IS 2911-Part 2
IS 2911-Part 2
Indian Standard
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
निर्माण — रीति सहं िता
भाग 2 इमारती लकड़ी की पाइल
( दसू रा पनु रीक्षण )
( Second Revision )
© BIS 2021
Price Group 5
Soil and Foundation Engineering Sectional Committee, CED 43
FOREWORD
This Indian Standard (Second Revision) was adopted by the Bureau of Indian Standards, after the draft finalized by
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
the Soil and Foundation Engineering Sectional Committee had been approved by the Civil Engineering Division
Council.
Piles find application in foundations to transfer loads from a structure to competent sub-surface strata having
adequate load-bearing capacity. The load transfer mechanism from a pile to the surrounding ground is complicated
and is not yet fully understood, although application of pile foundations is in practice over many decades. Broadly,
piles transfer axial loads either substantially by friction along its shaft and/or by the end bearing. Piles are used
where either of the above load transfer mechanism is possible depending upon the subsoil stratification at a
particular site. Construction of pile foundation requires a careful choice of piling system depending upon the
subsoil conditions, the load characteristics of the structure and the limitations of total settlement, differential
Indian Standard
DESIGN AND CONSTRUCTION OF
PILE FOUNDATIONS — CODE OF PRACTICE
PART 2 TIMBER PILES
( Second Revision )
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
1 SCOPE 3.6 Butt Diameter — Diameter at the larger end of the
pile shaft.
1.1 This standard (Part 2) covers the design and
construction of timber piles for earth retaining 3.7 Cut-off Level — It is the level where a pile is
structures, shore protection, slope protection, cut-off in order to make structural connection to the pile
compaction of ground or to support structures up to caps or beams or any other structural components at
3.1 For general terms relating to timber, reference shall 3.13 Initial Test Pile ― One or more piles, which are
be made to IS 707. not working piles, may be installed to assess the load
carrying capacity of a pile.
3.2 Allowable Load ― The load which may be
applied to a pile after taking into account its ultimate 3.14 Load Bearing Pile ― A pile formed in the ground
load capacity, group effect, the allowable settlement, for transmitting the load of a structure to the soil by the
negative skin friction and other relevant loading resistance developed at its tip and/or along its surface.
conditions including reversal of loads, if any. It may be formed either vertically or at an inclination
(batter pile) and may be required to resist uplift forces.
3.3 Anchor Pile ― An anchor pile means a pile meant
for resisting pull or uplift forces. If the pile supports the load primarily by resistance
developed at the pile tip or base, it is called ‘End bearing
3.4 Batter Pile (Raker Pile) ― The pile which is pile’ and, if primarily by friction along its surface, then
installed at an angle to the vertical. ‘Friction pile’.
3.5 Brooming — Separation of fibres at butt or tip of a 3.15 Net Displacement — The net vertical movement
timber pile, caused by excessive or improper driving or of the pile top after the pile has been subjected to a test
improper treatment or due to deceased timber. load and subsequently released.
1
IS 2911 (Part 2) : 2021
3.16 Pile Line — The rope used to lift a pile and hold it a) Site investigation data as laid down under
in place during the early stages of driving. IS 1892. Sections of trial boring, supplemented,
wherever appropriate, by penetration tests,
3.17 Pile Ring — A metal hoop used to bind the head should incorporate data/information down to
of a timber pile during driving to prevent splitting and depth sufficiently below the anticipated level of
brooming. founding of piles but this should generally be not
3.18 Pile Shoe — A metal protection for the foot of a less than 10 m beyond the pile founding level.
pile to prevent damage or to obtain greater penetration Adequacy of the bearing strata should be ensured
when driving through hard material. by supplementary tests, if required.
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
b) The nature of the soil both around and beneath the
3.19 Pile Spacing — The centre to centre distance proposed pile should be indicated on the basis of
between adjacent piles. appropriate tests of strength, compressibility, etc.
Ground water level and artesian conditions, if any,
3.20 Routine Load Test — It is carried out on a
should also be recorded. Results of chemical tests
working pile with a view to check whether pile is
to ascertain the sulphate, chloride and any other
capable of taking the working load assigned to it
deleterious chemical content of soil and water, and
without exceeding permissible settlement.
pH of soil should be indicated.
