5 Mark Paper 3
5 Mark Paper 3
5 Mark Paper 3
S-1 List five energy saving measures for air conditioning system.
1
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
Insulate all cold lines / vessels using economic insulation thickness to minimize
heat gains.
Optimize air conditioning volumes by measures such as use of false ceiling and
segregation of critical areas for air conditioning by air curtains.
Minimize part load operations by matching loads and plant capacity on line;
adopt variable speed drives for varying load.
Ensure regular maintenance of all AC plant components as per manufacturers
guide lines.
Ensure adequate quantity of chilled water flows, cooling water flows
Avoid by pass flow by closing valves of ideal equipment
Adopt VAR system where economics permit as non CFC solutions
Make efforts to continuously optimize condenser and evaporator parameters for
minimizing specific energy consumption and maximizing capacity
S-2 The total system resistance of a piping loop is 50 meters and the static head is 15
meters at designed water flow. Calculate the system resistance offered at 75%, 50%
and 25% of water flow
2
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
Solution:
S-3
In a DG set, the generator is rated at 1000 kVA, 415V, 1390 A, 0.8 PF, 1500 RPM.
The full load specific energy consumption of this DG set as measured by the energy
auditor is 4.0 kWh per liter of fuel and air drawn by the DG set is 14 kg/kg of fuel. The
energy auditor has recommended a waste heat recovery (WHR) system. Also the
auditor indicated that the waste heat recovery potential is 2.6x105 kCal/hr at the
existing engine exhaust gas temperature of 583oC.
3
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
Solution:
S-4 The input power to a fan is 30kW for a 2500 Nm3/hr fluid flow. The fan pulley
diameter is 300mm. If the flow to be reduced by 15% by changing the fan pulley,
what should be the diameter of fan pulley and power input to fan.
Solution
S-5
Define Lux and Luminous efficacy
4
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
Ans
Lux (lx) is the illuminance produced by a luminous flux of one lumen,
uniformly distributed over a surface area of one square meter. It is also defined as
the International System unit of illumination, equal to one lumen per square meter.
….. (2.5 marks)
Luminous efficacy is defined as the ratio of luminous flux emitted by a lamp to
the power consumed by the lamp. Efficacy is energy efficiency of conversion from
electricity to light form.
….. (2.5 marks)
S-6 During an energy audit of a power plant cooling tower, the following observations
were made.
Ans
5
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
improved COC
8 Total water S.No 3 - S.No 6 (2333- 327.5 m3/hr 0.5 mark
saving per hour 2005.5)
9 Water S.No 8/785 (327.5/785) 0.417 m3/MW 1 mark
saving/MW
generation
Ans:
b) This expression also indicates that higher COPCarnot is achieved with higher
evaporator temperature and lower condenser temperature. But COPCarnot is only
a ratio of temperatures, and hence does not take into account the type of
compressor.
….. (2 marks)
where the cooling effect is the difference in enthalpy across the evaporator and
expressed as kW
….(1 mark)
S-8
The following single line diagram depicts the location of a 100 kW heater load and a
200 kW motor (which is 200 metres away from the 415V, LT bus). The main incoming
line power factor of the system is 0.85 lag. Calculate the rating of capacitors to
improve PF of main incoming line to 0.9 lag.
6
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
Ans:
Total Inductive load requiring PF compensation = 200kW (since the other 100 kW is
a resistive load)
….. (1 mark)
Operating PF cos ø1= 0.85 lag.
Desired PF cos ø2= 0.90 lag
-1 -1
kVAr required = kW((tan(cos ø )-tan(cos ø ))
1 2
….. (1 mark)
-1 -1
= 200(tan (cos 0.85)-tan (cos 0.90))
= 200( tan(31.78)-tan(25.84))
= 200(0.619-0.484)
= 200(0.135)
= 27 kVAr
….(3 marks)
S-1 a. The rated compressor capacity is 15 m3/min. Evaluate if there is any capacity
de-rating using the air-receiver tank filling method conducted at shop floor.
The relevant data is given below.
7
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
S-2 State three advantages of improvement of Power Factor at Load side. Power Factor
at the load side is 0.75 and average minimum load is 100 kW. What is the kVAr rating
of capacitor to improve the Power Factor at the load side to 0.95?
