ISB - ITPM - Assignment - Critical Path

This document outlines the critical path method for the E-Governance Reporting System Project. It includes a table with 22 tasks that need to be completed for the project, listed in order with their predecessors, estimated duration in days, and identifiers. It also includes a diagram that visually maps out the dependencies and critical path between each of the 22 tasks to complete the project.

Uploaded by

fran7788
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
420 views2 pages

ISB - ITPM - Assignment - Critical Path

This document outlines the critical path method for the E-Governance Reporting System Project. It includes a table with 22 tasks that need to be completed for the project, listed in order with their predecessors, estimated duration in days, and identifiers. It also includes a diagram that visually maps out the dependencies and critical path between each of the 22 tasks to complete the project.

Uploaded by

fran7788
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

E-Governance Reporting System Project

Critical Path method

Data:

ID WBS Task Name Predec Estima


essors ted
Durati
on
(days)
1 1.1.1 Gather Data - 3

2 1.1.2 Study Feasibility - 4

3 1.1.3 Prepare Problem Definition 1,2 1


Report
4 1.2.1 Interview Users  3 5

5 1.2.2 Study existing System  3 8

6 1.2.3 Define User Requirements  4 5

7 1.2.4 Prepare System Analysis 5,6 1


Report 
8 1.3.1 Input and Output  7 8

9 1.3.2 Processing and Database  7 10

10 1.3.3 Evaluation  8,9 2

11 1.3.4 Prepare System Design Report  10 2

12 1.4.1 Software  11 15

13 1.4.2 Hardware  11 10

14 1.4.3 Network  11 6

15 1.4.4 Prepare System Development 12,13,14 2


Report
16 1.5.1 Software  15 6

17 1.5.2 Hardware  15 4

18 1.5.3 Network  15 4

19 1.5.4 Prepare testing Report  16,17,18

20 1.6.1 Training  19

21 1.6.2 System Conversion  19

22 1.6.3 Prepare Implementation 20,21


Report 
E-Governance Reporting System Project Critical Path method
1 2
3 4 ID Number
1.1.1 1.1.2 4 ES Duration EF
6
5
5 WBS
1.2.1
3 1.2.3
LS Float LF
1

1.1.3 5
8 7
1
1.2.2
1.2.4

8 9
8 10

1.3.1 1.3.2

10 11
2
2
1.3.3 1.3.4

12 13 14
15 10 6

1.4.1 1.4.2 1.4.3

15
2

1.4.4

17 18
16
4 4
6
1.5.2 1.5.3
1.5.1

19
1

1.5.4

21
20
2
4
1.6.2
1.6.1

22
1
1.6.3