PEKERJAAN PERSIAPAN
A. 2.2.1.1 1 M2 Pembuatan Pagar Sementara dari Kayu Tinggi 2 Meter
A. 2.2.1.1.a Bahan
Semen portland 5.0000 kg x Rp. 1,700.00 = Rp. 8,500.00
Pasir beton 0.0050 m3 x Rp. 172,500.00 = Rp. 862.50
Koral beton 0.0090 m3 x Rp. 287,500.00 = Rp. 2,587.50
Kayu sembarang 0.0720 m3 x Rp. 6,325,000.00 = Rp. 455,400.00
Paku biasa 0.0600 kg x Rp. 23,000.00 = Rp. 1,380.00
Residu/colter 0.4000 ltr x Rp. 86,200.00 = Rp. 34,480.00
Jumlah (1) Rp. 503,210.00
A. 2.2.1.1.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 89,080.00
Jumlah (1) + (2) Rp. 592,290.00 Rp. 592,290.00
A. 2.2.1.5.a Bahan
Kayu sembarang 0.0600 m3 x Rp. 6,325,000.00 = Rp. 379,500.00
Paku biasa 0.0800 kg x Rp. 23,000.00 = Rp. 1,840.00
Besi strip 1.1000 kg x Rp. 9,700.00 = Rp. 10,670.00
Semen portland 35.0000 kg x Rp. 1,700.00 = Rp. 59,500.00
Pasir pasang 0.1500 m3 x Rp. 172,500.00 = Rp. 25,875.00
Pasir beton 0.1000 m3 x Rp. 172,500.00 = Rp. 17,250.00
Koral beton 0.1500 m3 x Rp. 287,500.00 = Rp. 43,125.00
Bata merah 30.0000 bh x Rp. 630.00 = Rp. 18,900.00
Seng plat 0.2500 lbr x Rp. 59,800.00 = Rp. 14,950.00
Jendela nako 0.2000 bh x Rp. 18,800.00 = Rp. 3,760.00
Kaca polos 0.0800 m2 x Rp. 155,000.00 = Rp. 12,400.00
Kunci tanam 0.1500 bh x Rp. 230,000.00 = Rp. 34,500.00
Triplek 4 mm 0.0600 lbr x Rp. 92,000.00 = Rp. 5,520.00
Jumlah (1) Rp. 627,790.00
A. 2.2.1.5.b Tenaga
Pekerja 2.0000 oh x Rp. 115,000.00 = Rp. 230,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Tukang batu 1.0000 oh x Rp. 172,000.00 = Rp. 172,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 819,450.00
Jumlah (1) + (2) Rp. 1,447,240.00 Rp. 1,447,240.00
A. 2.2.1.7.a Bahan
Kayu sembarang 0.0700 m3 x Rp. 6,325,000.00 = Rp. 442,750.00
Paku biasa 0.3000 kg x Rp. 23,000.00 = Rp. 6,900.00
Semen portland 10.5000 kg x Rp. 1,700.00 = Rp. 17,850.00
Pasir beton 0.0300 m3 x Rp. 172,500.00 = Rp. 5,175.00
Koral beton 0.0500 m3 x Rp. 287,500.00 = Rp. 14,375.00
Seng gelombang 7 kaki BJLS 20 1.5000 lbr x Rp. 69,500.00 = Rp. 104,250.00
Seng plat 0.2500 lbr x Rp. 59,800.00 = Rp. 14,950.00
Jumlah (1) Rp. 606,250.00
A. 2.2.1.7.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 511,750.00
Jumlah (1) + (2) Rp. 1,118,000.00 Rp. 1,118,000.00
A. 2.2.1.10.a Bahan
Bambu 1.2500 btg x Rp. 23,000.00 = Rp. 28,750.00
Ijuk 0.1860 kg x Rp. 28,700.00 = Rp. 5,338.20
Jumlah (1) Rp. 34,088.20
A. 2.2.1.10.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 511,750.00
Jumlah (1) + (2) Rp. 545,838.20 Rp. 545,830.00
A. 2.2.1.18.a Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0450 oh x Rp. 172,000.00 = Rp. 7,740.00
Kepala Tukang 0.0045 oh x Rp. 207,000.00 = Rp. 931.50
Mandor 0.0075 oh x Rp. 227,000.00 = Rp. 1,702.50
Jumlah (2) Rp. 27,624.00 Rp. 27,620.00
A. 2.2.1.19.a Tenaga
Pekerja 0.1600 oh x Rp. 115,000.00 = Rp. 18,400.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 20,216.00 Rp. 20,210.00
PEKERJAAN TANAH
A. 2.3.1.1 1 M3 Penggalian Tanah Biasa Sedalam 1 M
A. 2.3.1.1.a Tenaga
Pekerja 0.7500 oh x Rp. 115,000.00 = Rp. 86,250.00
Mandor 0.0250 oh x Rp. 227,000.00 = Rp. 5,675.00
Jumlah Rp. 91,925.00 Rp. 91,920.00
A. 2.3.1.3.a Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Mandor 0.0670 oh x Rp. 227,000.00 = Rp. 15,209.00
Jumlah Rp. 135,959.00 Rp. 135,950.00
A. 2.3.1.6.a Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah Rp. 148,215.00 Rp. 148,210.00
A. 2.3.1.8.a Tenaga
Pekerja 0.3300 oh x Rp. 115,000.00 = Rp. 37,950.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah Rp. 40,220.00 Rp. 40,220.00
PEKERJAAN PONDASI
A. 3.2.1.1 1 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 3Pp
A. 3.2.1.1.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Semen portland 202.0000 kg x Rp. 1,700.00 = Rp. 343,400.00
Pasir pasang 0.4850 m3 x Rp. 172,500.00 = Rp. 83,662.50
Jumlah (1) Rp. 772,062.50
A. 3.2.1.1.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 1,106,112.50 Rp. 1,106,110.00
A. 3.2.1.2.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Semen portland 163.0000 kg x Rp. 1,700.00 = Rp. 277,100.00
Pasir pasang 0.5200 m3 x Rp. 172,500.00 = Rp. 89,700.00
Jumlah (1) Rp. 711,800.00
A. 3.2.1.2.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 1,045,850.00 Rp. 1,045,850.00
A. 3.2.1.10 1 M Pemasangan Pondasi Siklop, 60% Beton Camp. 1Pc : 2Pb : 3Kr dan 40% Batu Kali
3
A. 3.2.1.10.a Bahan
Batu kali 0.4800 m3 x Rp. 287,500.00 = Rp. 138,000.00
Semen portland 194.0000 kg x Rp. 1,700.00 = Rp. 329,800.00
Pasir beton 0.3120 m3 x Rp. 172,500.00 = Rp. 53,820.00
Kerikil beton 0.4680 m3 x Rp. 230,000.00 = Rp. 107,640.00
Besi beton 126.0000 kg x Rp. 10,800.00 = Rp. 1,360,800.00
Kawat beton 1.8000 kg x Rp. 28,700.00 = Rp. 51,660.00
Jumlah (1) Rp. 2,041,720.00
A. 3.2.1.10.b Tenaga
Pekerja 3.4000 oh x Rp. 115,000.00 = Rp. 391,000.00
Tukang batu 0.8500 oh x Rp. 172,000.00 = Rp. 146,200.00
Kepala Tukang 0.0850 oh x Rp. 207,000.00 = Rp. 17,595.00
Mandor 0.1700 oh x Rp. 227,000.00 = Rp. 38,590.00
Jumlah (2) Rp. 593,385.00
Jumlah (1) + (2) Rp. 2,635,105.00 Rp. 2,635,100.00
A. 4.4.1.2 1 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 3Pp
A. 4.4.1.2.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 32.9500 kg x Rp. 1,700.00 = Rp. 56,015.00
Pasir pasang 0.0910 m3 x Rp. 172,500.00 = Rp. 15,697.50
Jumlah (1) Rp. 159,912.50
A. 4.4.1.2.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 274,262.50 Rp. 274,260.00
A. 4.4.1.3 1 M Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 4Pp
2
A. 4.4.1.3.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 26.5500 kg x Rp. 1,700.00 = Rp. 45,135.00
Pasir pasang 0.0930 m3 x Rp. 172,500.00 = Rp. 16,042.50
Jumlah (1) Rp. 149,377.50
A. 4.4.1.4 1 M Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 5Pp
2
A. 4.4.1.4.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 22.2000 kg x Rp. 1,700.00 = Rp. 37,740.00
Pasir pasang 0.1020 m3 x Rp. 172,500.00 = Rp. 17,595.00
Jumlah (1) Rp. 143,535.00
A. 4.4.1.4.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 257,885.00 Rp. 257,880.00
A. 4.4.1.7 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 2Pp
A. 4.4.1.7.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 18.9500 kg x Rp. 1,700.00 = Rp. 32,215.00
Pasir pasang 0.0380 m3 x Rp. 172,500.00 = Rp. 6,555.00
Jumlah (1) Rp. 82,870.00
A. 4.4.1.7.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 140,045.00 Rp. 140,040.00
A. 4.4.1.8 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 3Pp
