Descriptions Crew Unit Unit 1 Bar Bending Works Item Nos Crew Nos Production Per 8hrs Production Per Hrs

Download as xls, pdf, or txt
Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1/ 8

Item crew Production Production

Descriptions crew Unit Unit


Nos nos per 8hrs per hrs
1 Bar Bending Works
Slab & Beam Fiter 1 170 Kg/day 21.25 Kg/hrs
Helper 1.5
Footing Fiter 1 200 Kg/day 25 Kg/hrs
Helper 1.5

2 Formwork Fixing & is a Removal


Slab & Beam Carpenter 1 5 Sqm/day 0.625 Sqm/hrs
Helper 1.5
Footing Carpenter 1 7 Sqm/day 0.875 Sqm/hrs
Helper 1.5
Column box fix Carpenter 1 20 Sqm/day 2.5 Sqm/hrs
Helper 2
Column Starter fix Carpenter 1 6 Nos/day 0.75 Nos/hrs
Helper 2
3 Formwork Making
Beam Side Carpenter 1 6 Sqm/day 0.75 Sqm/hrs
Helper 1
Column box fix Carpenter 1 3 Sqm/day 0.375 Sqm/hrs
Helper 1
Starter Carpenter 1 5 Nos/day 0.625 Nos/hrs
Helper 1
4 Concrete
Slab & Beam Mason 1 20 M3/day 2.5 M3/hrs
Helper 1
5 Block Mason 1 6 M2/day 0.75 M2/hrs
Helper 1.5
6 Plastering
Internal Mason 1 10 M2/day 1.25 M2/hrs
Helper 1.5
External Mason 1 12 M2/day 1.5 M2/hrs
Helper 1.5
Ceiling Mason 1 12 M2/day 1.5 M2/hrs
Helper 1.5
Corner beading fixing Mason 1 7 Nos/day 0.875 Nos/hrs
Helper 1
Mesh fixing & packing Mason 1 60 Running ft/d 7.5 Running ft/hrs
Helper 1.5
7 Earth Works Excavation
Manual Excavation DL 2 2.83 M3/day 0.35375 M3/hrs
Machine Operated 60 M3/day 7.5 M3/hrs
8 Water Proofing
horizontal membrane application applicator 1 150 m2/day 18.75 m2/hrs
Helper 1
vertical membrane application applicator 1 50 m2/day 6.25 m2/hrs
Helper 2
brush on application applicator 1 20 m2/day 2.5 m2/hrs
Helper 1
bore packing applicator 1 3 No/day 0.375 No/hrs
Helper 1
9 Plumbing Works
toilet chasing chipper 1 7 Rmt/day 0.875 Rmt/hrs
waterline fixing plumber 1 3 toilet/day 0.375 toilet/hrs
helper 1.5
sanitary line fixing plumber 1 3 toilet/day 0.375 toilet/hrs
helper 2
sanitary &cp fitting plumber 1.5 4 toilet+kitch 0.5 toilet+kitchen/hrs
helper 3
Running ft/hrs
toilet+kitchen/hrs
Ite Production Production
Description Gang Time Unit
m per 8hrs per hrs
1 Excavation & Earth Work
1.1 Site clearing to remove depth of 20cm 1D. L 8hr 10 1.250 m2
1.2 Trench Excavation in ordinary soil
a. To a depth of 1.2m 1D.L 8hr 1.25 0.156 m3
b. To a depth of 2.2m 1D.L 8hr 1 0.125 m3
c. To a depth of 3.00m 1D.L 8hr 0.75 0.094 m3
1.3 Bulk excavation in ordinary soil
a. To a depth of 1.5m 1D.L 8hr 1.5 0.188 m3
1.4 Cart Away
a. To 500m away from the site 1D.L 8hr 1.5 0.188 m3
