Schedule of Quantities of Road Work For M/S Ask Automobiles, Bhiwadi

This document provides a schedule of quantities and costs for road work for M/s Ask Automobiles in Bhiwadi, totaling ₹46,924,537. It includes 15 line items describing work like site clearance, excavation, earth filling, concrete work, reinforcement steel, kerb stone, paver blocks, brick work and more. The schedule contains details of the work description, unit, quantity, rate and amount for each item. The high level essential information is a cost estimate for road work for a company, breaking down costs by item and providing specifics of the road construction work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
398 views2 pages

Schedule of Quantities of Road Work For M/S Ask Automobiles, Bhiwadi

This document provides a schedule of quantities and costs for road work for M/s Ask Automobiles in Bhiwadi, totaling ₹46,924,537. It includes 15 line items describing work like site clearance, excavation, earth filling, concrete work, reinforcement steel, kerb stone, paver blocks, brick work and more. The schedule contains details of the work description, unit, quantity, rate and amount for each item. The high level essential information is a cost estimate for road work for a company, breaking down costs by item and providing specifics of the road construction work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SCHEDULE OF QUANTITIES OF ROAD WORK FOR M/s ASK AUTOMOBILES, BHIWADI

ROAD WORK
₹ 46,924,537.00
S.NO. DESCRIPTION UNIT QTY RATE AMOUNT
1 Site Clearance

Clearing jungle,garbage including uprooting of rank vegetation, grass, brush ,wood, trees
and saplings and removal of rubbish up to a distance outside the periphery of the area
cleared. Rate also also including disposal of malba, garbage by mechanical Transport to
the nearest dumping ground complete in all respect. Sqm RO 35

2 Excavation

Earth work in excavation from existing ground level for site levelling & development in all
kinds of soil including dressing of sides and ramming of bottoms, lift upto 1.5 m., stacking
the material temporarily near the excavated area and then disposal of surplus excavated
soil within the factory premises including spreading levelling and consolidated with 8-10
ton vibro rollar to achieve 95% proctor density ,dressing to camber as per direction of
Engineer-in-charge.
Cum 230 250.00 57,500.00

3 Earth Filling

Supply selected/ approved earth brought from outside the site and filling the same in
plinths, back of retaining walls, foundations and trenches and spreading in landscaping
and other location as directed by the Project Manager and shall be done in layers, not
exceeding 20cm in depth and consolidating each deposited layer by vibro roller of 8 to 10
tonne capacity, ramming and watering as under optimum moisture conditions to give at
least 95% of the maximum dry density (proctor density) including transportation, cost of
soil, royalty, loading, unloading, carriage to dumping spot and all incidentals at all depths
and levels, for all leads and lifts complete (Net consolidated area fill volume will be
computed from the initial and final levels. Volume in slopes, embankments etc. will be
computed applying appropriate formula,). ITEM INCLUDES EARTH COMPACTION TEST
COST SUPPORTED WITH INDEPENDENT LAB TEST REPORT

Cum 36750 280 10,290,000.00

4 Disposal of Material

Loading, disposal, unloading of malba/earth from the site premises by mechanical


Transport to the nearest dumping ground as approved by local authorities/ as per
direction of Engineer-in-charge. Cum R.O 550

5 Sub Grade Preparation

Preparation of sub grade by excavating earth to an average of 22.5 cms. depth, dressing
to camber and consolidating with 8- 10 MT road roller including making good the
undulations etc. and disposal of surplus earth with in the factory premises. (This item
shall not be payable wherever earth filling,cutting is done). Sqm R.O 45

6 Soling

Providing, laying, spreading and compacting hard core in two layers under floor / road
stone aggregate of specified sizes ( 63 to 95 mm size to be used in lower / base layer with
45 to 63 mm size stone to be used in upper / top layer along with up to 20 mm size stone
aggregate to be used as void filler ) including spreading in uniform thickness, screening,
hand picking, sorting and rolling with 3 wheeler power / vibratory roller of 8 to 10 tonne
capacity to achieve required compaction and brooming requisite type of screening / binding
material to fill up interstices of coarse aggregate watering and compacting to required
density.
Cum 4279 1600 6,846,400.00

7 Plain Cement Concrete (PCC)

Providing and laying in position cement concrete (without flyash) of specified grade
including the cost of centering and shuttering - All work up to plinth level :