A. 4.4.1.8.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 14.3700 kg x Rp. 1,700.00 = Rp. 24,429.00
Pasir pasang 0.0400 m3 x Rp. 172,500.00 = Rp. 6,900.00
Jumlah (1) Rp. 75,429.00
A. 4.4.1.8.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 132,604.00 Rp. 132,600.00
A. 4.4.1.9 1 M Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 4Pp
2
A. 4.4.1.9.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 11.5000 kg x Rp. 1,700.00 = Rp. 19,550.00
Pasir pasang 0.0430 m3 x Rp. 172,500.00 = Rp. 7,417.50
Jumlah (1) Rp. 71,067.50
A. 4.4.1.9.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 128,242.50 Rp. 128,240.00
A. 4.4.1.10 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 5Pp
A. 4.4.1.10.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 9.6800 kg x Rp. 1,700.00 = Rp. 16,456.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Jumlah (1) Rp. 68,318.50
A. 4.4.1.10.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 125,493.50 Rp. 125,490.00
A. 4.4.1.23 1 M2 Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 4Pp
A. 4.4.1.23.a Bahan
Batu terawang roster 30.0000 bh x Rp. 40,200.00 = Rp. 1,206,000.00
Semen portland 11.0000 kg x Rp. 1,700.00 = Rp. 18,700.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 1,230,737.50
A. 4.4.1.23.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 1,287,912.50 Rp. 1,287,910.00
A. 4.4.1.25 1 M Pemasangan Dinding Bata Ringan tebal 7,5 cm dengan Mortar Siap Pakai
2
A. 4.4.1.25.a Bahan
Bata ringan tebal 7,5 cm 8.4000 m3 x Rp. 1,063,700.00 = Rp. 8,935,080.00
Mortar siap pakai 0.4730 kg x Rp. 7,400.00 = Rp. 3,500.20
Jumlah (1) Rp. 8,938,580.20
A. 4.4.1.25.b Tenaga
Pekerja 0.6700 oh x Rp. 115,000.00 = Rp. 77,050.00
Tukang batu 1.3000 oh x Rp. 172,000.00 = Rp. 223,600.00
Kepala Tukang 0.1300 oh x Rp. 207,000.00 = Rp. 26,910.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 328,241.00
A. 4.4.1.25.c Peralatan
Peralatan 10.0000 % x Rp. 1,063,700.00 = Rp. 106,370.00
106,370.00
Jumlah (1) + (2) + (3) Rp. 9,373,191.20 Rp. 9,373,190.00
A. 4.4.1.26 1 M2 Pemasangan Dinding Bata Ringan tebal 10 cm dengan Mortar Siap Pakai
A. 4.4.1.26.a Bahan
Bata ringan tebal 10 cm 8.4000 m3 x Rp. 1,063,700.00 = Rp. 8,935,080.00
Mortar siap pakai 0.0630 kg x Rp. 7,400.00 = Rp. 466.20
Jumlah (1) Rp. 8,935,546.20
A. 4.4.1.26.b Tenaga
Pekerja 0.6710 oh x Rp. 115,000.00 = Rp. 77,165.00
Tukang batu 1.3000 oh x Rp. 172,000.00 = Rp. 223,600.00
Kepala Tukang 0.1300 oh x Rp. 207,000.00 = Rp. 26,910.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 328,356.00
A. 4.4.1.26.c Peralatan
Peralatan 10.0000 % x Rp. 1,063,700.00 = Rp. 106,370.00
106,370.00
Jumlah (1) + (2) + (3) Rp. 9,370,272.20 Rp. 9,370,270.00
A. 4.4.1.27.a Bahan
Glass block 25.0000 bh x Rp. 34,500.00 = Rp. 862,500.00
Semen portland 11.5000 kg x Rp. 1,700.00 = Rp. 19,550.00
Pasir pasang 0.0430 m3 x Rp. 172,500.00 = Rp. 7,417.50
Jumlah (1) Rp. 889,467.50
A. 4.4.1.27.b Tenaga
Pekerja 0.0850 oh x Rp. 115,000.00 = Rp. 9,775.00
Tukang batu 0.1850 oh x Rp. 172,000.00 = Rp. 31,820.00
Kepala Tukang 0.0185 oh x Rp. 207,000.00 = Rp. 3,829.50
Mandor 0.0085 oh x Rp. 227,000.00 = Rp. 1,929.50
Jumlah (2) Rp. 47,354.00
Jumlah (1) + (2) Rp. 936,821.50 Rp. 936,820.00
PEKERJAAN PLESTERAN
A. 4.4.2.1 1 M2 Pemasangan Plesteran 1Pc : 1Pp, Tbl 15 mm
A. 4.4.2.1.a Bahan
Semen portland 15.5040 kg x Rp. 1,700.00 = Rp. 26,356.80
Pasir pasang 0.0160 m3 x Rp. 172,500.00 = Rp. 2,760.00
Jumlah (1) Rp. 29,116.80
A. 4.4.2.1.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 95,926.80 Rp. 95,920.00
A. 4.4.2.2.a Bahan
Semen portland 10.2240 kg x Rp. 1,700.00 = Rp. 17,380.80
Pasir pasang 0.0200 m3 x Rp. 172,500.00 = Rp. 3,450.00
Jumlah (1) Rp. 20,830.80
A. 4.4.2.2.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 87,640.80 Rp. 87,640.00
A. 4.4.2.19.a Bahan
Semen portland 5.1840 kg x Rp. 1,700.00 = Rp. 8,812.80
Pasir pasang 0.0260 m3 x Rp. 172,500.00 = Rp. 4,485.00
Jumlah (1) Rp. 13,297.80
A. 4.4.2.19.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang batu 0.0750 oh x Rp. 172,000.00 = Rp. 12,900.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 33,622.00
Jumlah (1) + (2) Rp. 46,919.80 Rp. 46,910.00
PEKERJAAN KAYU
A. 4.6.1.1 1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. I
A. 4.6.1.1.a Bahan
Balok Kayu 1.1000 m3 x Rp. 20,125,000.00 = Rp. 22,137,500.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 22,217,950.00
A. 4.6.1.1.b Tenaga
Pekerja 7.0000 oh x Rp. 115,000.00 = Rp. 805,000.00
Tukang kayu 21.0000 oh x Rp. 172,000.00 = Rp. 3,612,000.00
Kepala Tukang 2.1000 oh x Rp. 207,000.00 = Rp. 434,700.00
Mandor 0.3500 oh x Rp. 227,000.00 = Rp. 79,450.00
Jumlah (2) Rp. 4,931,150.00
Jumlah (1) + (2) Rp. 27,149,100.00 Rp. 27,149,100.00
A. 4.6.1.2 1 M Pembuatan dan Pemasangan Kusen Pintu dan Kusen Jendela Kayu kls. II
3
A. 4.6.1.2.a Bahan
Balok Kayu 1.2000 m3 x Rp. 10,350,000.00 = Rp. 12,420,000.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 12,500,450.00
A. 4.6.1.2.b Tenaga
Pekerja 6.0000 oh x Rp. 115,000.00 = Rp. 690,000.00
Tukang kayu 18.0000 oh x Rp. 172,000.00 = Rp. 3,096,000.00
Kepala Tukang 1.8000 oh x Rp. 207,000.00 = Rp. 372,600.00
Mandor 0.3000 oh x Rp. 227,000.00 = Rp. 68,100.00
Jumlah (2) Rp. 4,226,700.00
Jumlah (1) + (2) Rp. 16,727,150.00 Rp. 16,727,150.00
4.6.1.2.1 1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Kusen Jendela Kayu kls. III
4.6.1.2.1.a Bahan
Balok Kayu 1.2000 m3 x Rp. 6,900,000.00 = Rp. 8,280,000.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 8,360,450.00
4.6.1.2.1.b Tenaga
Pekerja 6.0000 oh x Rp. 115,000.00 = Rp. 690,000.00
Tukang kayu 18.0000 oh x Rp. 172,000.00 = Rp. 3,096,000.00
Kepala Tukang 1.8000 oh x Rp. 207,000.00 = Rp. 372,600.00
Mandor 0.3000 oh x Rp. 227,000.00 = Rp. 68,100.00
Jumlah (2) Rp. 4,226,700.00
Jumlah (1) + (2) Rp. 12,587,150.00 Rp. 12,587,150.00
A. 4.6.1.3.a Bahan
Papan Kayu 0.0400 m3 x Rp. 10,350,000.00 = Rp. 414,000.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 415,150.00
A. 4.6.1.3.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang kayu 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 246,671.00
Jumlah (1) + (2) Rp. 661,821.00 Rp. 661,820.00
A. 4.6.1.4 1 M2 Pembuatan dan Pemasangan Pintu Klamp Sederhana, Kayu kls. III
A. 4.6.1.4.a Bahan
Papan Kayu 0.0400 m3 x Rp. 6,900,000.00 = Rp. 276,000.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 277,150.00
A. 4.6.1.4.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang kayu 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 246,671.00
