Work Breakdown Schedule

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

5

TWO STOREY RESIDENTIAL

Pre-Construction Works Siteworks / Earthworks

1.0 Permits and Insurance 2.0 Mobilization 3.0 Layout and Staking
2.1 Construction of temporary
1.1 Pre-Survey of Property
facilities 3.1 Clearing and Grubbing
1.2 Acquiring of Construction
Permit and Insurance 2.2 Project Signages 3.2 Excavation

1.3 Conforming with Construction


Safety and Security 3.3 Gravel Bedding
2.3 Securing of Construction
Requirements
Equipment
3.4 Backfilling
3.5 Soil Positioning
3.6 Leveling and Compaction
3.7 Hauling and Disposal

TWO STOREY RESIDENTIAL


TWO STOREY RESIDENTIAL
Structural Works
Masonry Works
4.0 Formworks 5.0 Steel Works 6.0 Concreting
Days 4.1 Ground Floor (Sub-grade) Days 5.1 Ground Floor (Sub-grade) Days 6.1 Ground Floor (Sub-grade) 7.1 Exterior 8.1 Interor
4 4.1.1 Footing 8 5.1.1 Footing 6 6.1.1 Footing 7.1.1 Ground Level 8.1.1 Ground Level
4 4.1.2 Tie Beams 4 5.1.2 Tie Beams 6 6.1.2 Tie Beams 8 7.1.2 CHB Laying 8 8.1.2 CHB Laying
4 4.1.3 Columns 8 5.1.3 Columns 6 6.1.3 Columns 10 7.1.3 Plastering 10 8.1.3 Plastering
4 4.1.4 Septic Tank 4 5.1.4 Septic Tank 6 6.1.4 Septic Tank 7.2 First Floor 8.2.1 First Floor
4.2 First Floor 5.2 First Floor 6.2 First Floor 8 7.2.1 CHB Laying 8 8.2.2 CHB Laying
5 4.2.1 Beams 9 5.2.1 Beams 7 6.2.1 Beams 10 7.2.2 Plastering 10 8.2.3 Plastering
5 4.2.3 Floor Slab 10 5.2.3 Floor Slab 7 6.2.3 Floor Slab 7.3 Second Floor 8.3.1 Second Floor
5 4.2.4 Column 5 5.2.4 Column 7 6.2.4 Column 8 7.3.1 CHB Laying 8 8.3.2 CHB Laying
5 4.2.5 Suspended Beams 5 5.2.5 Suspended Beams 7 6.2.5 Suspended Beams 10 7.3.2 Plastering 10 8.3.3 Plastering
4 4.2.6 Stairs 3 5.2.6 Stairs 2 6.2.6 Stairs 7.4 Roof Deck 8.4 Roof Deck
4.3 Second Floor 5.3 Second Floor 6.3 Second Floor 7 7.4.1 CHB Laying 7 8.4.1 CHB Laying
5 4.3.1 Beams 5 5.3.1 Beams 6 6.3.1 Beams 8 7.4.2 Plastering 1 8.4.2 Plastering
5 4.3.2 Floor Slab 8 5.3.2 Floor Slab 6 6.3.2 Floor Slab
5 4.3.3 Column 8 5.3.3 Column 6 6.3.3 Column
5 4.3.4 Suspended Beam 10 5.3.4 Suspended Beam 6 6.3.4 Suspended Beam
4.4 Roof 5.4 Roof 6.4 Roof
4 4.4.1 Suspended Slab 7 5.4.1 Suspended Slab 5 6.4.1 Suspended Slab
4 4.4.2 Columns 9 5.4.2 Columns 5 6.4.2 Columns
4 4.4.3 Roof Beams 4 5.4.3 Roof Beams 5 6.4.3 Roof Beams

TWO STOREY RESIDENTIAL

9.0 MEPS

9.1 First Floor Days 9.2 Second Floor Days 9.3 Roof Deck Days 9.4 Installation and Finalization Days
9.1.1 Electrical Roughing-ins Slab 3 9.2.1 Electrical Roughing-ins Slab 3 9.3.1 Electrical Roughing-ins Slab 3 9.4.1 Electrical Roughing-ins Drop Ceiling 3
9.1.2 Electrical Roughing-ins Exterior Walls 3 9.2.2 Electrical Roughing-ins Exterior Walls 3 9.3.2 Electrical Roughing-ins Exterior Walls 3 9.4.2 Electrical Roughing-ins Main Panels 3
9.1.3 Electrical Roughing-ins Interior Walls 3 9.2.3 Electrical Roughing-ins Interior Walls 3 9.3.3 Electrical Roughing-ins Interior Walls 3 9.4.3 Wiring and Cables 3
9.1.4 Plumbing Roughing-ins Waterline and Sewer 9.2.4 Plumbing Roughing-ins Waterline and Sewer 9.3.4 Plumbing Roughing-ins Waterline and Sewer
9.4.4 Installation of Electrical Light Fixtures
Slab 3 Slab 3 Slab9 3 3
9.1.5 Plumbing Roughing-ins Waterline and Sewer 9.2.5 Plumbing Roughing-ins Waterline and Sewer 9.3.5 Plumbing Roughing-ins Waterline and Sewer
9.4.5 Installation of Electrical Devices and Panels
Exterior Walls 3 Exterior Walls 3 Exterior Walls 3 3
9.1.6 Plumbing Roughing-ins Waterline and Sewer 9.2.6 Plumbing Roughing-ins Waterline and Sewer 9.3.6 Plumbing Roughing-ins Waterline and Sewer 9.4.6 Finalization of Main Line Electrical
Interior Walls 3 Interior Walls 3 Interior Walls 3 Connection 3
9.4.7 Installation of Toilet and Bath Fixtures 3
9.4.8 Kitchen and Drainage Fixtures 3
9.4.9 Finaliation of Final Water Line 3
9.4.10 Testing and Commission 1

TWO STOREY RESIDENTIAL

10.0 Architectural

Days 10.1 First Floor Days 10.2 Second Floor Days 10.3 Roof Deck
3 10.1.1 Ceiling Works 3 10.2.1 Ceiling Works 3 10.3.1 Fabriciation of Roof Truss
4 10.1.2 Tile Works 4 10.2.2 Tile Works 4 10.3.2 Painting of Roof Truss
10.1.3 Installation of Window and 10.2.3 Installation of Window and 10.2.3 Installation of Roofing
3 Door 3 Door 3 Sheets and G.I Accessories
7 10.1.4 Painting Works 7 10.2.4 Painting Works
5 10.1.5 Landscaping 5 10.2.5 Landscaping

TWO STOREY RESIDENTIAL

Days 11.0 Special Works Days 12.0 Post-Construction Works Days 13.0 Turnover
11.1.1 Facade Development and
12.1.1 Demobilization 13.1 Cleaning
2 Miscellaneous Works 2 2
12.1.2 Removal of Construction
11.1.2 Cladding Works 13.2 Turnoever of Documents
2 2 Equipment 1
12.1.3 Removal of Temporary
11.1.3 Waterproofing
2 2 Facilities