GENERAL GUIDELINES

GENERAL GUIDELINES

1. Fill out the Submission Booklet

2. Collate the evidence required as per regulation.

3. Suggested formats / documentation as highlighted in this document

4. Put together the submission package in a structured manner as illustrated


STRUCTURING THE GREEN BUILDING SUBMISSION PACKAGE
A1
A2 B1
A

B
B14

E
Green Building
F

G
H1 1. Fee Receipt
2. Submission Booklet
H 3. Others
H4

Supporting Documents
A1 Integrated Design Approach for achieving energy savings

Minutes of Meeting – Date stamped Photo

Minutes of Meeting Copy


A2 Post Contract Green Briefing

Format ….Undertaking letter


B1 Compliance with Thermal Insulation system & Best Practices Energy Conservation

Extract from Specifications


B1 Compliance with Thermal Insulation system & Best Practices Energy Conservation

Building details
B1 Compliance with Thermal Insulation system & Best Practices Energy Conservation
Building details
B1 Compliance with Thermal Insulation system & Best Practices Energy Conservation
Envelope U (thermal) Calculations and Sections
EXTERNAL WALL SEC NO 1
LAYER THK. DENSITY R Mass
DESCRIPTIONS
NO in Ib/ft3 o
F ft2.h/Btu Ib/ft2
1.00 1.000 Out side surface resistance 0.000 0.250 0.000
2 IN RHP (Roof APPLY.) Rigid Polyurethane Insulation Panel with Steel & Alu.facing Sandwich Panel (RH-4''Box Rib) Registered
442.02 3.400 2.188 21.334 0.620
2007
26.00 0.500 Plaster (Cement / Sand) 116.250 0.100 4.844
2.00 1.000 Inside vertical surface resistance 0.000 0.680 0.000
1.000 0.000 0.000 0.000 0.000
0.00 1.000 0.000 0.000 0.000 0.000
0.00 1.000 0.000 0.000 0.000 0.000
0.00 1.000 0.000 0.000 0.000 0.000
0.00 1.000 0.000 0.000 0.000 0.000
0.00 1.000 0.000 0.000 0.000 0.000
0.00 1.000 #N/A #N/A 0.000 0.000
Sec.Thk 3.900 REV. 2 2007 15 2 2007
AS PER DM REGU. Outside color U (Btu / OF ft2 h) R Mass
0.100 D 0.045 22.364 5.464

ROOF NO 4
LAYER THK. DENSITY R Mass
DESCRIPTIONS
NO in Ib/ft3 o
F ft2.h/Btu Ib/ft2
1.00 1.000 1 IN Outside surface resistance 0.000 0.250 0.000
6.00 2.000 Terrazzo Tiles 160.000 0.160 26.667
12.00 0.500 .5 IN Plaster (Cement / Sand) 116.250 0.100 4.844
68.01 3.100 Rigid Polyfoam-50 ((Rcc Roof Slabs ) - Registered 2007 - Certified DCL 3.125 19.452 0.807
9.02 4.000 Light Weight Concrete (Light Weight Aggregate) 100.000 0.687 33.333
9.00 8.000 Reinforced Concrete 150.000 0.624 100.000
12.00 0.500 .5 IN Plaster (Cement / Sand) 116.250 0.100 4.844
3.00 1.000 1 IN Inside horizontal surface resistance 0.000 0.920 0.000
0.00 1.000 #N/A #N/A 0.000 0.000
0.00 1.000 #N/A #N/A 0.000 0.000
0.00 1.000 #N/A #N/A 0.000 0.000
Sec.Thk 18.100 REV. (1) 25 9 2007
AS PER DM REGU. Outside color U (Btu / OF ft2 h) R Mass
0.078 D 0.045 22.294 170.495
B1 Compliance with Thermal Insulation system & Best Practices Energy Consn

Envelope Sections - Wall


Envelope Sections - Roof
Glazing Details / Sections
HAP Input summary sheet
HAP Input summary sheet
HAP Input summary sheet
B2 Limiting / Reversing Thermal Bridges

Compliance Strategies

Thermal Bridging Concept Report


Thermal Bridging Strategy

All the Non-Repeating Thermal Bridges (i.e. junctions of floor and roof with the external wall, and details around
window and door openings) shall be reduced by designing all insulating building components to work in unison and
by creating barrier to heat flow in building envelope. The insulation shall be reviewed in relation to its location within
wall and roofs, its interface/connectivity with surrounding or penetration materials and connectivity within & between
insulating
components.
Following are the general strategies to be adopted at a minimum in order to achieve minimize thermal bridges:
- All the gaps between ceiling and walls shall be sealed with either plaster, adhesive or flexible sealant.
- All the gaps between walls and floor shall be sealed with either plaster, adhesive or flexible sealant.
- All the penetrations through air barrier shall be sealed by using a flexible sealant.
- All the penetrations around windows & door openings shall be sealed by using a flexible sealant.
- Partially filled insulation shall be secured firmly against inner leaf of wall.
- Provide full depth insulation between and over joists extending to inner edge of wall.
- Cavities shall be kept clean of mortar snots and other debris during construction.
- Provide a continuous air barrier of masonry inner leaf with wet-finish plaster alongside of internal wall, floor and
ceilings. Apply flexible sealant to all interfaces between internal air barriers and window/door frames.