b. To 1km away from the site 1D.L 8hr 1 0.125 m3
1.5 Hard-coring 25cm thick 1M+4D.L 8hr 18 2.250 m2
1.6 Back fill around foundation:
a. Loose soil 1D.L 8hr 2 0.250 m3
b. Aggregate 1D.L 8hr 5.5 0.688 m3
2 Concrete Work
2.1 Lean concrete
a. 5cm thick 1M+6D.L 8hr 20 2.500 m2
b. 8cm thick 1M+6D.L 8hr 15 1.875 m2
2.2 Floor Slab
a. 8cm thick 1M+6D.L 8 hr 15 1.875 m2
b. 10cm thick 1M+6D.L 8hr 12.5 1.563 m2
c. 15cm thick 1M+6D.L 8hr 10 1.250 m2
2.3 Ground beam 1M+6D.L 8hr 1.5 0.188 m3
2.4 Footing 1M+6D.L 8hr 1.5 0.188 m3
2.5 Foundation column 1M+6D.L 8hr 1.25 0.156 m3
2.6 Upper tie beam 1M+6D.L 8hr 1.5 0.188 m3
2.7 Lintel 1M+6D.L 8hr 1 0.125 m3
2.8 Column up to 2m 1M+6D.L 8hr 1 0.125 m3
2.9 Column above 2m 1M+6D.L 8hr 1.25 0.156 m3
3 Masonry Work
3.1 Stone Masonry sub-structure.
a. 40cm thick 2M+6D.L 8hr 5 0.625 m3
b. 50cm thick 2M+6D.L 8hr 6 0.750 m3
c. 60cm thick 2M+6D.L 8hr 7 0.875 m3
3.2 Stone Masonry super structure
a. 40cm thick 2M+6D.L 8hr 3 0.375 m3
b. 50cm thick 2M+6D.L 8hr 4 0.500 m3
c. 60cm thick 2M+6D.L 8hr 5 0.625 m3
3.3 Brick Masonry Wall for plastering.
a. 25cm thick up to 2m 1M+3D.L 8hr 7 0.875 m2
b. 12cm thick up to 2m 1M+3D.L 8hr 9 1.125 m2
c. 25cm thick from 2-4m 1M+3D.L 8hr 5 0.625 m2
d. 12cm thick from 2-4m 1M+3D.L 8hr 7 0.875 m2
4
5
5.2 Ridge cover 1C+2D.L 8hr 4pcs 2hr/pos
5.3 Valley cover 1C+2D.L 8hr 10m2 48min/m2
5.4 Gutter fixing 1C+2D.L 8hr 10m2 48min/m2
5.5 Joining eucalyptus truss
up to 10m span on ground 1C+2D.L 8hr 13m2 48min/m2
6 Metal Work
6.1 Metal door fixing 1W+2D.L 8hr 3pcs 2.66hr/pcs
6.2 Metal Window fixing 1W+2D.L 8hr 4pcs 2hr/pcs
6.3 French Window fixing 1W+2D.L 8hr 2pcs 4hr/pcs
7 Plastering & Pointing
7.1 1st cost plastering 1P+2D.L 8hr 35m2 14min/m2
7.2 2nd cost plastering 1P+2D.L 8hr 10m2 48min/m2
7.3 3rd cost plastering 1P+2D.L 8hr 14m2 34min/m2
7.4 Pointing on stone Wall
7.5 Pointing on brick wall 1P+2D.L 8hr 8m2 4hr/m2
7.6 Pointing on Hollow block 1P+2D.L 8hr 14m2 34min/m2
7.7 Pointing on dressed stone 1P+2D.L 8hr 12m2 40min/m2
7.8 Rendering 1P+2D.L 8hr 20m2 24min/m2
8 Flooring
Cement Screed 1M+2D.L 8hr 14m2 34min/m2
Cement tile fixing 1M+2D.L 8hr 10m2 48min/m2
Plastic tile fixing 1M+2D.L 8hr 17m2 48min/m2
Par - quet flooring 1M+2D.L 8hr 15m2 32min/m2
Wooden flooring 1C+2D.L 8hr 8m2 1hr/m2
Ceramic wall tile 1M+2D.L 8hr 7m2 1.14hrn/m2
Plastic tile skirting 1M+2D.L 8hr 40ml 12min/ml
Cement tile skirting 1M+2D.L 8hr 12ml 40min/m2
Marble slate flooring 1M+2D.L 8hr 12ml 40min/m2
