Principle of Power Generation
Principle of Power Generation
Principle of Power Generation
can be obtained.
1
allowed to impinge energy on the blades through penstocks, thus
station.
also include the study of rainfall, run off and stream flow
available head and its limitations and facility for storage and
because the reserves of fuels (i.e coal and oil) are depleting daily.
2
Below is the schematic diagram of high Hydro- Electric
Station
Advantage
3
1. It requires no fuel as water is used for the generation of
electrical energy
maintenance
control.
Disadvantage
plant.
located in highly hillly areas which are quite away from the
consumer.
4
CHOICE (SELECTION) OF SITE FOR HYDRO-ELECTRIC
POWER STATION
cost
transported.
consumption period.
5
FORMATION OF HYDRO-ELECTRIC POWER STATION
- Hydraulic structures
- Water turbines
- Electrical equipment
Solution
6
convert the mechanical energy developed into electrical energy. It
power source in which the heat for ignition the fuel is obtained
from the compression of air in the engine cylinder before the fuel
turbine with small power stations and its therefore used as stand
7
a high temp without creating high vapour pressure which is used
Hot metal
8
They are available plentiful but very expensive. The process
1
In this process 1000th of the original mass is converted heat.
of 140 parts mined of mined U35, only one part can undergo
fission. But the U35 is burnt in air with natural U35 to convert
breeder reactor. The heat in the hot metal is exchanged to the gas
velocity.
work properly.
9
The following are the characteristic of a nuclear power station:
reactor.
bombardment.
system.
energy level.
10
The generation of power by magnetohydro station (MHD)
conductor.
11
BASIC PRINCIPLE OF MHD GENERATOR
preceding page.
gas. The chamber is also supplied with compressed air. The gas
12
flow of current in the electric circuit. An inverter is used to
high grade cool estimate at about 1307 million tones. There is the
follow:
13
TRANSMISSION AND DISTRIBUTION OF ELECTRICAL POWER
the above figure how power is supplied from the generator, say
14
primary distribution. Secondary is at 415/240V, where voltage is
UK : 50H Z
USA: 60HZ
15
MAJOR COMPONENTS IN A TYPICAL POWER SYSTEM
LAYOUT
2. Step – up Transformers
4. Busbars
5. Transmissions Lines
6. Distributions lines
16
computerized control of all grid operations, which the old
The operators will also have at their disposal the grid data with
load centres via grid lines, which are high voltage levels of 330kv
criteria.
17
Transmission losses in 1998 has been estimated to be 9.77% of
CONSUMPTION
voltage from 132kv to 33kv and 11kv levels. The 33kv lines are
then used to convey power to urban and rural areas and also
18
voltage is finally stepped down to 415/240V using distribution
LOAD CURVE
time in hours. The load curve shows the variation of load on the
varies from time to time. These load variations during the whole
19
THE IMPORTANCE OF LOAD CURVE
should be run.
expansion
6. The area under the daily load curve gives the number of
8. The area under the daily load curve divided by the total
day i.e
20
:- Average load = Area in (kwhr) under daily load curve
24 hours
The ratio of the area under the load curve to the total area of
Maximum Demand
Average load x 24
Max. demand x 24
contained
factors are
- Demand factors
- Average demand
21
- Connected load
- Maximum demand
product of plant capacity and the number of hours for which the
of time.
Connected load
22
Daily average load = No of units (kwhr) generated in a day
24 hours
No of hours in a month
No of hours in a year
24 x 365
23
Base load – base load is the load below, which the demand never
fails and must be supplied 100% of all the time. The power plants
use to supply the load at the base portion of the load curve. This
and Nuclear power station are often used to provide base loading
requirement.
intermediate load.
Peak load: Peak load is the load that will satisfy the maximum
should be for a short period in the whole year. Gas turbine units,
24
requirements. Gas turbine generating units are popular because
Max . demand
generated in a year.
Solution:
25
Example:
Demand factor 20
(I) Connected load
=max . dm= =20.4565
43
Units generate/annum
(II) Average demand = hours ∈a year
6
61.5 x 10
=7020 kw
8759
Solution
A . D( Average demand)
Load factor = M . D(Maximum Demand )
500,000
Load Factor = 100 x 365 x 24 =57.1 % (¿ 0.571)
26
Examples: A power station has to supply load as follows:
Time 0–6 6 – 12 12 – 14 14 – 18 18 – 24
(hours)
30 90 60 100 50
Solution
Example:
27
b. 100kw between 6 am and 10 am
c. 50 kw between 6 am and 10 am
1. Diversity factor
3. Load factor
Solution
(Hours)
(kw)
A -
B - 100kw 100kw - -
C - 50 kw 50 kw - -
28
Sum of individual max demand of groups = 200 + 100 + 150 +
100 = 400 kw
= 1.286
LINE SUPPORTS
properties:-
29
Cheap in cost and economical to maintain
as an economical proposition.
30
Steel Poles:- The steel poles are often used as a substitute for
(i) Rail Poles (ii) Tubular Poles (iii) Rolled Steel joints
than steel poles: Moreover, they give good out look, require. Little
the poles facilitate the climbing of poles and at the same time
reduce the weight of line support. The main difficulty with the
31
11kv. However, for long distance transportation at higher voltage,
climate conditions and permit the use of longer spans. The risk of
protection covers.
32
requirements. In general, a cable must fulfill the following
necessary requirements.
current.
2. The conductor size should be such that the cable carries the
which it is designed.
it.
CONSTRUCTION OF CABLES
Armouring.
33
1. Cores or conductor:- A cable may have one or more than
compound.
34
not be out of place to mention have that bedding, armouring are
injury.
cables
handling cables.
It should be non-inflammable.
35
36