Drawings for acceptable construction details shall be prepared by the contractor and approval has to be taken from
the consultant prior to proceed for the construction in relevance to the above
requirements.
B3 Envelope Tightness (Prescriptive Based)

Letter of Undertaking

Method Statement – From Qualified Thermographer

Extract from Specification


B4 Envelope Tightness (Performance Based)

THIS IS A VOLUNTARY CREDIT ……

Letter of Undertaking

Method Statement – From Qualified Thermographer

Extract from Specification


B5 Efficient sizing of HVAC system

Heat Load Calculations


B5 Efficient sizing of HVAC system
Heat load estimate should provide proof of the ENVELOPE U
values being used in the project.

Input sheet of the software can be submitted


B5 Efficient sizing of HVAC system

Schedule of Equipment
B6 Central Air-conditioning Units with Energy Recovery Units (ERV)

Ventilation / Exhaust Air Calculations

Air Balancing Calculations / Table


B6 Central Air-conditioning Units with Energy Recovery Units (ERV)

Energy Recovery Table with Efficiency details

HVAC Drawings indicating the units


B7 Selection of Air-conditioning Units with HIGH Energy Efficiency Ratio (EER)

Heat Load Summary with EER of the units for various areas 1 of 2
B7 Selection of Air-conditioning Units with HIGH Energy Efficiency Ratio (EER)

Heat Load Summary with EER of the units for various areas 2 of 2
B7 Selection of Air-conditioning Units with HIGH Energy Efficiency Ratio (EER)
B8 Energy Efficient Auxiliary Systems of HVAC – Blowers and Pumps

NOT APPLICABLE ……
B9 Interior Lighting Levels

LPD Calculation and Reduction Chart

Lighting Drawing along with Notes / Legend


B9 Interior Lighting Levels

LPD Calculation and Reduction Chart


B10 Exterior Lighting Levels

LPD Calculation and Reduction Chart

Lighting Drawing along with Notes / Legend


B10 Exterior Lighting Levels

LPD Calculation and Reduction Chart


LPD Calculation and Reduction Chart
LPD Calculation and Reduction Chart

Notes in Electrical Drawing


B11 Use of Renewable Sources of Energy for domestic heating

Extract from Specification


B11 Use of Renewable Sources of Energy for domestic heating

Hot Water Calculation


B11 Use of Renewable Sources of Energy for domestic heating

Hot Water Calculation / Notes in the drawing


B11 Use of Renewable Sources of Energy for domestic heating

Roof Top Water Supply Layout with Solar System Notes / Legend in the Drawing
B11 Use of Renewable Sources of Energy for domestic heating

Roof Top Water Supply Layout with Solar System Notes / Legend in the Drawing
B12 Use of Renewable Sources of Energy for Power

THIS IS A VOLUNTARY CREDIT ……

Solar PV system layout

Notes in the Electrical Drawing


B13 Energy Metering

Single Line Diagram


B13 Energy Metering

Metering Schedule

Extract of Specification
B14 COMMISSIONING

Commissioning Specifications (Extract)


B14 COMMISSIONING

Commissioning Specifications (Extract)


B14 COMMISSIONING

Commissioning Specifications (Extract)


B14 COMMISSIONING

Details of Training proposed


B15 BUILDING ENERGY SIMULATION REPORT [Conditioned areas > 2000 m2]

General
1. GB consultant to follow same requirements as LEED based regulation.
2. GB should be from Trakhees re qualified list.

A copy of the Energy Modeling Report

A copy of the Simulation output from software


B16 INDEPENDENT COMMISSIONING AGENT [Conditioned area >2000 m2]

General
1. Commissioning Specialist should follow same requirements as LEED based regulation.
2. Commissioning specialist should be from Trakhees re qualified list.
C. LIGHTING
C1 Use of Solar Day lighting technologies

Sky lighting
THIS IS A VOLUNTARY CREDIT ……

Relevant Extract / Section of Specification

Design Drawings showing Skyllights along with Clear LEGEND


C2 Use of Energy Saving High Performance Lamps

Villa Lighting Layout Drawings

Relevant Extract / Section of Specification


C2 Use of Energy Saving High Performance Lamps [OFFICE Portion]

Notes / Legend in the Electrical Drawing


C3 Use of Electronic Ballast

Relevant Extract / Section of Specification

Electrical Drawing
C3 Use of Electronic Ballast
Notes / Legend in the Electrical Drawing
D1 Use of Programmable thermostat for HVAC system