Marble slate skirting 1M+2D.L 8hr 16ml 30min/m2
Fixing pre-cast windows 1M+2D.L 8hr 10ml 48min/ml
Fixing un pre-cat window sill 1M+2D.L 8hr 6ml 1.33min/ml
9 Glazing
9.1 Cutting 1G+2D.L 8hr 50m2 10min/m2
9.2 Fixing 1G+2D.L 8hr 20m2 24min/m2
10 Painting
a) Plastic paint
10.1 Painting plastered wallSurface 3ocats 1P + 1DL 8hr 30m2 16min/m2
10.2 Painting Rendered wallsurface 1P + 1DL 8hr 25m2 19min/m2
10.3 Painting Abujedid wall 1P + 1DL 8hr 20m2 24min/m2
10.4 Painting Hard board obi 1P + 1DL 8hr 20m2 24min/m2
10.4 Painting Cheap boardceiling 1P + 1DL 8hr 20m2 24ming/m2
b) Synthetic paint
10.6 Plastered wall surface in 3 coats 1p + ID1 8hr 25m2 19min/m2
10.7 Wooden surface 1p + ID1 8hr 25m2 19min/m2
10.8 Metal surface 1p + ID1 8hr 25m2 19min/m2
11 Sanitary work
11.1 G.1. pipe laying inGround ½ - 11/4 1P+2DL 8hr 120m2 4min/ml
Fixing – Bath tubeShower complete,
11.2 washBasin, water closest, bidetSink, 1p+1DL 8hr 1pcs 8hr/pcs
urinal
12 Electrical installation
2 Fixing conduits 1E+1DL 8hr 40ml 12min/ml
12.2
Pulling wires 1E+1DL 8hr 50ml 10min/ml
.12.3
Fixing switch & out-lets 1E+1DL 8hr 20pcs 24min/pcs
.12.4
Fixing fittings 1E+1DL 8hr 10pcs 48min/pcs
.12.5
Fitting distribution board 1E+1DL 8hr 10pcs 8min/pcs
.
13 Site Work
13.1 Drain laying
1M +3
0.10 - 0.30m 8hr 30ml 16min/ml
1DL
0.40 - 0.60 m 8hr 20ml 24min/ml
0.80 - 1.00 m 8hr 10ml 48min/ml
13.2 Curb Stone 1m+3DL 8hr 30ml 16min/ml
13.3 0.60 x 0.60 x 0.60m
manhole out of brick 1m+3DL 8hr 3pcs 4hr/pcs
13.4 0.60 x 0.60 x 0.60m
manhole out of hollow block 1m+3DL 8hr 2pcs 4hr/pcs
13.5 Fencing with Galv.
Fencing net 1C+2DL 8hr 50m2 10min/m2
CREW FORMATION Hourly
Item Type of activity Unit
Labour Equipment Output
1 Forman
1 5cm thick lean concrete (c-7) m3 2 mason 1 mixer 2.25m3
45 D/L
1 Forman 1Mixer
2 Concrete C-15 m3 2 mason 1 Vibrator 2.25m3
45 D/L
1 Forman 1 Mixer
3 C-25 concrete for footing m3 2 mason 1 Vibrator 2.25m3
45 D/L
1 Forman 1 Mixer
4 C-25 concrete for column m3 2 mason 2 Vibrator 0.75m3
25 D/L
1Forman 1 Mixer
5 C-25 concrete for Grade beam m3 2 mason 2 Vibrator 1.75m3
45 D/L
1 Forman 1 Mixer
6 C-25 Concrete for slab m3 2 Mason 2 Vibrator 2.50m3
45 D/L
1 Forman 1 Mixer
7 C-25 top beam and Lintel m3 2 Mason 2 Vibrator 1.50m3
45 D/L
1/6 Forman
8 30 cm Ribbed slab m2 1Mason - 2.00m2
2 D/L
1/6 Forman
1 carpenter
9 Wooden form work (Footing) m2 - 0.60m2
1 Helper
1 D/L
1/6 Forman
1 carpenter
10 Wooden form work (Column) m2 - 0.50m2
1 Helper
1 D/L