3.21 Routine Test Pile — A pile which is selected for c) For piling work in water, data on high flood levels,
2
IS 2911 (Part 2) : 2021
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
gravity.
suitable driving formula depending upon how the load
5.2.3 Single or Double Acting Hammer ― A hammer is transferred. If the load is transferred predominantly
operated by steam compressed air or internal by end bearing, either Engineering News Formula or
combustion, the energy of its blows being derived Hiley’s expression or any other suitable expression with
mainly from the source of motive power and not from suitable factor of safety may be used. The minimum
gravity alone. factor of safety shall, however, be 3. If the pile transfers
the load predominantly by friction, then a suitable
5.2.4 Hydraulic Hammer ― A hammer operated dynamic expression which accounts for parameters
by a hydraulic fluid can be used with advantage for relating to friction as well as end bearing may be used.
3
IS 2911 (Part 2) : 2021
6.5 Spacing of Piles 8.4 Both the ends shall be sawn at right angles to the
The minimum centre to centre spacing of pile is length of pile and the surface shall be made flush by
considered from three aspects, namely, trimming the knots and limbs.
a) practical aspects of installing the piles; 9 PRESERVATIVE TREATMENT
b) diameter of the pile; and
The timber shall be treated in accordance with IS 401,
c) nature of the load transfer to the soil and possible especially where conditions are not favourable.
reduction in the load capacity of piles group.
NOTE — In the case of piles of non-circular cross-section, 10 WORKING AND DRIVING STRESSES
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
diameter of the circumscribing circle shall be adopted.
The working stresses shall be as given in IS 883. These
6.5.1 In case of piles founded on hard stratum and may be exceeded by not more than 100 percent during
deriving their capacity predominantly from end bearing, driving.
the minimum spacing shall be 2.5 times the diameter
of the circumscribing circle corresponding to the 11 DESIGN OF PILE CAP (RCC)
cross-section of the pile shaft.
11.1 The method of analysis and allowable stresses
6.5.2 Piles deriving their load carrying capacity should be in accordance with IS 456.
predominantly from friction shall be spaced sufficiently
4
IS 2911 (Part 2) : 2021
13.2 The pile tip shall be pointed (unless the driving is eccentricity cannot be taken care of by a redesign of
wholly in soft strata) in the form of truncated cone or the pile cap or pile ties, the piles shall be replaced or
a pyramid having the end 25 cm2 to 40 cm2 in area and supplemented by additional piles.
the length shall be 1.5 to 2 times the diameter or side NOTE — In case of raker piles up to a rake of 1 in 6, there may
of square. be no reduction in the capacity of the pile.
13.2.1 If the driving is to be done through hard material 13.6 Sequence of Piling
as stiff clay, gravels, etc, metal shoes of approved
design shall be attached to the tip. 13.6.1 In a pile group, the sequence of installation of
piles shall normally be from the centre to the periphery
of the group or from one side to the other.
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
13.3 To prevent splitting and reduce brooming, the
head of the pile should be hooped with a suitable ring
13.6.2 Driving a Group of Friction Piles
or wrapped with wires.
Driving piles in loose sand tends to compact the sand,
13.3.1 The heads of the piles shall be further protected which in turn, increases the skin friction.
by the provision of cushion blocks.
In case where stiff clay or dense sand layers have to be
13.3.2 Use of followers shall be restricted to the extent penetrated, similar precautions as described in 13.2.1
of driving the pile up to the cut-off level only. Suitable need to be taken. This may be overcome by driving
connections shall be designed and provided to ensure the piles from the centre outwards or by beginning at
5
IS 2911 (Part 2) : 2021
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
15.2.2 Treated piles shall be handled with hemp or shall not be disturbed by boring holes or driving nails
manila rope slings or other means of support that will to support temporary material or staging.
not damage the surface of the wood.
