scope of the project
D. Project costs
2. Which stage of project management life cycle requires the maximum time of completion
A.Conceptualization
B. Planning
C. Execution
D. Estimation
3. .In Project management when does planning take place?
A.Before the project
B.During the project execution
C.At the start of the project
D.After the project
4 .In the initial stage of the project the probability of completing the project is ___ . A.Zero
B.High
C.Low
D.Medium
9. The time with which direct cost does not reduce with the increase in time is known as
A.crash time
B.normal time
C.optimistic time
D.standard time
10. The time corresponding to minimum total project cost is
A.crash time
B.normal time
C.optimistic time
D.between normal time and crash time
30. Project Manager must ensure that it develops appropriate trade off/s as
A. Time, cost and performance
B. Time, value and performance
C.Men, Materials and Machines
D.Money, Cost and Return on Investment
31. Who orchestrate the completion of the project by inducting the right people at the right time to address the
right issue and make the right decisions?
A.Project Coordinator
B.Project Manager
C.Operations Manager
D.Strategic Business Unit Head
33.In which stage of team development, team members are worried about how they fit in with the others and how their
capabilities and skills compare.
A.Norming
B.Storming
C.Forming
D.Performing
34 Which of the following represents the estimated value of the work actually accomplished?
A. Earned value (EV)
B. Planned value (PV)
C. Actual cost (AC
D. Cost variance (CV)
35. A schedule performance index (SPI) of 0.76 means:
A. You are over budget
B. You are ahead of schedule
C. You are only progressing at 76 percent of the rate originally planned
D. You are only progressing at 24 percent of the rate originally planned
36. A cost performance index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89 percent more than planned
B. When the project is completed we will have spent 89 percent more than planned
C. The project is only progressing at 89 percent of the rate planned
D. The project is only getting 89 cents out of every dollar invested
37. The cash inflows and (outflows) associated with a project are as follows:
At start (120000) , Year1-40000, Year2-50000, Year3-60000, Residual Value(at the end of 3rd year)-20000. The
payback period for this project would be:
A 2 years and 3 months.
B 2 years and 6 months.
C 3 years.
D 2 years.
38: A Firm is considering undertaking a project that would yield annual profits (after depreciation) of Rs 68,000 for 5
years. The initial outlay of the project would be Rs 800,000 and the project's assets would have a residual value of Rs
50,000 at the end of the project. What would be the accounting rate of return for this project?
A 16%
B 8.5%
C 8.0%
D 9.1%
39.A firm is about to undertake a project and has computed the NPV of the project using a variety of discount rates:
Discount Rate used NPV
10% 130
15% 50
20% -50
What is the approximate IRR of this project?
A 20%
B 17.5%
C 15%
D 22.5%
40. A project has a 60% chance of a $100,000 profit and a 40 per cent of a US $100,000 loss.
The Expected Monetary Value for the project is A. $100,000 profit
B. $60,000 loss
C. $ 20,000 profit
D. $40,000 loss
41. In a payback period method of project evaluation and appraisal the project with
……………….or equal to cut off period will be accepted.
A. More than
B. Less than
C.Positive
D. Negative
42. A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was
carried out at end of 60 weeks and results are as given:
Budgeted cost of work performed (EV) = 17 crores Actual Cost of work performed (AC = 19 crores Budgeted
cost of work scheduled (PV) = 21 crores What is the cost performance index?
A.0.895
B.0.81
C.0.90
D.1.12
43. In which of the following cases project is in better shape?
A.When both CPI and SPI are less than 1
B.When CPI is more than 1 and SPI is less than one
C.When CPI is less than one and SPI is more than one
D.When both CPI and SPI are more than one
44. A company is considering investing surplus funds in a project. Calculate the NPV at 10 % discount rate for the
following data
Project Year 0 Year 1 Year 2
A (100) 100 100
A. 73.5
B. 173.5
C. 273.5
D. 100
45. Amount of work completed to date compared with planned in the Earned Value Management method is .
A. Schedule Performance Index
B. Cost Performance Index
C. Percentage Complete
D .Percentage Spent
46. The budgeted cost for all the activities in a project with the help of Earned Value Method is
A. Actual Cost
B. Budget at completion
C. Budget for completion
D. Estimate at completion
d) All of these
Answer: d
Answer : b
Answer : d
c) Psychological risks
Answer: d
5. What are the policies that influence access to finance in context of Innovative entrepreneurship?
a) Debt financing
b) Venture capital
c) Business Angels
d) All of these
Answer: d
a) Debt
b) Equity
c) Stock
d) None of these
Answer: b
7. Which of the following possible financing options has become a popular choice for entrepreneurs?
a) Angel investor
b) Credit cards
c) Venture capital
d) Public offering
Answer: b
a) To make money
b) To be independent
c) To be famous
d) To be powerful
Answer: b
b) Take-over of a competitor
c) Issuing shares
Answer: d
10. The resistance of employees in an organization against flexibility, growth, and diversification can be
overcome by developing_____________.