Jumlah (1) + (2) Rp. 523,821.00 Rp. 523,820.00
A. 4.6.1.6 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. I
A. 4.6.1.6.a Bahan
Papan Kayu 0.0240 m3 x Rp. 20,125,000.00 = Rp. 483,000.00
Lem kayu 0.3000 kg x Rp. 51,700.00 = Rp. 15,510.00
Jumlah (1) Rp. 498,510.00
4.6.1.6.1 1 M Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. II
2
4.6.1.6.1.a Bahan
Papan Kayu 0.0240 m3 x Rp. 10,350,000.00 = Rp. 248,400.00
Lem kayu 0.3000 kg x Rp. 51,700.00 = Rp. 15,510.00
Jumlah (1) Rp. 263,910.00
4.6.1.6.1.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 827,470.00 Rp. 827,470.00
A. 4.6.1.7 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. I
A. 4.6.1.7.a Bahan
Papan Kayu 0.0640 m3 x Rp. 20,125,000.00 = Rp. 1,288,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 1,313,850.00
A. 4.6.1.7.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 2,018,300.00 Rp. 2,018,300.00
4.6.1.7.1 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. II
4.6.1.7.1.a Bahan
Papan Kayu 0.0640 m3 x Rp. 10,350,000.00 = Rp. 662,400.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 688,250.00
4.6.1.7.1.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,392,700.00 Rp. 1,392,700.00
A. 4.6.1.8 1 M2 Pembuatan Daun Pintu Tripleks Rangkap, Rangka Kayu kls. II tertutup
A. 4.6.1.8.a Bahan
Papan Kayu 0.0250 m3 x Rp. 10,350,000.00 = Rp. 258,750.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 377,290.00
A. 4.6.1.8.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang kayu 2.1000 oh x Rp. 172,000.00 = Rp. 361,200.00
Kepala Tukang 0.2100 oh x Rp. 207,000.00 = Rp. 43,470.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 493,115.00
Jumlah (1) + (2) Rp. 870,405.00 Rp. 870,400.00
A. 4.6.1.8.1 1 M2 Pembuatan dan Pemasangan Pintu Tripleks Rangkap, Rangka Tertutup Kayu Lapis Seng
A. 4.6.1.8.1.a Bahan
Papan Kayu sembarang 0.0256 m3 x Rp. 6,325,000.00 = Rp. 161,920.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Seng plat bjls 22 8.0000 kk x Rp. 104,500.00 = Rp. 836,000.00
Jumlah (1) Rp. 1,116,460.00
A. 4.6.1.8.1.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang kayu 2.1000 oh x Rp. 172,000.00 = Rp. 361,200.00
Kepala Tukang 0.2100 oh x Rp. 207,000.00 = Rp. 43,470.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 493,115.00
Jumlah (1) + (2) Rp. 1,609,575.00 Rp. 1,609,570.00
A. 4.6.1.9.a Bahan
Papan Kayu 0.0256 m3 x Rp. 20,125,000.00 = Rp. 515,200.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 633,740.00
4.6.1.9.1.a Bahan
Papan Kayu 0.0256 m3 x Rp. 10,350,000.00 = Rp. 264,960.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 383,500.00
4.6.1.9.1.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 947,060.00 Rp. 947,060.00
A. 4.6.1.13.a Bahan
Balok Kayu 1.1000 m3 x Rp. 20,125,000.00 = Rp. 22,137,500.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 5.6000 kg x Rp. 23,000.00 = Rp. 128,800.00
Jumlah (1) Rp. 22,411,800.00
A. 4.6.1.13.b Tenaga
Pekerja 4.0000 oh x Rp. 115,000.00 = Rp. 460,000.00
Tukang kayu 12.0000 oh x Rp. 172,000.00 = Rp. 2,064,000.00
Kepala Tukang 1.2000 oh x Rp. 207,000.00 = Rp. 248,400.00
Mandor 0.2000 oh x Rp. 227,000.00 = Rp. 45,400.00
Jumlah (2) Rp. 2,817,800.00
Jumlah (1) + (2) Rp. 25,229,600.00 Rp. 25,229,600.00
A. 4.6.1.15.a Bahan
Balok Kayu 1.1000 m3 x Rp. 10,350,000.00 = Rp. 11,385,000.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 3.0000 kg x Rp. 23,000.00 = Rp. 69,000.00
Jumlah (1) Rp. 11,599,500.00
A. 4.6.1.15.b Tenaga
Pekerja 6.7000 oh x Rp. 115,000.00 = Rp. 770,500.00
Tukang kayu 20.1000 oh x Rp. 172,000.00 = Rp. 3,457,200.00
Kepala Tukang 2.0100 oh x Rp. 207,000.00 = Rp. 416,070.00
Mandor 0.3350 oh x Rp. 227,000.00 = Rp. 76,045.00
Jumlah (2) Rp. 4,719,815.00
Jumlah (1) + (2) Rp. 16,319,315.00 Rp. 16,319,310.00
4.6.1.20.1 1 M² Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. III
4.6.1.20.1.a Bahan
Kayu 0.0163 m ³ × Rp. 6,900,000.00 = Rp. 112,470.00
Paku biasa 0.2500 kg × Rp. 23,000.00 = Rp. 5,750.00
Jumlah (1) Rp. 118,220.00
4.6.1.20.1.b Tenaga
Pekerja 0.2000 Oh × Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.3000 Oh × Rp. 172,000.00 = Rp. 51,600.00
Kepala tukang 0.0300 Oh × Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0100 Oh × Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 83,080.00
Jumlah (1) + (2) Rp. 201,300.00 Rp. 201,300.00
A. 4.6.1.21.a Bahan
Papan Kayu 0.0108 m3 x Rp. 20,125,000.00 = Rp. 217,350.00
Paku biasa 0.1000 kg x Rp. 23,000.00 = Rp. 2,300.00
Jumlah (1) Rp. 219,650.00 ###
A. 4.6.1.21.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 51,175.00
Jumlah (1) + (2) Rp. 270,825.00 Rp. 270,820.00
4.6.1.22.1.a Bahan
Papan Kayu 0.0110 m3 x Rp. 10,350,000.00 = Rp. 113,850.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
A. 4.6.1.23.a Bahan
Balok Kayu 0.0280 m3 x Rp. 10,350,000.00 = Rp. 289,800.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 293,250.00
4.6.1.23.1 1 M Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. III
2
4.6.1.23.1.a Bahan
Balok Kayu 0.0280 m3 x Rp. 6,900,000.00 = Rp. 193,200.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 196,650.00
4.6.1.23.1.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 105,781.00
Jumlah (1) + (2) Rp. 302,431.00 Rp. 302,430.00
A. 4.6.1.24 1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Lapis Seng
A. 4.6.1.24.a Bahan
Papan Kayu 0.0400 m3 x Rp. 6,900,000.00 = Rp. 276,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Seng plat bjls 22 8.0000 kk x Rp. 104,500.00 = Rp. 836,000.00
Jumlah (1) Rp. 1,137,850.00
A. 4.6.1.24.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,842,300.00 Rp. 1,842,300.00
A. 4.6.1.26.a Bahan
Papan Kayu 0.0070 m3 x Rp. 20,125,000.00 = Rp. 140,875.00
Paku biasa 0.1000 kg x Rp. 23,000.00 = Rp. 2,300.00
Paku skrup 0.1500 kg x Rp. 69,000.00 = Rp. 10,350.00
Jumlah (1) Rp. 153,525.00
A. 4.6.1.26.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang kayu 1.8000 oh x Rp. 172,000.00 = Rp. 309,600.00
Kepala Tukang 0.1800 oh x Rp. 207,000.00 = Rp. 37,260.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 422,670.00
Jumlah (1) + (2) Rp. 576,195.00 Rp. 576,190.00
A. 4.6.1.28 1 M Pemasangan Daun Pintu Panel Double Tripleks 9 mm Lapis HPL Rangka Kayu
2
A. 4.6.1.28.a Bahan
Kayu sembarang 0.0250 m3 x Rp. 6,325,000.00 = Rp. 158,125.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
HPL 2.0000 m2 x Rp. 184,000.00 = Rp. 368,000.00
