Method Statement For Exterrnal Plastering
Method Statement For Exterrnal Plastering
Page1|5
INDEX
1. Purpose
2. Scope
3. Reference documents
4. Material
5. Procedure
6. Responsibility
7. Quality Control
8. Documentation
9. Safety
Page2|5
1.0 PURPOSE:
The purpose of this document is to describe the work procedure to be adopted for Transverse contraction
joint and longitudinal joints.
.
2.0 SCOPE:
The scope covers the work method for initial & final groove cutting, preparation of transverse &
contractual joint.
4.0 MATERIALS:
5.0 PROCEDURE:
Page3|5
Cutting and filling for longitudinal joints
o Joint cutting will commence at the earliest possible after paving. Joint cutting area to be marked to
initial cut.
o Initial cut shall be as per approved drawing with the help of diamond saw blade. This cut will be
washed out immediately.
o Widening of the joint to a width as per CRD, Contraction joint & for longitudinal joints shall be
taken up after 2 to 3 weeks by cutting for thickness specified in CRD operated by concrete sawing
machine. Widening joint shall be washed immediately after the cut. Joint shall be cleaned with
compressed air and shall be dried completely before priming & sealing.
o Polysulphite Sealant shall then be filled specified depth and finished by tooling specified shape as
per manufacturer’s specification.
6.0 RESPONSIBILITY
a) The Project Manager shall be responsible for all the activities of work execution.
b) The site engineer shall be the responsible to execute the work as per the approved method statement. Ensure
operatives are working in accordance with method statement.
c) The supervisor shall be responsible for managing site execution and control of labours, materials &
tools/tackles for the work.
d) The surveyor shall be responsible for the level, co-ordinate checking with respect to the drawing.
Work with site engineer to carry out the as- built survey/ top of concrete if any.
e) The QC engineer shall be responsible for ensuring the quality of work as per the Technical
specifications & Method statement. ITP implementation and ensuring the quality of work execution.
f) The safety officer shall be responsible to ensure the safety of workers during the progress of work.
Page4|5
9.0 DOCUMENTATION:
a) Architecture Drawing.
b) Site log/Register/Checklist
9.0 SAFETY:
a) All supervisory staff in general and Safety supervisor / steward in particular should be
continuously monitoring the activity during operations.
b) Safety supervisor / steward should ensure that Hazard Identification & Risk Analysis (HIRA) is
followed for this particular process.
c) Construction Engineer should ensure that all staff and workers on site are wearing PPE.
d) Construction Engineer / Safety steward should report any incident immediately to Safety Officer
/ Engineer.
Page5|5