Work Breakdown Schedule
Work Breakdown Schedule
Work Breakdown Schedule
1.0 Permits and Insurance 2.0 Mobilization 3.0 Layout and Staking
2.1 Construction of temporary
1.1 Pre-Survey of Property
facilities 3.1 Clearing and Grubbing
1.2 Acquiring of Construction
Permit and Insurance 2.2 Project Signages 3.2 Excavation
9.0 MEPS
9.1 First Floor Days 9.2 Second Floor Days 9.3 Roof Deck Days 9.4 Installation and Finalization Days
9.1.1 Electrical Roughing-ins Slab 3 9.2.1 Electrical Roughing-ins Slab 3 9.3.1 Electrical Roughing-ins Slab 3 9.4.1 Electrical Roughing-ins Drop Ceiling 3
9.1.2 Electrical Roughing-ins Exterior Walls 3 9.2.2 Electrical Roughing-ins Exterior Walls 3 9.3.2 Electrical Roughing-ins Exterior Walls 3 9.4.2 Electrical Roughing-ins Main Panels 3
9.1.3 Electrical Roughing-ins Interior Walls 3 9.2.3 Electrical Roughing-ins Interior Walls 3 9.3.3 Electrical Roughing-ins Interior Walls 3 9.4.3 Wiring and Cables 3
9.1.4 Plumbing Roughing-ins Waterline and Sewer 9.2.4 Plumbing Roughing-ins Waterline and Sewer 9.3.4 Plumbing Roughing-ins Waterline and Sewer
9.4.4 Installation of Electrical Light Fixtures
Slab 3 Slab 3 Slab9 3 3
9.1.5 Plumbing Roughing-ins Waterline and Sewer 9.2.5 Plumbing Roughing-ins Waterline and Sewer 9.3.5 Plumbing Roughing-ins Waterline and Sewer
9.4.5 Installation of Electrical Devices and Panels
Exterior Walls 3 Exterior Walls 3 Exterior Walls 3 3
9.1.6 Plumbing Roughing-ins Waterline and Sewer 9.2.6 Plumbing Roughing-ins Waterline and Sewer 9.3.6 Plumbing Roughing-ins Waterline and Sewer 9.4.6 Finalization of Main Line Electrical
Interior Walls 3 Interior Walls 3 Interior Walls 3 Connection 3
9.4.7 Installation of Toilet and Bath Fixtures 3
9.4.8 Kitchen and Drainage Fixtures 3
9.4.9 Finaliation of Final Water Line 3
9.4.10 Testing and Commission 1
10.0 Architectural
Days 10.1 First Floor Days 10.2 Second Floor Days 10.3 Roof Deck
3 10.1.1 Ceiling Works 3 10.2.1 Ceiling Works 3 10.3.1 Fabriciation of Roof Truss
4 10.1.2 Tile Works 4 10.2.2 Tile Works 4 10.3.2 Painting of Roof Truss
10.1.3 Installation of Window and 10.2.3 Installation of Window and 10.2.3 Installation of Roofing
3 Door 3 Door 3 Sheets and G.I Accessories
7 10.1.4 Painting Works 7 10.2.4 Painting Works
5 10.1.5 Landscaping 5 10.2.5 Landscaping
Days 11.0 Special Works Days 12.0 Post-Construction Works Days 13.0 Turnover
11.1.1 Facade Development and
12.1.1 Demobilization 13.1 Cleaning
2 Miscellaneous Works 2 2
12.1.2 Removal of Construction
11.1.2 Cladding Works 13.2 Turnoever of Documents
2 2 Equipment 1
12.1.3 Removal of Temporary
11.1.3 Waterproofing
2 2 Facilities