Tripleks 9 mm 2.0000 m2 x Rp. 138,000.00 = Rp. 276,000.00
Jumlah (1) Rp. 828,665.00
A. 4.6.1.29.a Bahan
Balok Kayu sembarang 0.0280 m3 x Rp. 6,325,000.00 = Rp. 177,100.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Kalsiboard 1,2x2,4 m 0.8600 lbr x Rp. 80,500.00 = Rp. 69,230.00
Lem kayu 0.5600 kg x Rp. 51,700.00 = Rp. 28,952.00
Jumlah (1) Rp. 278,732.00
A. 4.6.1.29.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 419,622.00 Rp. 419,620.00
A. 4.1.1.3.a Bahan
Semen portland 299.0000 kg x Rp. 1,700.00 = Rp. 508,300.00
Pasir beton 0.5710 m3 x Rp. 172,500.00 = Rp. 98,497.50
Kerikil beton 0.7530 m3 x Rp. 230,000.00 = Rp. 173,190.00
Jumlah (1) Rp. 779,987.50
A. 4.1.1.3.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,041,674.50 Rp. 1,041,670.00
A. 4.1.1.4 1 M3 Pembuatan Lantai Kerja Beton Mutu f'c = 7,4 MPa slump (3-6) cm, w/c = 0,87
A. 4.1.1.4.a Bahan
Semen portland 230.0000 kg x Rp. 1,700.00 = Rp. 391,000.00
Pasir beton 0.6380 m3 x Rp. 172,500.00 = Rp. 110,055.00
Kerikil beton 0.7610 m3 x Rp. 230,000.00 = Rp. 175,030.00
Jumlah (1) Rp. 676,085.00
A. 4.1.1.4.b Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0600 oh x Rp. 227,000.00 = Rp. 13,620.00
Jumlah (2) Rp. 190,160.00
Jumlah (1) + (2) Rp. 866,245.00 Rp. 866,240.00
A. 4.1.1.5 1 M3 Pembuatan Beton Mutu f'c = 14,5 MPa, slump (120 ±20) mm
A. 4.1.1.5.a Bahan
Semen portland 326.0000 kg x Rp. 1,700.00 = Rp. 554,200.00
Pasir beton 0.5430 m3 x Rp. 172,500.00 = Rp. 93,667.50
Kerikil beton 0.7620 m3 x Rp. 230,000.00 = Rp. 175,260.00
Jumlah (1) Rp. 823,127.50
A. 4.1.1.5.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,084,814.50 Rp. 1,084,810.00
A. 4.1.1.8.a Bahan
Semen portland 384.0000 kg x Rp. 1,700.00 = Rp. 652,800.00
Pasir beton 0.4940 m3 x Rp. 172,500.00 = Rp. 85,215.00
Kerikil beton 0.7700 m3 x Rp. 230,000.00 = Rp. 177,100.00
Jumlah (1) Rp. 915,115.00
A. 4.1.1.8.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,176,802.00 Rp. 1,176,800.00
4.1.1.8.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 21,7 MPa
4.1.1.8.1.a Bahan
Ready Mix Concrete Mutu f'c = 21,7 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,092,000.00 = Rp. 1,092,000.00
Jumlah (1) Rp. 1,092,000.00
4.1.1.8.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,222,843.50 Rp. 1,222,840.00
4.1.1.10.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 26,4 MPa
4.1.1.10.1.a Bahan
Ready Mix Concrete Mutu f'c = 26,4 MPa(Agg. Batu Pecah) 1.0000 m3 x Rp. 1,173,000.00 = Rp. 1,173,000.00
Jumlah (1) Rp. 1,173,000.00
4.1.1.10.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,303,843.50 Rp. 1,303,840.00
A. 4.1.1.11.a Bahan
Semen portland 439.0000 kg x Rp. 1,700.00 = Rp. 746,300.00
Pasir beton 0.4790 m3 x Rp. 172,500.00 = Rp. 82,627.50
Kerikil beton 0.7450 m3 x Rp. 230,000.00 = Rp. 171,350.00
Jumlah (1) Rp. 1,000,277.50
A. 4.1.1.11.b Tenaga
Pekerja 2.1000 oh x Rp. 115,000.00 = Rp. 241,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.1050 oh x Rp. 227,000.00 = Rp. 23,835.00
Jumlah (2) Rp. 332,780.00
Jumlah (1) + (2) Rp. 1,333,057.50 Rp. 1,333,050.00
4.1.1.11.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 28,8 MPa
4.1.1.11.1.a Bahan
Ready Mix Concrete Mutu f'c = 28,8 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,207,000.00 = Rp. 1,207,000.00
Jumlah (1) Rp. 1,207,000.00
4.1.1.11.1.b Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Tukang batu 0.1750 oh x Rp. 172,000.00 = Rp. 30,100.00
Kepala Tukang 0.0175 oh x Rp. 207,000.00 = Rp. 3,622.50
Mandor 0.0525 oh x Rp. 227,000.00 = Rp. 11,917.50
Jumlah (2) Rp. 166,390.00
Jumlah (1) + (2) Rp. 1,373,390.00 Rp. 1,373,390.00
A. 4.1.1.12 1 M3 Pembuatan Beton Mutu f'c = 31,2 MPa, slump (120 ± 20) mm
A. 4.1.1.12.a Bahan
Semen portland 448.0000 kg x Rp. 1,700.00 = Rp. 761,600.00
Pasir beton 0.4760 m3 x Rp. 172,500.00 = Rp. 82,110.00
Kerikil beton 0.7410 m3 x Rp. 230,000.00 = Rp. 170,430.00
Jumlah (1) Rp. 1,014,140.00
A. 4.1.1.12.b Tenaga
Pekerja 2.1000 oh x Rp. 115,000.00 = Rp. 241,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.1050 oh x Rp. 227,000.00 = Rp. 23,835.00
Jumlah (2) Rp. 332,780.00
Jumlah (1) + (2) Rp. 1,346,920.00 Rp. 1,346,920.00
4.1.1.22.1.a Bahan
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Jumlah (1) Rp. 12,640.00
A. 4.1.1.22.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 159,622.00 Rp. 159,620.00
4.1.1.23.1.a Bahan
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Jumlah (1) Rp. 12,640.00
4.1.1.23.1.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 159,622.00 Rp. 159,620.00
A. 4.1.1.24.1.a Bahan
Papan Kayu sembarang 0.0200 m3 x Rp. 6,325,000.00 = Rp. 126,500.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0075 m3 x Rp. 6,325,000.00 = Rp. 47,437.50
Tripleks tebal 6 mm 0.1750 lbr x Rp. 103,500.00 = Rp. 18,112.50
Jumlah (1) Rp. 198,370.00
A. 4.1.1.24.1.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 345,352.00 Rp. 345,350.00
A. 4.1.1.27.a Bahan
Papan Kayu sembarang 0.0264 m3 x Rp. 6,325,000.00 = Rp. 166,980.00
Paku biasa 0.6000 kg x Rp. 23,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 180,780.00
A. 4.1.1.27.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 28,701.00
Jumlah (1) + (2) Rp. 209,481.00 Rp. 209,480.00
A. 4.5.2.32.1 1 M Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,30 mm
2
A. 4.5.2.32.1.a Bahan
Atap genteng metal tebal 0,30 mm 1.3000 lbr x Rp. 62,000.00 = Rp. 80,600.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 94,400.00
A. 4.5.2.32.1.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 136,897.00 Rp. 136,890.00
A. 4.5.2.32.2 1 M2 Pemasangan Genteng Metal ukr. 800x100 Atap Pelana Tebal 0,35 mm
A. 4.5.2.32.2.a Bahan
Atap genteng metal tebal 0,35 mm 1.3000 lbr x Rp. 74,700.00 = Rp. 97,110.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 110,910.00
A. 4.5.2.32.2.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 153,407.00 Rp. 153,400.00
A. 4.5.2.32.3 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,40 mm
A. 4.5.2.32.3.a Bahan
Atap genteng metal tebal 0,40 mm 1.3000 lbr x Rp. 85,200.00 = Rp. 110,760.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 124,560.00
A. 4.5.2.32.3.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 167,057.00 Rp. 167,050.00
A. 4.5.2.33.1 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,30 mm
A. 4.5.2.33.1.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 62,000.00 = Rp. 124,000.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 137,800.00