Relevant Extract / Section of Specification


D1 Use of Programmable thermostat for HVAC system

Programmable Thermostat with Timer


Drawing indicating Thermostat location T controls at a basic level
D1 Use of Programmable thermostat for HVAC system

Notes / Legend in the Electrical Drawing

Programmable Thermostat with Timer


T controls at a basic level
D2 Control of External Lights

Relevant Extract / Section of Specification


D2 Control of External Lights

Electrical Drawing Notes / Legend in the Electrical Drawing


D3 Interlock of Toilet / Bathroom Fans

Relevant Extract / Section of Specification


D3 Interlock of Toilet / Bathroom Fans

Electrical Drawing / Thermostat location Notes / Legend in the Electrical Drawing


D4 Use of Occupancy Sensor / Motion Sensor for internal lighting devices

Relevant Extract / Section of Specification


D4 Use of Occupancy Sensor / Motion Sensor for internal lighting devices
D4 Use of Occupancy Sensor / Motion Sensor for internal lighting devices

Extract from Specification – Motion Sensor


D4 Use of Occupancy Sensor / Motion Sensor for internal lighting devices

Electrical Drawing / Motion Sensor location

Notes / Legend in the Electrical Drawing


PART - 7

E. WATER
E1 Usage of STP for treating Grey Water & Reuse of treated water

THIS IS A VOLUNTARY CREDIT ……

Relevant Extract / Section of Specification

Drawings indicating the proposed STP


E2 Performance Requirements of Sanitary Fittings

Relevant Extract / Section of Specification Comprising the flow rates

Revision 00 July 2016 Page 73 of 102


E2 Performance Requirements of Sanitary Fittings

Notes from the Water Supply Layout Drawing


E3 Water Efficient landscaping & Irrigation Systems

Relevant Extract / Section of Specification


E3 Water Efficient landscaping & Irrigation Systems

Landscape layout / Setting out drawing


E3 Water Efficient landscaping & Irrigation Systems

Relevant Notes in the Drawing


E4 Water Efficient landscaping & Irrigation - Eliminate Potable Water

THIS IS A VOLUNTARY CREDIT ……

Relevant Extract / Section of Specification

Landscape layout / Setting out drawing


E4 Water Efficient landscaping & Irrigation - Eliminate Potable Water

THIS IS A VOLUNTARY CREDIT ……

Landscape layout / Setting out drawing

Drawings indicating the proposed STP


PART - 8

F. ENVIRONMENT & INDOOR AIR QUALITY


F1 Building Ventilation and Minimum Indoor Air Quality (IAQ)

Relevant Extract / Section of Specification


F1 Building Ventilation and Minimum Indoor Air Quality (IAQ)
Fresh Air Calculations (sample)
F1 Building Ventilation and Minimum Indoor Air Quality (IAQ)

Fresh Air Calculations (sample)


F1 Building Ventilation and Minimum Indoor Air Quality (IAQ)

Drawing / Layout showing FAHU


F1 Building Ventilation and Minimum Indoor Air Quality (IAQ)

Fresh Air Schematic


F2 Control of Environmental Tobacco Smoke

NOT APPLICABLE ……
F3 Low Emitting Paints, Coatings, Adhesives and Sealants

Relevant Extract / Section of Specification mentioning the requirements

Drawing indicating the requirements under GENERAL NOTES / GENERL REQUIREMENTS

Revision 00 July 2016 Page 87 of 102


F4 Use of Ozone Friendly materials in AC Eqpts,Thermal Insulation, Foam & FF Eqpts

Relevant Extract / Section of Specification mentioning the requirements

Relevant Notes in the Drawing


PART -9

G. SUSTAINABLE SITE AND MANAGEMENT


G1 Construction Activity Pollution Prevention (CAPP) / (ESC)

Draft template of Erosion & Sedimentation Control Plan


G1 Construction Activity Pollution Prevention (CAPP) / (ESC)

Relevant Extract / Section of Specification mentioning the requirements


G2 Heat Island Effect – Non Roof

Relevant Extract / Section of Specification mentioning the SRI requirements


G2 Heat Island Effect – Non Roof
Drawings Highlighting the requirement

Relevant Notes in the Drawing


G3 Heat Island Effect –Roof

Relevant Extract / Section of Specification mentioning the SRI requirements

Relevant Notes in the Drawing


Roof Plan
PART - 10

H. OPERATIONAL SUSTAINABILIY
H1 Recycling Facility – Storage & Collection of Recyclables

Relevant Extract / Section of Specification mentioning the SRI requirements

Drawing indicating the location of Bins


H2 Energy Efficient Equipments (White Goods)

Relevant Extract / Section of Specification


H2 Energy Efficient Equipments (White Goods)

Letter of Undertaking by the client (where relevant)


H3 Building User Guide

Extract of specification mentioning this requirement

Draft structure / format of the proposed building user guide


H3 Building User Guide

Draft structure / format of the proposed


building user guide
H4 Facility / Building Services Tuning

NOT APPLICABLE ……
END OF DOCUMENT