Capacitor required to improve Pf from 0.75 to 0.95 for an Average Load of 100 kW
= 100{tan (cos-1 0.75) - tan (cos-1 0.95)} = 100(0.882-0.329) = 55.3 kVAr, say 55 kVAr
Or
2 2 2 2
kVArOld = √(kVAold -kW ) =√(100/0.75) -100 = 87.67 kVAr
8
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
S-3 One unit of electricity in end-use application is equivalent to about two units of
electricity generated. Substantiate your answer with the computation of cascade
efficiency from generating plant ex-bus to end-use application.
Assume: Efficiency of Generator yard substation as 98%; transmission and
Distribution Loss = 20%; Efficiency of End-use application= 65%
S-5
List five energy saving measures in a commercial building.
Ans Optimize air conditioning volumes by measures such as use of false ceiling
and segregation of critical areas for air conditioning by providing partitions.
9
Bureau of Energy Efficiency
REGULAR Paper 3 – Set A
S-6 Explain how a Variable Frequency Drive saves power in a three phase electric
motor driven pumping system? What will be the reduction in power drawn by a
motor by reducing the speed by half?
Ans The VFD converts a basic fixed-frequency, fixed voltage sine-wave power (line
power) to a variable frequency, variable-voltage output used to control speed of
induction motors.
By controlling speed of a pump rather than controlling flow through use of throttling
valves, energy savings can be substantial.
By affinity law, if the speed of the pumping is reduced by 1/2, the power drawn by the
motor will be reduced by a factor of eight (1/2) 3 = 1/8.Using a fixed speed motor
would require some type of mechanical throttling device, such as a vane or damper;
but the fact remains that the motor would running full load and almost full speed (full
power), dropping the pressure across the flow control device.
S-7 A performance analysis of a DG set was carried out. The following are the data
obtained.
Period of trial – 2 hrs
Energy generated -1500 kWh
Level difference in diesel day tank – 51.6 cm
Diameter of day tank – 1m
Calorific value of fuel -10500 kcals/kg
The air drawn by the DG set is 30 kg/kg of fuel. The energy auditor recommended for
a waste heat recovery system. Also the auditor indicated waste heat recovery
potential is 2.6x105 kcal/hr if the flue gas temperature after waste heat recovery
system is maintained at 1800C.
a) Calculate the average efficiency of DG set and its specific fuel consumption
b) Calculate present flue gas exit temperature if specific gravity of fired fuel oil of
0.86 and specific heat of flue gas is 0.25 kcal/kg 0C.
Ans
1 Fuel consumption (litres) during 2 hrs of trail period 405
{(area x height diff) of day tank} ={3.14x(12)/4 x0.516x1000)lit
2 Specific gravity of fuel oil (given) 0.86
3 Oil consumption in (kg/hr) (405x 0.86 / 2) 174.18
kg/hr or
202.5
lit/hr
4 Specific fuel consumption (kWh/lit) ( Ans a) 3.7
kWh/lit
or 4.3
10
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
kWh/kg
5 Air supplied per kg of fuel (kg) (given) 30
6 Mass of flue gas (Sl.No.5)+1kg 31
7 Mass of flue gas kg per hour (Sl.No 6 x Sl.No 3) 5399.5
8 Waste heat recovery potential (kCal/hr) (given) 260000
9 Delta T across waste heat recovery system 192.61
(Heat kCal/hr)/(mass of flue gas/hr*specific heat)
10 Exit flue gas temp. after waste heat recovery system 180
(given)
11 Present Flue gas temp. or temp. before waste heat 372.6
recovery system (1800C+Delta T) ( Ans b)
12 Efficiency of DG set {750x860/(174.18x10500)} ( Ans a) =35.3
S-8 A 415 V, 15kW, 3-ph, 50Hz Induction motor operates at full load, with 88% efficiency
and 0.85 power factor lagging:
a) Find the current drawn by the motor
b) If this motor is replaced by 92.5% energy efficient motor with 0.92 power
factor, what will be the power savings in terms of k W and kVA?
Ans a). kWin (Input power) = 15 / 0.88 = 17.05 kW
Line current = 17.050 / (√3 x 0.415 x 0.85) = 27.91 Amp
kVAin = 17.05/0.85=20.06 kVA OR (√3 x 415X27.91)
11
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
S-1 Determine the discharge pipe inner diameter size (in mm) for compressed air system, having
following parameters.
P2 x V2 / T2 = P1 x V1 / T1
(1.013 + 7) x V2 / (273 + 35) = 1.013 x 1000 / 273
Optimize air conditioning volumes by measures such as use of false ceiling and
segregation of critical areas for air conditioning by air curtains.