A. 4.5.2.33.1.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 180,297.00 Rp. 180,290.00
A. 4.5.2.33.2 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,35 mm
A. 4.5.2.33.2.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 74,700.00 = Rp. 149,400.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 163,200.00
A. 4.5.2.33.2.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 205,697.00 Rp. 205,690.00
A. 4.5.2.33.3 1 M Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,40 mm
2
A. 4.5.2.33.3.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 85,200.00 = Rp. 170,400.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 184,200.00
A. 4.5.2.33.3.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 226,697.00 Rp. 226,690.00
A. 4.5.2.40.a Bahan
Nok/rabung seng 0.3000 lbr x Rp. 19,500.00 = Rp. 5,850.00
Paku seng 0.0400 kg x Rp. 40,200.00 = Rp. 1,608.00
Jumlah (1) Rp. 7,458.00
A. 4.5.2.40.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0700 oh x Rp. 172,000.00 = Rp. 12,040.00
Kepala Tukang 0.0070 oh x Rp. 207,000.00 = Rp. 1,449.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 32,101.00
Jumlah (1) + (2) Rp. 39,559.00 Rp. 39,550.00
A. 4.5.2.46.a Bahan
Nok/Rabung zincalume 1.1000 lbr x Rp. 82,200.00 = Rp. 90,420.00
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 91,800.00
A. 4.5.2.46.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0700 oh x Rp. 172,000.00 = Rp. 12,040.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 32,308.00
Jumlah (1) + (2) Rp. 124,108.00 Rp. 124,100.00
A. 4.4.3.45.a Bahan
Underlayer 1.0500 m2 x Rp. 75,500.00 = Rp. 79,275.00
Lem 0.3500 kg x Rp. 51,700.00 = Rp. 18,095.00
Jumlah (1) Rp. 97,370.00
A. 4.4.3.45.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.1200 oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 38,286.00
Jumlah (1) + (2) Rp. 135,656.00 Rp. 135,650.00
A. 4.4.3.57.a Bahan
Batu alam paras 1.1000 m2 x Rp. 230,000.00 = Rp. 253,000.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 279,012.50
A. 4.4.3.57.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 434,902.50 Rp. 434,900.00
A. 4.4.3.60.a Bahan
Wallpaper 2.2000 m1 x Rp. 86,200.00 = Rp. 189,640.00
Lem 0.2500 kg x Rp. 51,700.00 = Rp. 12,925.00
Jumlah (1) Rp. 202,565.00
A. 4.4.3.60.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.1750 oh x Rp. 172,000.00 = Rp. 30,100.00
Kepala Tukang 0.0170 oh x Rp. 207,000.00 = Rp. 3,519.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 74,323.00
Jumlah (1) + (2) Rp. 276,888.00 Rp. 276,880.00
A. 4.4.3.67.a Bahan
Paving blok tbl. 8 cm berwarna 1.0100 m2 x Rp. 127,700.00 = Rp. 128,977.00
Pasir beton 2.0700 m3 x Rp. 172,500.00 = Rp. 357,075.00
Jumlah (1) Rp. 486,052.00
A. 4.4.3.67.b Tenaga
Pekerja 0.5000 oh x Rp. 115,000.00 = Rp. 57,500.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 154,145.10
A. 4.4.3.67.c Peralatan
Peralatan 10.0000 % x Rp. 127,700.00 = Rp. 12,770.00
Rp. 12,770.00
Jumlah (1) + (2) + (3) Rp. 652,967.10 Rp. 652,960.00
A. 4.4.3.73.a Bahan
Keramik dinding ukr. 25x45 cm warna/motif 8.8900 bh x Rp. 12,900.00 = Rp. 114,681.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 186,617.50
A. 4.4.3.73.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 387,047.50 Rp. 387,040.00
A. 4.4.3.75.a Bahan
Keramik dinding ukr. 20x25 cm warna/motif 20.0000 bh x Rp. 4,300.00 = Rp. 86,000.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 157,936.50
A. 4.4.3.75.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 358,366.50 Rp. 358,360.00
A. 4.4.3.77.a Bahan
Batu alam andesit 1.1000 m2 x Rp. 287,500.00 = Rp. 316,250.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 342,262.50
A. 4.4.3.77.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 498,152.50 Rp. 498,150.00
A. 4.4.3.80.a Bahan
Paving block tipe segi enam (merah) 44.0000 bh x Rp. 2,800.00 = Rp. 123,200.00
Pasir pasang 0.0550 m3 x Rp. 172,500.00 = Rp. 9,487.50
Jumlah (1) Rp. 132,687.50
A. 4.4.3.80.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 73,240.00
Jumlah (1) + (2) Rp. 205,927.50 Rp. 205,920.00
A. 4.7.1.5 1 M Pengecatan Bidang Kayu Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Minyak)
2
A. 4.7.1.5.a Bahan
Cat menie kayu 0.2000 kg x Rp. 37,900.00 = Rp. 7,580.00
Plamir 0.1500 kg x Rp. 9,200.00 = Rp. 1,380.00
Cat dasar 0.1700 kg x Rp. 46,000.00 = Rp. 7,820.00
Cat minyak / kilat 0.3500 kg x Rp. 77,000.00 = Rp. 26,950.00
Kuas 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0300 ltr x Rp. 57,500.00 = Rp. 1,725.00
Amplas 0.2000 lbr x Rp. 13,800.00 = Rp. 2,760.00
Jumlah (1) Rp. 48,502.00
A. 4.7.1.5.b Tenaga
Pekerja 0.0700 Oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.1050 Oh x Rp. 172,000.00 = Rp. 18,060.00
Kepala tukang 0.0040 Oh x Rp. 207,000.00 = Rp. 828.00
Mandor 0.0030 Oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 27,619.00
Jumlah (1) + (2) Rp. 76,121.00 Rp. 76,120.00
A. 4.7.1.10 1 M Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Penutup)
2
A. 4.7.1.10.a Bahan
Plamir 0.1200 kg x Rp. 9,200.00 = Rp. 1,104.00
Cat dasar / sealer 0.1200 kg x Rp. 46,000.00 = Rp. 5,520.00
Cat dinding / tembok 0.2600 kg x Rp. 103,500.00 = Rp. 26,910.00
Jumlah (1) Rp. 33,534.00
A. 4.7.1.10.b Tenaga
Pekerja 0.0400 Oh x Rp. 115,000.00 = Rp. 4,600.00
Tukang cat 0.1200 Oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala tukang 0.0120 Oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0020 Oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 28,178.00
Jumlah (1) + (2) Rp. 61,712.00 Rp. 61,710.00
A. 4.7.1.17 1 M2 Pengecatan Permukaan Baja / Besi dengan Menie Besi dan Perancah Kayu
A. 4.7.1.17.a Bahan
Cat menie besi 0.1000 kg x Rp. 43,700.00 = Rp. 4,370.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Peranca kayu sembarang 0.0020 m3 x Rp. 6,325,000.00 = Rp. 12,650.00
Jumlah (1) Rp. 17,882.00
A. 4.7.1.17.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang cat 0.2250 oh x Rp. 172,000.00 = Rp. 38,700.00
Kepala Tukang 0.0225 oh x Rp. 207,000.00 = Rp. 4,657.50
Mandor 0.0075 oh x Rp. 227,000.00 = Rp. 1,702.50
Jumlah (2) Rp. 73,810.00
Jumlah (1) + (2) Rp. 91,692.00 Rp. 91,690.00
A. 4.7.1.19 1 M2 Pengecatan Permukaan Baja Galvanis secara Manual 1 Lapis Cat Mutakhir
A. 4.7.1.19.a Bahan
Cat 0.3000 kg x Rp. 77,000.00 = Rp. 23,100.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 23,962.00
A. 4.7.1.19.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang cat 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 20,385.00