7.1 P.C.C. 1:3:6 ( 1cement :3 coarse sand : 6 graded stone aggregate ) Cum 1345 4650 6,254,250.00

7.2 P.C.C. 1:4:8 ( 1cement :4 coarse sand : 8 graded stone aggregate ) Cum RO 4460

7.3 P.C.C. 1:5:10 ( 1cement :5 coarse sand : 10graded stone aggregate ) Cum R.O 4280

8 Concrete Work

Providing and laying of design mix good quality concrete of M-25 Grade with OPC of
43/53 grade mix included concrete placing , spreading, compaction, leveling, pumping, MS
channel side shuttering and curing etc. complete, as approved and as directed by the
Engineer in charge. cum 149 6320 941,680.00

1
S.NO. DESCRIPTION UNIT QTY RATE AMOUNT
9 Vacuum Dewatered Flooring (VDF)
Extra for vacuum dewatering the concrete floors using TREMIX or equivalent over above
item and finishing the top surface to required level/ slope and grade with rough / polish
finish using power trowels (both fan & disc) of standard make including curing etc.
complete as per specification and drawing. Sqm 382 170 64,940.00

10 Reinforcement Steel

Providing, laying and fixing in position steel reinforcement in all reinforced concrete work,
including straightening, cutting, removal of loose rust by wire brush and coating with
cement slurry, bending, hoisting, laying in position to the shape and profile required at all
levels and heights as per drawing and design and/ or as directed, binding with 18 gauge
MS annealed wire etc. complete.
Thermomechanically Treated Reinforcement (TMT and / or High yield strength Deformed
(Tor steel) bars of all grades. Kg 12446 12 149,352.00

11 Grooves Cutting

Extra for cutting grooves in road (Both longitudinal as well as transverse) including filling
with mastic sealing compound grade 'B' conforming to IS:1834 (Marking tape to be fixed on
either side of groove before filling the mastic compound to ensure a neat and clear finish).

(a) 5mm x 40mm Rmt R.O 205

12 Kerb Stone

Providing and laying at or near ground level factory made rubber mould finish kerb stone
of M-25 grade cement concrete in position to the required line, level and curvature, jointed
with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without
grooves (thickness of joints except at sharp curve shall not to more than 5mm), including
making drainage opening wherever required complete etc. as perdirection of Engineer-in-
charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb
stone shall be approved by Engineer-in-charge). (KK/NIMCO Make) size 150x600x450

Rmt 7950 575 4,571,250.00

13 Paver Block

13.1 Providing and laying 60mm thick factory made rubber mould finish cement concrete paver
block of M-30 grade of approved size, design & shape, laid in required colour and zig zag
pattern and including 50mm thick compacted bed of coarse sand, filling the joints with line
sand etc. all complete as per the direction of Engineer-in-charge. (KK/NIMCO Make)
Sqm 810.00 875 708,750.00

13.2
Providing and laying 80mm thick factory made rubber mould finish cement concrete paver
block of M-40 grade of approved size, design & shape, laid in required colour and zig zag
pattern and including 50mm thick compacted bed of coarse sand, filling the joints with line
sand etc. all complete as per the direction of Engineer-in-charge. (KK/NIMCO Make)
Sqm 17445 940 16,398,300.00

14 Saucer Drain

Providing and fixing precast 300mm wide 100mm thick Saucer Drain in slope with average
100 mm thick base pcc ( 1:3:6) made out of cement conc M-30 of required shape and
design including jointing ,fixing at position complete. (KK/NIMCO Make) Rmtr R.O 915

15 Brick Work

Providing and constructing brick masonry using selected quality burnt clay (non-modular)
bricks of class designation 75 in foundation and plinth laid in cement mortar 1:6 (1 cement :
6 coarse sand) mix, joints finished, flush/ raked to 6mm depth including scaffolding, curing
complete as per specification and drawing or as directed by Project Manager.
Cum 81 6350 514,350.00

16 Plaster

16.1 Providing and applying 15mm thick plaster to masonry ,RCC walls, columns etc. in cement
mortar 1:5 (1 cement : 5 fine and coarse sand in equal proportion) finished smooth
including hacking the surfaces, scaffolding, curing,chicken wiremesh, making grooves at
desired location etc. complete as per drawing.( Rate inclusive of adding waterproofing
compound as per manufacturer specifications)
Sqm 253 275 69,575.00

17 Painting
17.1 Providing & applying (two or more coats) with synthetic enamel paint of approved quality
and colour on new work over an under coat of primer and Base putty complete in all
respect. Sqm 253 230 58,190.00

TOTAL OF ROAD WORK AMOUNT ₹ 46,924,537.00