Saudi Aramco Typical Inspection Plan
Saudi Aramco Typical Inspection Plan
00 30-Jun-16
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW SPECIAL PROCESS (NDE) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
SAIC-MPT- SAIC-MPT-
1.2 MPT Personnel Qualification Review RH RH Maintain Current Roster/CVs for NDE Techs.
2002 2002
SAIC-MPT-
SAIC-MPT-
1.3 NDE Process Control Procedure* 2010 RH RH *Combine all NDE Methods applicable
2010
2.0 EQUIPMENT
Visual Insp & Verification of MPT mat'ls SAIC-MPT- SAIC-MPT- Use SATR-NDE-2010
2.1 W* S
and Equipment 2003 2003 Each day checked against In-Process work.
Storage, Handling & Preservation of MPT *Safety Checks are done for each In-Process application
2.2 See Remarks See Remarks W* S
materials (*See Safety Check) listed below
3.0 APPLICATION IN-PROCESS VERIFICATION = DAILY SUPERVISION BY CONTRACTOR* (*Prime/Sub) OF NDT SERVICE PROVIDERS, & SAEP-1160 DATABASE UPDATES
In-Process Inspection of MPT using Prod Same as above The prod technique should not be used
SAIC-MPT- SAIC-MPT-
3.2 Technique [As per SAEP 1144 page 10 W* S on highly polished or machined surfaces due the
2005 2005
para 1.3 Prods should be avoided] possibility of arc damage to the surface.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-MPT- SAIC-MPT-
3.4 Demagnetization & Post Cleaning W S
2007 2007
GENERAL NOTES
NOTICE (SAEP-1160, Section 9.2): Use of Welding and NDT SAICS 9.2.1 One SAIC per day per activity is required for production welding on a daily or continual basis, e.g., fit-up, in-process, and final
inspection. Applicable weld numbers must be entered in Remarks Box on the appropriate SAIC. 9.2.2 Special welding activities such as branch connections, tie-ins, sleeve installation, hot-tap welding, and
temperature tie-ins will require a separate IR per weld per activity in accordance with the applicable SATIP. 9.2.3 NDT subcontractors must complete NDT Checklists on a daily basis per above but not as an IR
with the exception of the start of NDT activities. SAIC-W-2008 details SAEP-1160 Data Reqmts for Welding with NDE Control per SAIC-MPT-2010.
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
###
###