Jumlah (1) + (2) Rp. 44,347.00 Rp. 44,340.00
A. 4.7.1.21 1 M2 Pengecatan Permukaan Baja Galvanis secara Semprot Sistem 3 Lapis Cat Mutakhir
A. 4.7.1.21.a Bahan
Cat dasar 0.3000 kg x Rp. 46,000.00 = Rp. 13,800.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 14,375.00
A. 4.7.1.21.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang cat 0.7000 oh x Rp. 172,000.00 = Rp. 120,400.00
Kepala Tukang 0.0700 oh x Rp. 207,000.00 = Rp. 14,490.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 185,430.00
Jumlah (1) + (2) Rp. 199,805.00 Rp. 199,800.00
A. 4.7.1.23.a Bahan
Waterproof dasar 0.1000 kg x Rp. 63,200.00 = Rp. 6,320.00
Waterproof penutup 0.2600 kg x Rp. 63,200.00 = Rp. 16,432.00
Jumlah (1) Rp. 22,752.00
A. 4.7.1.23.b Tenaga
Pekerja 0.0200 oh x Rp. 115,000.00 = Rp. 2,300.00
Tukang cat 0.0630 oh x Rp. 172,000.00 = Rp. 10,836.00
Kepala Tukang 0.0063 oh x Rp. 207,000.00 = Rp. 1,304.10
Mandor 0.0025 oh x Rp. 227,000.00 = Rp. 567.50
Jumlah (2) Rp. 15,007.60
Jumlah (1) + (2) Rp. 37,759.60 Rp. 37,750.00
A. 4.7.1.25.b Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.0090 oh x Rp. 172,000.00 = Rp. 1,548.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 11,087.00
Jumlah (1) + (2) Rp. 39,847.00 Rp. 39,840.00
A. 4.7.1.26 1 M Pengecatan Bidang Baja / Besi dengan Cat Minyak dan Perancah Kayu
2
A. 4.7.1.26.a Bahan
Cat menie besi 0.2000 kg x Rp. 43,700.00 = Rp. 8,740.00
Cat minyak / kilat 0.2600 kg x Rp. 77,000.00 = Rp. 20,020.00
Peranca kayu sembarang 0.0020 m3 x Rp. 6,325,000.00 = Rp. 12,650.00
Jumlah (1) Rp. 41,410.00
A. 4.7.1.26.b Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.0090 oh x Rp. 172,000.00 = Rp. 1,548.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 11,087.00
Jumlah (1) + (2) Rp. 52,497.00 Rp. 52,490.00
A. 5.1.1.25.a Bahan
Pipa PVC tipe AW Ø 1/2" 1.2000 m' x Rp. 7,300.00 = Rp. 8,760.00
Perlengkapan 35% x Rp. 7,300.00 = Rp. 2,555.00
Jumlah (1) Rp. 11,315.00
A. 5.1.1.25.b Tenaga
Pekerja 0.0360 oh x Rp. 115,000.00 = Rp. 4,140.00
Tukang batu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 16,156.00
Jumlah (1) + (2) Rp. 27,471.00 Rp. 27,470.00
A. 5.1.1.27.a Bahan
Pipa PVC tipe AW Ø 1" 1.2000 m' x Rp. 13,600.00 = Rp. 16,320.00
Perlengkapan 35% x Rp. 13,600.00 = Rp. 4,760.00
Jumlah (1) Rp. 21,080.00
A. 5.1.1.27.b Tenaga
Pekerja 0.0360 oh x Rp. 115,000.00 = Rp. 4,140.00
Tukang batu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 16,156.00
Jumlah (1) + (2) Rp. 37,236.00 Rp. 37,230.00
A. 5.1.1.31.a Bahan
Pipa PVC tipe AW Ø 3" 1.2000 m' x Rp. 66,900.00 = Rp. 80,280.00
Perlengkapan 35% x Rp. 66,900.00 = Rp. 23,415.00
Jumlah (1) Rp. 103,695.00
A. 5.1.1.31.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 36,237.50
Jumlah (1) + (2) Rp. 139,932.50 Rp. 139,930.00
A. 5.1.1.40.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. Ø 15 cm panjang 1 m 1.0000 bh x Rp. 28,700.00 = Rp. 28,700.00
Jumlah (1) Rp. 29,824.50
A. 5.1.1.40.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 109,269.50 Rp. 109,260.00
A. 5.1.1.42.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. Ø 30 cm panjang 1 m 1.0000 bh x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 47,124.50
A. 5.1.1.42.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 126,569.50 Rp. 126,560.00
A. 5.1.1.44.a Bahan
Semen portland @ 40 kg 0.0225 zak x Rp. 68,000.00 = Rp. 1,530.00
Pasir pasang 0.0022 m3 x Rp. 172,500.00 = Rp. 379.50
Riol ukr. Ø 50 cm panjang 1 m 1.0000 bh x Rp. 103,500.00 = Rp. 103,500.00
Jumlah (1) Rp. 105,409.50
A. 5.1.1.44.b Tenaga
Pekerja 0.6666 oh x Rp. 115,000.00 = Rp. 76,659.00
Tukang batu 0.2500 oh x Rp. 172,000.00 = Rp. 43,000.00
Kepala Tukang 0.0250 oh x Rp. 207,000.00 = Rp. 5,175.00
Mandor 0.0332 oh x Rp. 227,000.00 = Rp. 7,536.40
Jumlah (2) Rp. 132,370.40
Jumlah (1) + (2) Rp. 237,779.90 Rp. 237,770.00
A. 5.1.1.47.a Bahan
Semen portland @ 40 kg 0.0450 zak x Rp. 68,000.00 = Rp. 3,060.00
Pasir pasang 0.0042 m3 x Rp. 172,500.00 = Rp. 724.50
Riol ukr. Ø 100 cm panjang 1 m 1.0000 bh x Rp. 143,700.00 = Rp. 143,700.00
Jumlah (1) Rp. 147,484.50
A. 5.1.1.47.b Tenaga
Pekerja 1.3331 oh x Rp. 115,000.00 = Rp. 153,306.50
Tukang batu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0662 oh x Rp. 227,000.00 = Rp. 15,027.40
Jumlah (2) Rp. 264,683.90
Jumlah (1) + (2) Rp. 412,168.40 Rp. 412,160.00
A. 5.1.1.49.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. 1/2 Ø 20 cm panjang 1 m 1.0000 bh x Rp. 19,500.00 = Rp. 19,500.00
Jumlah (1) Rp. 20,624.50
A. 5.1.1.49.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 100,069.50 Rp. 100,060.00
A. 4.2.1.4 1 M2 Pembuatan Pintu Besi Plat Baja tbl. 2 mm Rangkap, Rangka Baja Siku
A. 4.2.1.4.a Bahan
Besi siku L 30.30.3 15.0000 kg x Rp. 9,400.00 = Rp. 141,000.00
Besi plat baja 32.8000 kg x Rp. 12,600.00 = Rp. 413,280.00
Kawat las 0.0500 kg x Rp. 25,500.00 = Rp. 1,275.00
Jumlah (1) Rp. 555,555.00
A. 4.2.1.4.b Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Tukang las 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0520 oh x Rp. 227,000.00 = Rp. 11,804.00
Jumlah (2) Rp. 334,889.00
Jumlah (1) + (2) + (3) Rp. 890,444.00 Rp. 890,440.00
A. 4.2.1.11.a Bahan
Profil aluminium 1.1000 m x Rp. 46,000.00 = Rp. 50,600.00
Skrup fixer 2.0000 Bh x Rp. 19,500.00 = Rp. 39,000.00
Sealant 0.0600 tube x Rp. 14,900.00 = Rp. 894.00
Jumlah (1) Rp. 90,494.00
A. 4.2.1.11.b Tenaga
Pekerja 0.0430 oh x Rp. 115,000.00 = Rp. 4,945.00
Tukang 0.0430 oh x Rp. 172,000.00 = Rp. 7,396.00
Kepala Tukang 0.0043 oh x Rp. 207,000.00 = Rp. 890.10
Mandor 0.0021 oh x Rp. 227,000.00 = Rp. 476.70
Jumlah (2) Rp. 13,707.80
Jumlah (1) + (2) Rp. 104,201.80 Rp. 104,200.00
A. 4.2.1.19 1 M1 Pemasangan Talang 1/2 Lingkaran D - 15 cm, Seng Plat BJLS 30 lebar 45 cm
A. 4.2.1.19.a Bahan
Seng plat 1.0500 m x Rp. 59,800.00 = Rp. 62,790.00
Paku 0.0100 kg x Rp. 40,200.00 = Rp. 402.00
Besi Strip 0.5000 kg x Rp. 9,700.00 = Rp. 4,850.00
Jumlah (1) Rp. 68,042.00
A. 4.2.1.19.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 76,876.00
Jumlah (1) + (2) Rp. 144,918.00 Rp. 144,910.00
A. 4.2.1.20 1 M Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x120 cm, untuk Partisi
2
A. 4.2.1.20.a Bahan
Rangka metal hollow 40.40.2 mm 3.5000 m1 x Rp. 46,000.00 = Rp. 161,000.00
Assesoris (perkuatan, las dll) 100% Ls x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 207,000.00
A. 4.2.1.20.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang 0.2500 oh x Rp. 172,000.00 = Rp. 43,000.00