a) Entrepreneurship
b) Managerial domain
c) Intrapreneurship
d) Administrative domain
Answer: c
a) Innovation
b) Business model
c) Modeling
d) Creative flexibility
Answer: a
d) None of these
Answer: D
a) To make money
b) To be independent
c) To be famous
d) To be powerful
Answer: b
b) Take-over of a competitor
c) Issuing shares
d) Development of an organization
Answer: a
a) Innovation
b) Business model
c) Modeling
d) Creative flexibility
Answer: a
16. The activity which occurs when the new venture is started is called -
a) Motivation
b) Business skills
c) Departure point
d) Goal orientation
Answer: c
17. Having less than 50 percent of equity share in an international venture is calleda) Minority interest
b) Joint venture
c) Majority interest
d) Exporting
Answer: a
18. Bankers say that most businesses fail because of the _________ inability to plan properly.
a) Investors
b) Marketers
c) Entrepreneurs
d) Consultants
Answer: c
d) Economic conditions
Answer: d
20. What is the most common reason given for why people choose to become entrepreneurs?
Answer: c
21. _____ is the position of a firm on a continuum ranging from highly conservative to highly entrepreneurial.
a) Risk tolerance
b) Entrepreneurial intensity
c) Inventiveness
d) Organizational bureaucracy
Answer: b
22. Some entrepreneurs report that the financial rewards associated with entrepreneurship can be bittersweet
if they are accompanied by________.
c) motivating factors
Answer: d
c) Avoidance
d) Both b & c
Answer: a
a) Existing entrepreneurs
Answer: c
25. Fiscal and monetary measures to stimulate investment in private & public sector includes______________
d) All of these
Answer : d
26. Why should an entrepreneur do a feasibility study for starting a new venture?
Answer: a
27. Which of the following factor has allowed small companies to act like they are big ones?
a) Technology
b) Customers
c) Economic development
d) Competition
Answer: a
Answer: a
a) The act of initiating, creating, building, expanding and sustaining a venture and gathering The necessary resources
to exploit an opportunity in the marketplace for long-term wealth and capital gain
b) The act of creating, building, expanding and sustaining a venture, building an entrepreneurial team and gathering
the necessary resources to exploit an opportunity in the marketplace for long-term wealth and capital gain
c) The act of initiating, creating, building, expanding and sustaining a venture, building an entrepreneurial team and
gathering the necessary resources to exploit an opportunity in the marketplace for long-term wealth and capital gain
Answer: c
30. A women Entrepreneur is supposed to have a minimum financial interest in share capital of
entrepreneurial enterprise:
a) 35 per cent
b) 51 per cent
c) 25 per cent
Answer: b
31. Sustainability of entrepreneur development depends on factors like_______________
a) Technical skills
b) Technology
c) Organizational sustainability
d) All of these
Answer : d
investment
d) None of these
Answer: a
34. __________________ are the informal associations of people who choose to come together to find ways to
improve their living condition
a) NGO
b) Self-Help Groups
c) Private companies
d) None of these
Answer: b
35. The activity which occurs when the new venture is started is called:
a) Motivation
b) Business skills
c) Departure point
d) Goal orientation
Answer: C
36. Having less than 50 percent of equity share in an international venture is called:
a) Minority interest
b) Joint venture
c) Majority interest
d) Exporting
Answer: a
a) Entrepreneurship
b) Intrapreneurship
Answer: b
38. Individuals influencing an entrepreneur’s career choice and style are known as which of the following?
a) Role model
b) Moral-support network
d) Support system
Answer: a
39. Industry analysis should include information on –
d) Economic conditions
Answer: d
40. We need to update the business plan because
a) Environmental factors and internal factors can change the direction of the plan
Answer: a
41. From the following which one is not classification of entrepreneurs according to the types of business?
a) Wholesale trade
b) Retail trade
c) Exporter
d) Rural entrepreneur
Answer: d
42. What is the process by which individuals pursue opportunities without regard to resources they currently
control?
a) Startup management
b) Entrepreneurship
c) Financial analysis
d) Feasibility planning
Answer: b
a) Service businesses
b) Manufacturing companies
c) Constructive companies
d) A variety of ventures
Answer: d
Answer: a
45. Influence on innovation and job creation best typifies entrepreneurial firms'________.
a) Impact on society
b) Economic impact