Minimize the air conditioning loads by measures such as roof cooling, roof
painting, efficient lighting, pre-cooling of fresh air by air- to-air heat exchangers
etc.
Minimize part load operations by matching loads and plant capacity on line;
adopt variable speed drives for varying load.
12
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
………5 marks
(Each point carries one mark)
S-3 A stream of moist air with a mass flow rate of 10.1 kg/s and with a specific humidity of
0.01 kg per kg dry air, mixes with a second stream of superheated water vapor, flowing at
0.1 kg/s. If we assume proper and uniform mixing without condensation, then what will be
humidity ratio of the final stream, in kg per kg dry air?
Ans Humidity ratio of final stream,
Dry air (can also be calculated as) = [ 10.1 kg/s – (moisture i.e. 10.1 x 0.01)]
………………..5 marks
Or
Mass of moist air = 10.1 kg/s.
Specific humidity is = 0.01 kg/kg dry air
Amount of dry air in moist air can be found out as follows:
Let X be the amount of dry air, then by mass
balance X + X * (Specific humidity) = 10.1 kg/s
X + X * (0.01) = 10.1 kg/s
On solving, we get X=10 kg/s
Now, Moisture in moist air is 0.1 kg/s
Superheated steam = 0.1 kg/s
Humidity ratio of final steam =
M1H1 + M2H2 (0.01x10) + (0.1x1)
H =----------------------- = -------------------------------- = 0.02 kg per kg of
dry air Dry air (10)
………………..5 marks
13
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
S-5 The operating boiler load and associated Induced-draft fan power consumption of a
70% Position # 2 12 29
60% Position # 3 8 26
The fan consumes 35 kW at 100% boiler loading with damper in full open condition.
Estimate the daily energy savings that can be achieved if the damper is replaced by a
VFD for induced draft fan to meet the desired requirements.
14
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
a) Voltage levels can be varied without isolating the connected load to the
transformer using
Ans
a) On load tap changer (OLTC)
b) Soft starter
c) √3 (i.e.square root of three)
d) Cycles of Concentration (COC)
e) Lumens
………………..5 marks
(each one carries one mark)
S-7 A 75 kW, 415 V, 140 Amp, 4 pole, 50 Hz, 3-phase squirrel cage induction motor has
a full load efficiency of 87.6%. The measured operating motor terminal voltages in a
3-phase supply are 415 V, 418 V & 420 V. The current drawn in 3-phase supply are
15
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
137 Amp, 132 Amp & 137 Amp. Estimate the additional temperature rise of motor,
due to unbalanced voltage supply.
Deviation from
Phase V mean voltage
R 415 -2.67
Y 418 0.33
B 420 2.33
Mean 417.67 0
S-8
Briefly explain any three different methods of flow control for fans
When a fan flow change is required on a permanent basis, and the existing fan can
handle the change in capacity, the volume change can be achieved with a speed
change. The simplest way to change the speed permanently is with a pulley change.
For this, the fan must be driven by a motor through a v-belt system.
Damper Control:
Guide vanes are curved sections that lay against the inlet of the fan. Guide vanes
pre-swirl the air entering the fan housing. This changes the angle at which the air is
presented to the fan blades, which, in turn, changes the characteristics of the fan
curve. Guide vanes are energy efficient for modest flow reductions – from 100
percent flow to about 80 percent. Below 80 percent flow, energy efficiency drops
sharply.
Variable speed operation involves reducing the speed of the fan to meet reduced flow
16
Bureau of Energy Efficiency
Paper 3 – Set A with Solutions
requirements. Fan performance can be predicted at different speeds using the fan
laws. Since power input to the fan changes as the cube of the flow, this will usually
be the most efficient form of capacity control.
………………..5 marks
(Any of the above three to be considered)
17
Bureau of Energy Efficiency
Section – II: SHORT DESCRIPTIVE QUESTIONS Marks: 8 x 5 = 40
S-4 In a Thermal Power Station, the steam input to a turbine operating on a fully condensing mode
is 100 TPH. The heat rejection requirement of the steam turbine condenser is 555 kcal/kg of
steam condensed. The temperature of cooling water at the inlet and outlet of the turbine
condenser is 27 0C and 37 0C respectively. Find out the circulating cooling water flow.