Kepala Tukang 0.0250 oh x Rp. 207,000.00 = Rp. 5,175.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 79,876.00
Jumlah (1) + (2) Rp. 286,876.00 Rp. 286,870.00
A. 4.2.1.21 1 M2 Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x60 cm, untuk Plafond
A. 4.2.1.21.a Bahan
Rangka metal hollow 40.40.2 mm 4.0000 m1 x Rp. 46,000.00 = Rp. 184,000.00
Assesoris (perkuatan, las dll) 100% Ls x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 230,000.00
A. 4.2.1.21.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 111,781.00
Jumlah (1) + (2) Rp. 341,781.00 Rp. 341,780.00
A. 4.5.1.5 1 M2 Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 4mm
A. 4.5.1.5.a Bahan
Triplek tebal 4mm 0.3750 lbr x Rp. 92,000.00 = Rp. 34,500.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Jumlah (1) Rp. 35,190.00
A. 4.5.1.5.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 67,095.00 Rp. 67,090.00
A. 4.5.1.5.1.a Bahan
Triplek tebal 6 mm 0.3750 lbr x Rp. 103,500.00 = Rp. 38,812.50
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Jumlah (1) Rp. 39,502.50
A. 4.5.1.5.1.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 71,407.50 Rp. 71,400.00
A. 4.5.1.7 1 M2 Pemasangan Langit - langit Gypsum board ukr. 120x240x9 mm, tbl. 9mm
A. 4.5.1.7.a Bahan
Gypsum board 0.3640 lbr x Rp. 60,900.00 = Rp. 22,167.60
Paku skrup 0.1100 kg x Rp. 69,000.00 = Rp. 7,590.00
Jumlah (1) Rp. 29,757.60
A. 4.5.1.7.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 22,270.00
Jumlah (1) + (2) Rp. 52,027.60 Rp. 52,020.00
4.5.1.7.1.a Bahan
List gypsum profil 16-20 cm 1.0500 m x Rp. 14,300.00 = Rp. 15,015.00
Tepung gypsum 0.1500 kg x Rp. 5,700.00 = Rp. 855.00
Jumlah (1) Rp. 15,870.00
4.5.1.7.1.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 19,143.00
Jumlah (1) + (2) Rp. 35,013.00 Rp. 35,010.00
4.5.1.7.2.a Bahan
List gypsum profil 12-15 cm 1.0500 m x Rp. 11,500.00 = Rp. 12,075.00
Tepung gypsum 0.1500 kg x Rp. 5,700.00 = Rp. 855.00
Jumlah (1) Rp. 12,930.00
A. 4.5.1.9.a Bahan
List kayu profil 1.0500 m x Rp. 34,500.00 = Rp. 36,225.00
Paku 0.0100 kg x Rp. 23,000.00 = Rp. 230.00
Jumlah (1) Rp. 36,455.00
A. 4.5.1.9.b Tenaga
Pekerja 0.0500 oh x Rp. 115,000.00 = Rp. 5,750.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 16,066.00
Jumlah (1) + (2) Rp. 52,521.00 Rp. 52,520.00
A. 4.4.1.1 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 2Pp Rp 290,300.00
A. 4.4.1.2 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 3Pp Rp 274,260.00
A. 4.4.1.3 M2
Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 4Pp Rp 263,720.00
A. 4.4.1.4 M2
Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 5Pp Rp 257,880.00
A. 4.4.1.7 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 2Pp Rp 140,040.00
A. 4.4.1.8 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 3Pp Rp 132,600.00
A. 4.4.1.9 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 4Pp Rp 128,240.00
A. 4.4.1.10 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 5Pp Rp 125,490.00
A. 4.4.1.22 M2
Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 3Pp Rp 1,287,910.00
A. 4.4.1.23 M2 Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 4Pp Rp 1,287,910.00
A. 4.4.1.25 M2
Pemasangan Dinding Bata Ringan tebal 7,5 cm dengan Mortar Siap Pakai Rp 9,373,190.00
A. 4.4.1.26 M2
Pemasangan Dinding Bata Ringan tebal 10 cm dengan Mortar Siap Pakai Rp 9,370,270.00
A. 4.4.1.27 M2
Pemasangan Glass Block Rp 936,820.00
A. 4.6.1.1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. I Rp 27,149,100.00
A. 4.6.1.2 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. II Rp 16,727,150.00
4.6.1.2.1 M3
Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. III Rp 12,587,150.00
A. 4.6.1.3 M2
Pembuatan dan Pemasangan Pintu Klamp Standar, Kayu kls. II Rp 661,820.00
A. 4.6.1.4 M2
Pembuatan dan Pemasangan Pintu Klamp Sederhana, Kayu kls. III Rp 523,820.00
A. 4.6.1.5 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. I Rp 1,535,300.00
4.6.1.5.1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. II Rp 1,144,300.00
A. 4.6.1.6 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. I Rp 1,062,070.00
4.6.1.6.1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. II Rp 827,470.00
A. 4.6.1.7 M2
Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. I Rp 2,018,300.00
4.6.1.7.1 M3
Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. II Rp 1,392,700.00
A. 4.6.1.8 M2 Pembuatan Daun Pintu Tripleks Rangkap, Rangka Kayu kls. II tertutup Rp 870,400.00
A. 4.6.1.8.1 M2 Pembuatan dan Pemasangan Pintu Tripleks Rangkap, Rangka Tertutup Kayu Lapis Seng Rp 1,609,570.00
A. 4.6.1.9 M2
Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. I Rp 1,197,300.00
4.6.1.9.1 M2
Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. II Rp 947,060.00
A. 4.6.1.10 M2
Pemasangan Jalusi Kusen Kayu kls. I Rp 1,749,440.00
4.6.1.10.1 M2 Pemasangan Jalusi Kusen Kayu kls. II Rp 1,162,940.00
A. 4.6.1.13 M3
Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. I Bentang 6m Rp 25,229,600.00
4.6.1.13.1 M3
Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. II Bentang 6m Rp 14,477,100.00
4.6.1.13.2 M3 Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. III Bentang 6m Rp 10,682,100.00
A. 4.6.1.14 M3
Pemasangan Kontruksi Kuda-kuda Ekspose, Kayu kls. I Rp 29,144,110.00
A. 4.6.1.15 M3
Pemasangan Kontruksi Gording, Kayu kls. II Rp 16,319,310.00
A. 4.6.1.16 M2 Pemasangan Rangka Atap Genteng Keramik, Kayu kls. II Rp 555,150.00
A. 4.6.1.17 M2
Pemasangan Rangka Atap Genteng Beton, Kayu kls. II Rp 772,500.00
A. 4.6.1.18 M2 Pemasangan Rangka Atap Sirap, Kayu kls. II Rp 184,490.00
A. 4.6.1.19 M2
Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. II Rp 256,070.00
4.6.1.19.1 M2
Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. III Rp 202,940.00
A. 4.6.1.20 M2 Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. II Rp 257,530.00
4.6.1.20.1 M2
Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. III Rp 201,300.00
A. 4.6.1.21 M1 Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. I Rp 270,820.00
4.6.1.21.1 M1
Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. II Rp 165,250.00
A. 4.6.1.22 M1
Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. I Rp 273,700.00
4.6.1.22.1 M1 Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. II Rp 166,170.00
A. 4.6.1.23 M2
Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. II Rp 399,030.00
