Project Management 1 Conformance To The Requirements
Project Management 1 Conformance To The Requirements
3. Grade of a product:
4. The interpretation of Quality can vary from person to person due to differences in:
a. Culture
b. Nationality
c. Economic background
d. All of the above
a. Legal liabilities
b. Planning
c. Quality audits
d. Field testing
6. The company has to repair or replace a product. This will be taken as a?
a. Recall cost
b. Warranty cost
c. Scrap and rework cost
d. Inspection and testing cost
a. Prevention cost
b. The cost of evaluating processes to ensure they are error free
c. Cost of appraising the project’s viability
d. Cost of appraising rework
12. The three key levels at which responsibility can be defined is at the _______ level, at the
_________ level and at the ____________ level.
13. The functional manager and project manager have equal power in which organizational
structure?
a. Weak matrix
b. Functional
c. Strong matrix
d. [D]Balanced matrix
14. Mark the option which does not form a component of a communication process model
a. Arguments
b. Understanding
c. Feedback
d. Body language
15. The ______ allows determination of the early start, early finish, late start and late finish.
a. Three-point estimates
b. Flow chart technique
c. Precedence diagramming method
d. Critical path method
Ans. 1 to 15
1. a
2. d
3. c
4. d
5. a
6. b
7. c
8. b
9. c
10. b
11. b
12. a
13. d
14. a
15. d
16. The three phases involved in the management of large projects are
a. is the latest time an activity can be started without delaying the entire project.
b. is a task or subproject that must be completed.
c. marks the start or completion of a task.
d. is the amount of time a task may be delayed without changing the overall project
completion time.
20. PERT analysis computes the variance of the total project completion time as
a. the sum of the variances of all activities not on the critical path.
b. the sum of the variances of all activities on the critical path.
c. the variance of the final activity of the project.
d. the sum of the variances of all activities in the project.
a. are used when two activities have identical starting and ending events.
a. 18 days
b. 60 days
c. 20 days
d. 19 days
26. An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic
time of 23 days. What is its variance?
a. 16.33
b. 4
c. 15.6
d. 2
27. Activities A and B are both 6 days long and the only immediate predecessors to activity C.
Activity A has ES=8 and LS=8 and activity B has ES=7 and LS=10. What is the ES of activity
C?
a. 16
b. 13
c. 14
d. 15
28. A project's critical path is composed of activities A, B, and C. Activity A has a standard
deviation of 2, activity B has a standard deviation of 1, and activity C has a standard deviation of
2. What is the standard deviation of the critical path?
a. 25
b. 5
c. 3
d. 9
29. What is the probability that a project with a mean completion time of 23.9 days and a
variance of 6 days will be finished in 26 days?
a. 0.80
b. 0.37
c. 0.20
d. 0.63
a. LF-Activity time.
d. ES + Activity time.
31. The ethical issue of divulging confidential information to some bidders to give them an
unfair advantage is known as
a. bid rigging.
b. bribery.
c. low balling.
d. expense account padding.
16 to 31
16. a
17. a
18. d
19. d
20. c
21. d
22. c
23. d
24. c
25. a
26. a
27. d
28. b
29. d
30. d
31. d
32. Which of the following is not a main element of the project management process?
a. Schedule.
b. Estimation.
c. Plan.
d. Monitor.
e. Systems design.
35. Which of the following is not a view of project assurance in a PRINCE2 project?
a. User.
b. Specialist.
c. Business.
d. Software.
e. All of the above.
36. Which of the following are claimed as advantages of the AON method over the AOA method
of network diagram notation?
38. Which of the following is not a reason to reduce project completion time?
39. Which of the following is the benefit of the network analysis approach?
Ans. 32 to 41
32. e
33. b
34. e
35. d
36. e
37. c
38. d
39. a
40. a
41. b
a. an optimistic time
b. a most probable time
c. a pessimistic time
d. all of the above
43 . three phases involved in the management of large projects are
a. Gantt chart
b. PERT
c. CPM
d. all of the above
48 . PERT analysis computes the variance of the total project completion time as
a. ensuring that all necessary activities are finished in the proper sequence and on
time
b. keeping the project within budget
c. making sure that the people assigned to the project receive the motivation,
direction, and information needed to do their jobs.
d. all of the above
a. activity-on-arc
b. activity-on-node
c. Gantt chart
d. all of the above
53 . Dummy activities
a. have no time
b. are inserted into networks to maintain the logic of the network
c. are used when two activities have identical starting and ending events.
d. all of the above
55 . An activities has a optimistic time of 4 days, a most likely time of 7 days, and a pessimistic
time 13 days. What is its expected time?
a. 4 days
b. 7 days
c. 7.5 days
d. 8 days
56. An activitiy has a optimistic time of 4 days, a most likely time of 7 days, and a pessimistic
time 13 days. What is its variance?
a. 1.5
b. 2.25
c. 7.5
d. 13.5
Ans. 42 to 56
42. d
43. d
44. d
45. c
46. a
47. d
48. b
49. d
50. d
51. d
52. b
53. d
54. c
55. c
56. b
57. Effective software project management focuses on four P's which are
58. Organizations that achieve high levels of maturity in people management have a higher
likelihood of implementing effective software engineering processes.
a. True
b. False
a. milestones
b. work products
c. QA points
d. All of the above
61. Project management is less important for modern software development since most projects
are successful and completed on time.
a. True
b. False
62. Which of the following is not generally considered a player in the software process?
a. customers
b. end-users
c. project managers
d. sales people
63. The best person to hire as a project team leader is the most competent software engineering
practitioner available.
a. True
b. False
64. The best project team organizational model to use when tackling extremely complex
problems is the
a. closed paradigm
b. open paradigm
c. random paradigm
d. synchronous paradigm
65. Which factors should be considered in choosing the organizational structure for a software
team? (Select all that apply)
66. One of the best ways to avoid frustration during the software development process is to
a. give team members more control over process and technical decisions.
b. give team members less control over process and technical decisions.
c. hide bad news from the project team members until things improve.
d. reward programmers based on their productivity.
a. True
b. False
68. Which of these software characteristics is not a factor contributing to project coordination
difficulties?
a. interoperability
b. performance
c. scale
d. uncertainty
69. Which of these software characteristics are used to determine the scope of a software project?
70. The major areas of problem decomposition during the project scoping activity are the
a. customer workflow
b. functionality to be delivered
c. process used to deliver functionality
d. software process model
e. both b and c
71. Product and process decomposition often occurs simultaneously as the project plan evolves.
a. True
b. False
72. When can selected common process framework activities be omitted during process
decomposition?
73. How does a software project manager need to act to minimize the risk of software failure?
75. Which of these are critical practices for performance-based project management?
Ans. 57 to 75
57. c
58. a
59. d
60. d
61. b
62. d
63. b
64. b
65. e
66. a
67. b
68. b
69. c
70. e
71. a
72. d
73. e
74. e
75. e