= 5550 m3/hr
S-5 List any five benefits of power factor improvement in an industrial power distribution system
S-8 A medium sized engineering industry has installed two 480 CFM screw compressors,
A & B. Compressor-A is operating at full load and Compressor-B is running in load - unload
condition. The load power of both the compressor is 74 kW and the unload power of the
Compressor-B is 26 kW. Both the compressors are operated during working day.
The percentage loading of the Compressor-B during working day is 64 %. After arresting the
leakage in the system the loading of the compressor was found to be 35 %. Estimate the energy
savings per day.
Existing Case:
Ans Energy consumed per hour by Compressor -A= 74 kW
Energy consumed per hour by Compressor -B= 0.64 x 74 + 0.36 X 26 = 56.72 kW
Total energy consumed (Compressor A& B) = 74 + 56.72 = 130.72 kW/hr
Energy consumed per day= 130.72 X 24 hrs = 3137.3 kWh/day
Leakage Calculation:
Energy consumed per hour by Compressor -B= 0.64 x 74 + 0.36 X 26 = 56.72 kW
Energy consumed per hour by Compressor -B= 0.35 x 74 + 0.65 X 26 = 42.8 kW
Difference in power consumption = 56.72 - 42.8 = 13.92 kW/hr
Savings by arresting leakage per day= 13.92 X 24 = 334 kWh/day
20
Bureau of Energy Efficiency
Paper 3 Code : Pink
S-1 One of the Machining centres has installed 2 No’s of 270 cfm compressors for pneumatic operation and
also for cleaning operation of components after machining. The compressors are operated at 7 kg/cm2(g) and
are on-load for 80 % of the time. The load Power and the un-load Power of each 270 cfm compressor is, 40
kW and 15 kW respectively. The energy audit estimated that cleaning air requirement is 60% of the air
generated.
Calculate the daily energy consumption for cleaning air alone, assuming continuous operation of the
compressor.
Ans :
Average kW drawn by the compressors = [(80 x (0.8 x24))+ (30x (0.2 x 24))]/(24)
= 70 kW
Energy requirement for Cleaning air per day = (259 x 0.162 x 24)
= 1007 kWh/day
S-2 In a pharmaceutical industry a centrifugal pump is pumping 80 m3/hr of water into a pressurized
21
Bureau of Energy Efficiency
Paper 3 Code : Pink
container. The container pressure is 3 kg/cm 2(g). The discharge head of the pump is 5 kg/cm 2(g) and water
level is 5 meters below the pump central line. If the power drawn by the motor is 22 kW, find out the pump
efficiency. Assume motor efficiency as 90% and the water density as 1000 kg/m3.
S-2-
Ans:
Sol
Sl.
Parameter Process Value
No.
S3 A refrigeration system designed with 10 TR AHU is operating at 8.25 TR. The measured air
parameters are given below:
Cooling delivered (TR = (Difference in enthalpy) x (Volume of air / sp. volume x 3024)
= (Hi – Ho) x V / (v x 3024)
Volume of air handled by AHU = (TR x v x 3024 / (Hi – Ho))
= ((8.25 x 0.83 x 3024) / (10.26-7.26))
= 6903 m3/hr
S4 A fan is designed for 1300 m3/hr, 50 Hz and drawing 3 kW. If the fan is operated with VFD at 37 Hz for
6000 hours, calculate the velocity of air, when air is supplied through 150 mm diameter duct and the annual
energy savings.
Ans :
Power Drawn at 50 HZ = 3 kW
Operating frequency = 37 Hz
Flow at 37 Hz = 1300 x (37 / 50)
= 962 m3/hr
Diameter of the duct = 150 mm
Area of the duct = 0.0177 m2
22
Bureau of Energy Efficiency
Paper 3 Code : Pink
If the billing meter is monitoring demand every 15 minutes, calculate the maximum demand
registered and also the average PF, during the demand interval.
Ans :
Estimate the annual energy savings when compared to operation of fans continuously at a fixed speed of
1450 rpm.
Ans :
23
Bureau of Energy Efficiency
Paper 3 Code : Pink
3. Heat Pump
Ans :
1. Integrated Part Load Value (IPLV) for chillers (Page No. 126)
2. Evaporative Cooling (Page No. 136)
3. Heat Pump (Page No. 133)
S8 Write short notes on any two of the following: (Each 2.5 Marks)
24
Bureau of Energy Efficiency
Paper 3 Code : Pink
25
Bureau of Energy Efficiency