4.6.1.23.1 M2 Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. III Rp 302,430.00
A. 4.6.1.24 M2
Pembuatan dan Pemasangan Daun Pintu Panel Kayu Lapis Seng Rp 1,842,300.00
A. 4.6.1.25 M2
Pemasangan Dinding Pemisah Tripleks Rangkap, Rangka Kayu kls. II Rp 542,210.00
A. 4.6.1.26 M2 Pemasangan Dinding Lambrisering dari Papan Kayu kls. I Rp 576,190.00
A. 4.6.1.27 M2
Pemasangan Dinding Lambrisering dari Triplek Ukr. (120 x 240) cm Rp 55,600.00
A. 4.6.1.28 M2 Pemasangan Daun Pintu Panel Double Tripleks 9 mm Lapis HPL Rangka Kayu Rp 1,292,140.00
A. 4.6.1.29 M2 Pemasangan Dinding Pemisah Kalsiboard Rangkap, Rangka Kayu Rp 419,620.00
A. 4.6.1.30 M2
Pemasangan Dinding Pemisah GRC Rangkap, Rangka Besi Rp 290,150.00
A. 4.6.1.31 M2 Pemasangan Dinding Pemisah GRC (1 Sisi), Rangka Besi Rp 250,360.00
A. 4.6.1.32 M2
Pemasangan Dinding Pemisah GRC Tanpa Rangka Rp 139,820.00
A. 4.6.1.33 M2 Pemasangan Dinding Kalsiplank (Dinding Susun Sirih) 1 Sisi Rp 773,100.00
A. 4.5.2.32 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,25 mm Rp 123,240.00
A. 4.5.2.32.1 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,30 mm Rp 136,890.00
A. 4.5.2.32.2 M2 Pemasangan Genteng Metal ukr. 800x100 Atap Pelana Tebal 0,35 mm Rp 153,400.00
A. 4.5.2.32.3 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,40 mm Rp 167,050.00
A. 4.5.2.33 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,25 mm Rp 159,290.00
A. 4.5.2.33.1 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,30 mm Rp 180,290.00
A. 4.5.2.33.2 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,35 mm Rp 205,690.00
A. 4.5.2.33.3 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,40 mm Rp 226,690.00
A. 4.5.2.37 M1
Pemasangan Nok/Rabung Genteng Metal Rp 96,940.00
A. 4.5.2.39 M2
Pemasangan Atap Seng Gelombang Rp 70,990.00
A. 4.5.2.40 M1 Pemasangan Nok/Rabung Seng Rp 39,550.00
A. 4.5.2.43 M2 Pemasangan Aluminium Foil / Sisalation Rp 40,980.00
A. 4.5.2.45 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,25 mm Rp 78,230.00
A. 4.5.2.45.1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,30 mm Rp 87,070.00
A. 4.5.2.45.2 M2
Pemasangan Atap Zincalume (Spandeck) Tebal 0,35 mm Rp 101,810.00
A. 4.5.2.45.3 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,40 mm Rp 120,920.00
A. 4.5.2.46 M1
1 M Pemasangan Nok/Rabung Zincalume (Spandeck)
1
Rp 124,100.00
A. 4.5.2.47 M2 Pemasangan Atap Genteng Keramik Rp 369,340.00
A. 4.5.2.48 M1
Pemasangan Rabung Genteng Keramik Rp 174,080.00
A. 4.5.2.49 M2
Pemasangan Atap Single Bituminius Rp 434,040.00
A. 4.5.1.1 M2 Pemasangan Langit - langit Asbes Semen, tbl. 4 mm, 5 mm, dan 6 mm Rp 43,370.00
A. 4.5.1.5 M2 Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 4 mm Rp 67,090.00
A. 4.5.1.5.1 M2
Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 6 mm Rp 71,400.00
A. 4.5.1.6 M2
Pemasangan Langit - langit Lambriziring Kayu, Tebal 9 mm Rp 358,970.00
A. 4.5.1.7 M2
Pemasangan Langit - langit Gypsum board ukr. 120x240x9 mm, tbl. 9 mm Rp 52,020.00
4.5.1.7.1 M1 Pemasangan List Plafond Gypsum Profil 16-20 cm Rp 35,010.00
4.5.1.7.2 M1
Pemasangan List Plafond Gypsum Profil 12-15 cm Rp 32,070.00
A. 4.5.1.9 M1
Pemasangan List Langit - langit Kayu Profil Rp 52,520.00
3. PEKERJAAN PEMAGARAN
1 ### PT 6.1. - ### #N/A #N/A
2 ### PB 6.6. - ### #N/A #N/A
3 Pek. Sloof ukr. 20x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.17. - ### #N/A #N/A
4 Pek. Kolom ukr. 30x30 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.18. - ### #N/A #N/A
5 ### PD 6.8. - ### #N/A #N/A
6 ### PL 6.5. - ### #N/A #N/A
7 ### PPL 6.21. - ### #N/A #N/A
8 Relief minimalis Ls - M2 #REF! #REF!
9 Pasang jerjak / teralis pagar besi hollo + cat Ls - M2 575,000.00 -
10 Pasang gerbang pagar besi hollo komplit + cat Ls - M2 1,092,000.00 -
11 ### PC 6.8. - ### #N/A #N/A
12 Pengecatan coating batu alam Ls - M2 92,000.00 -
Jumlah Total 3 #N/A
5. PEKERJAAN AKHIR
1 Laporan dan foto dokumentasi proyek ls 1.00 unit - -
2 Asbuilt drawing ls 1.00 unit - -
3 Pembersihan lokasi pekerjaan ls 1.00 unit - -
Jumlah Total 5 -
HIMPUNAN
1 PEKERJAAN PERSIAPAN 350,000.00
2 PEKERJAAN GEDUNG KANTOR #N/A
3 PEKERJAAN PEMAGARAN #N/A
4 PEKERJAAN LANSEKAP #N/A
5 PEKERJAAN AKHIR -
Biaya Konstruksi #N/A
PPn 10% #N/A
Jumlah Biaya Konstruksi #N/A
Pembulatan #N/A
#N/A
Binjai, 2017
HIMPUNAN
I PEKERJAAN PERSIAPAN 2,100,000.00
II PEKERJAAN PARIT #N/A
III PEKERJAAN LAIN-LAIN / PENYELESAIAN 3,800,000.00
Biaya Konstruksi #N/A
PPn 10% #N/A
Jumlah Biaya Konstruksi #N/A
Pembulatan #N/A
Terbilang : Rupiah
Binjai, 2019
Kepada : Ibu Kepala Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Dari : Kabid Cipta Karya
Tanggal : Maret 2019
Nomor :
Sifat : Penting
Lampiran : 1 (satu) eks
Perihal : Mohon Penandatanganan Surat Pengantar dan Analisis Harga Satuan Pekerjaan (AHSP)
1. Guna pelaksanaan Pembinaan Teknis Bangunan Gedung Negara dan Drainase Perkotaan, perlu dibuat
suatu acuan dalam hal penyusunan Analisis Harga Satuan Pekerjaan (AHSP) serta Harga Satuan Upah dan
Bahan yang dalam hal ini berpedoman pada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat
Republik Indonesia No: 28/PRT/M/2016 dan No: 11/PRT/M/2013 tentang Pedoman Analisis Harga Satuan
Pekerjaan Bidang Pekerjaan Umum dan Perumahan Rakyat, serta Standar Pekerjaan lainnya yang disusun
oleh Bidang Cipta Karya Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai.
2. Karena penyusunsn Analisis Harga Satuan Pekerjaan (AHSP) serta Harga Satuan Upah dan Bahan telah
selesai dibuat sesuai dengan ketentuan dan peraturan yang berlaku, mohon tanda tangan Ibu
KATA PENGANTAR
Dalam rangka pelaksanaan pembinaan Teknis Bangunan Gedung Negara dan Drainase Perkotaan
perlu dibuat acuan untuk keseragaman Harga Satuan Upah dan Bahan serta Analisis Harga Satuan
Pekerjaan (AHSP) di lingkungan Pemerintah Kota Binjai
Adapun penyusunan Harga Satuan Upah dan Bahan serta Analisis Harga Harga Satuan Pekerjaan (AHSP) yang
dibuat berpedoman kepada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia Nomor :
28/PRT/M/2016 dan Nomor : 11/PRT/M/2013 tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan
Umum dan Perumahan Rakyat serta Standar Pekerjaan lainnya. Harga Satuan Upah dan Bahan yang dipakai adalah
Harga Hasil Survey untuk tahun 2019.
Harga Upah Kerja dan Bahan yang tertuang dalam analisa ini hanya berlaku untuk pekerjaan di Kota Binjai.
Sedangkan untuk Kota / Kabupaten yang lain disesuaikan dengan Harga Upah Pekerja dan Bahan yang ditetapkan oleh
Pemerintah setempat.