CPIM 용어정리
CPIM 용어정리
BSCM 350 제
Purest Form : Flow Manufacturing (inflexible flow line)
Planning Bills (BOM) : Artificial grouping of components for planning purpose, 계획목적으로 아이템 그룹에서의 평균량
계산한 BOM
Shop Packet : A Package of Documents used to plan and control the shop floor movement of an order (Manufacturing order,
operations sheets, engineering blueprints, picking lists, move tickets, inspection tickets, and time tickets)
= BOM, Route Sheets, Engineering drawings
System Nervousness : (Nervousness) minor changes in higher-level cause significant timing or quantity changes in lower
level schedules and orders (잦은 소규모의 Requirements change 에 따라 발생)
- 메시지 Filter 활용, use firm order 사용(replanning 최소화하는)
Distribution Warehouse : break down large lots into smaller items (expeditious move, handling - mix?)
Expeditious : 신속한 (expedite 재빠르게 처리하다)
MPS developing step : 1) develop preliminary MPS 2) Check the schedule against the capacity available 3) Resolve
differences between preliminary MPS and capacity available
Objective of scheduling : Meet Delivery Data while utilizing manufacturing resources effectively
TQM : 1) user 는 고객, 다음 프로세스 2) Daily monitoring by operator 3) defect -> stop & correct
Responsibility of a planner : 1) Reschedule due date of open order as required 2) reconcile errors and try to find their cause,
and solve critical material shortages by expediting or replanning.
Schedule Planned order -> by computer
Prelude : 도입부, 서곡
Particular Commodity : 특정 상품
Zone System : Order picker only pick their own zone(area) (divided), marshaling area 에 모음
Tracking Signal = Total Errors / MAD (총 Error 에서 부호 상관없이 총합 / MAD = Bias 계산)
Blanket purchase order : long-term commitment to a supplier for material (=Standing Order)
Buyer-planner : Buyer job, planner job 을 동시에 하는 사람, buyer, planner 각 사람보다 적은 부품을 다루지만 공급자와
정보, material 에서 섬세한 관계 형성 가능
MPS minimum planning horizon : longest cumulative lead time (for purchasing required items)
ATO environment : Many different end items are made from a few standard components or modules.
Increasing batch size -> Reducing queue -> reducing LT -> Improving forecast accuracy -> better order-promising and due-
date performance
Work cell : 다양한 기계들이 생산단위에 비슷한 공정을 거치는 부품들을 생산하기 위해 함께 있는 것
Dispatching : Releasing orders to the shop floor (가용작업들을 선택하고 순서를 정함, 업무를 작업자들에게 할당)
Rules - FCFS, EDD, ODD, SPT
Available Capacity : ability of a resource to produce a quantity of output for a particular period
Cycle Counting 특징 : ABC 재고관리로 자주 카운팅하는 아이템이 있을 수 있다. A>B>C, 부분적인 생산 손실을
감소시킨다.
Cycle Count 목적 : 재고 error 확인 및 조치
Central Storage (쉬운 관리) <-> Point of use Storage (자재 운반 감소, 보관비용 감소, 언제든 접근 가능)
POINT OF USE 는 재고로 관리하는 개념이 아니기 때문에 보관비가 감소함 - 자재 관리가 어려워진다.
Operation Time : setup + operation, Total Manufacturing LT : queue + setup + operation(run) + wait + move
Firm Planned Order (FPO) : planned order frozen in quantity and time (정해지면 컴퓨터가 자동 변경 x)
SOP 목적 : Build Teamwork, 변화 효과적 관리, 비즈니스 플랜 지원, 계획 현실성 확보, 제품 재고, 백로그 관리, 성과측정
Obsolete Inventory : 유행 지난 재고
Finite Loading : 필요량 이상 생산하지 않는 것 (DBR MTO 환경) - Forward - WIP inv 상승
Infinite Loading - MTS 환경 - Backward - WIP Inv 감소
Routing : Operation, Sequence, Work Centers, Tooling Necessary, Standard Setup and run times (Material flow X)
Product-focused layout : Fixed flow of work / flow operation (good inventory movement / bad labor, machine)
process layout : intermittent operation
project layout : fixed location operation
DRP : logic, translate MRP to distribution system, 다양한 수요를 예측하여 central supply, operation 에 수요정보 전달
Quality Cost
internal failures, external failures, appraisal costs, and prevention costs
Appraisal : 정형 평가와 품질 감사와 관련된 비용
process loss : 프로세스 상의 생산성을 떨어뜨리는 손실
Decentralized Distribution System (Pull) - Central Supply Organization Role : Respond to Demand from DC
Each distribution center places order to central supply organization
Centralized Distribution System (Push) - central supply organization Role : determine when to replenish stock at DC,
coordinate among DC, forecast demand at each DC
Input Rate(rope) : controlled by release of orders to the shop (if order release speed is faster than producing, input
rate(queue, WIP, LT) will increase)
Factor of 2 : x2
Demand Management include (Forecasted Requirements, service parts requirements, branch warehouse requirements, inter-
plant orders, order entry and order promising
Deterioration : 손상
Cycle stock(Lot-Size Stock) is one of the two main conceptual components of any inventory
순환재고 (발주량에 따라 주문해서 생기는 재고)
MRP
Exploding : process of multiplying the requirements
Offsetting : process of placing the exploded requirements (상쇄하다, 리드타임에 맞춰 놓는 것)
Forecasting Method
Qualitative - Quantitative (Intrinsic - Historical Data(Moving Average, Exp Smoothing, 회귀), Extrinsic - (집 - 가구)
Interruption : 중단
Carrying costs : capital cost, storage cost, risk cost, ownership cost
risk cost: Obsolescence , Damage, Deterioration , Pilferage
Consignment - 위탁
CRP - Open shop order, planned order(MRP), routing, time standard, lead times, center capacities
Shop order - 생산, 및 주문에 필요한 정보, open order - 입고예정량
Input rate : release order to shop floor 증가 - queue, wip, lead time 증가,
Output rate : work center capacity
Sequencing for short term planning of actual jobs to be run in each work center
PAB(Projected Available Balance) : Demand Time Fence 안에서 수요는 변하지 않음 - 이로 계산, 그 외 max 로 계산