6
IS 2911 (Part 2) : 2021
ANNEX A
( Clause 2 )
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
401 : 2001 Preservation of timber — Code of
practice (fourth revision) foundations — Code of practice
(Part 1/Sec 3) Concrete piles, Section 3
456 : 2000 Plain and reinforced concrete —
: 2010 Driven precast concrete piles
Code of practice (fourth revision)
(second revision)
707 : 2011 Timber technology and utilization (Part 4) : 2013 Load test on piles (second revision)
of wood, bamboo and cane —
Glossary of terms (third revision) 2974 (Part 1) : Code of practice for design
1982 and construction of machine
883 : 2016 Design of structural timber in foundations: Part 1 Foundation
7
IS 2911 (Part 2) : 2021
ANNEX B
( Foreword )
COMMITTEE COMPOSITION
Soil and Foundation Engineering Sectional Committee, CED 43
Organization Representative(s)
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
In Personal Capacity (Flat No. 202/395, Jodhpur Dr N. Som (Chairman)
Park, Kolkata 700068)
In Personal Capacity (D-1903, PWS, 7 Hills, Dr D. N. Naresh (Vice Chairman)
Narsingi(v), Kokapet Road, Ranga Reddy
500089)
AFCONS Infrastructure Limited, Mumbai Shri P. S. Bansod
Shri V. Ramamurty (Alternate)
8
IS 2911 (Part 2) : 2021
Organization Representative(s)
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
Shri Sujan Kulkarni (Alternate)
Geological Survey of India, Kolkata Dr Timir Baran Ghosal
Shri Prashant Tukaram Ilamkar (Alternate)
Ground Engineering Limited, New Delhi Shri Ashok Kumar Jain
Shri Neeraj Kumar Jain (Alternate)
Gujarat Engineering Research Institute, Vadodara Shri K. A. Keshvani
Shri R. S. Vasava (Alternate)
9
IS 2911 (Part 2) : 2021
Organization Representative(s)
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
National Institute of Disaster Management, Dr Chandan Ghosh
New Delhi Shri Amir Ali (Alternate)
NTPC Limited, Noida Shri Jitender Kumar
Shri Mohit Jhalani (Alternate)
Research Designs and Standards Organization Shri Sameer Singh
(Ministry of Railways), Lucknow Shri S. K. Ojha (Alternate)
RITES Limited, Gurugram Shri Alok Garg
Shri S. K. Kapoor (Alternate I)
Member Secretary
Shrimati Madhurima Madhav
Scientist ‘D’ (Civil Engineering), BIS
Panel for Review of IS 2911 (Part 1/Sec 1 to 4) and IS 2911 (Part 2), CED 43 : P3
Organization Representative(s)
10
(Continued from second cover)
Considering the limited use of timber piles due to reasons like non-availability of structural timber, the Committee
felt that the provisions regarding the timber piles be revised to restrict its use and to align its provisions regarding
determination of load carrying capacity and others with those in the revised standards for concrete piles, that is,
IS 2911 (Part 1/Sec 1 to 4) : 2010.
In the present revision of this standard (Part 2), the following major modifications have been made:
a) Definitions of various terms have been modified as per the prevailing engineering practices.
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
b) Scope of the standard has been restricted to allow use of timber piles for earth retaining structures,
shore protection, slope protection, compaction of ground, or to support structures up to two storeyed
structures.
c) Procedures for calculation of bearing capacity, structural capacity, factor of safety, lateral load
capacity, overloading, etc have also been modified to bring them at par with the present practices.
d) Design parameters with respect to adhesion factor, earth pressure coefficient, modulus of subgrade
reaction, etc have been revised to make them consistent with the outcome of modern research and
construction practices.
BIS is a statutory institution established under the Bureau of Indian Standards Act, 2016 to promote harmonious
development of the activities of standardization, marking and quality certification of goods and attending to
connected matters in the country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form without
the prior permission in writing of BIS. This does not preclude the free use, in the course of implementing the
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
standard, of necessary details, such as symbols and sizes, type or grade designations. Enquiries relating to
copyright be addressed to the Director (Publications), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
periodically; a standard along with amendments is reaffirmed when such review indicates that no changes are
needed; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standards
should ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of
‘BIS Catalogue’ and ‘Standards: Monthly Additions’.