HW Engineering I Solution To The Workout Problems
HW Engineering I Solution To The Workout Problems
1. A road has a crest vertical curve with the following characteristics: G1 = +4.8%, VPC at
Station 4+010 with elevation 750 m, VPT at Station 4+330, G2 = -1.6%.
A. What is the elevation of the vertical curve at Station 4+110?
we need L = 4330-14010=320 m, sta. of BVC = 750 m, g1 = 4.8% = 0.048, and
Where:
• y = roadway elevation at distance x
• x = distance from beginning of vertical curve
• a = (g2 – g1)/2L and
• b = g1
• c = elevation of BVC
𝑔2 − 𝑔1 (−1.6 − 4.8)
𝑎= = = −0.0001
2𝐿 200 ∗ 320
𝑔1 = 4.8% = 0.048, 𝑐 = eleva. of BVC = 750
𝑨𝒙𝟐 𝟔.𝟒∗𝟏𝟕𝟎𝟐
𝒚= = =2.89
𝟐𝑳 𝟐𝟎𝟎∗𝟑𝟐𝟎
C. What is the station and elevation of the highest point on the curve?
𝐴 = −1.6 − 4.8 = −6.4
𝑔1 𝐿 𝑔1 𝐿 −4.8∗320
𝑥ℎ𝑙 = − 𝑔 =− = =284.4444
2 −𝑔1 𝐴 −5.4
𝑔2 − 𝑔1
𝑦ℎ = (𝑥ℎ )2 + 𝑔1 𝑥ℎ + 𝐸𝑙𝑣. 𝐵𝑉𝐶
2𝐿
(−1.6−4.8) 4.8
𝑦ℎ = (284.444)2 + 100 ∗ 284.44 + 750=755.563 m
200∗320
2. A horizontal curve is to be designed for a Federal highway in plain terrain with a design
speed of 80 km/h. The maximum superelevation is 0.07 and the lateral coefficient of
friction is 0.15. What is the ruling minimum radius of the curve?
Solution:
𝑉2
𝑅𝑚𝑖𝑛 =
127(𝑒 + 𝜇)
802
𝑅𝑚𝑖𝑛 = =11.087 %
127(0.07+0.15)
3. PVI station and location are 14+260 and 1200 m. What are the endpoints' stations
and elevations of a 280 m long curve with incoming and outgoing grades of -4.00%
and +2.00%?
Solution:
280
𝑠𝑡𝑎. 𝑜𝑓 𝐵𝑉𝐶 = (14 + 260) − = 14 + 120
2
280
𝑠𝑡𝑎. 𝑜𝑓 𝐸𝑉𝐶 = (14 + 260) + = 14 + 400
2
4 280
𝐸𝑙𝑒𝑣. 𝑜𝑓 𝐵𝑉𝐶 = 1200 + ( )∗ = 1205.6 𝑚
100 2
2 280
𝐸𝑙𝑒𝑣. 𝑜𝑓 𝐸𝑉𝐶 = 1200 + ( )∗ = 1202 𝑚
100 2
Solution:
3.6
m Robj (1 cos ) m 10 8.2
2 2
8.2
8.2 (500 1.8)(1 cos ) cos 1
2 2 500 1.8
10.41
2
L 2 Robj sin 2 * 498.2 sin(10.41)
2
L 180m
6. What is the superelevation to be provided for a horizontal curve with a radius of 300 m
for a design speed of 85 km/h if the lateral coefficient of friction is a.) 0.1? b.) 0.15? and
c.) 0.2?
𝑉2
𝑅𝑢𝑠𝑒𝑑 =
127(𝑒 + 𝜇)
𝑉2
𝑒= −𝜇
127𝑅𝑢𝑠𝑒𝑑
852
𝑒= −𝜇
127 ∗ 300
852
a. 𝑒 = 127∗300 − 0.1 =8.96%
852
b. 𝑒 = 127∗300 − 0.15 =3.96%
852
c. 𝑒 = 127∗300 − 0.2= -0.01037
It tells us it is not possible to get a 85 KPH on the road which has a 0.2 side friction,
so the design speed should reduce or the road suffice friction should be minimized.
7. What is the design speed for a horizontal curve of radius 250 m, is to be provided on a
state highway in plain terrain with a superelevation of 0.08 and lateral coefficient of friction
is 0.21? The speed should be rounded into nearest multiple of 5 units.
Solution:
𝑉2
𝑅 = 127(𝑒+𝜇) ,
𝑉 = √𝑅 ∗ (127(𝑒 + 𝜇))
V=95 Km/h
8. A -2.5% grade is connected to a +1.0% grade by means of a 180 m vertical curve. The
P.I. station is 10+000 and the P.I. elevation is 100.0 m above sea level. What are the
station and elevation of the lowest point on the vertical curve?
Solution
3.5
𝑔2 – 𝑔1 1 − −2.5 100
𝑎 = = =
𝐿 180 180
• Location of highest/lowest point on the curve, 𝑥ℎ/𝑙
𝑔1 𝐿 𝑔1 𝐿 2.5
𝑥ℎ/𝑙 = − 𝑔 = = 3.5 ∗ 180 = 128.57 𝑚,
2 −𝑔1 𝐴
3.5
2.5 −2.5 2.5∗180
𝑦ℎ/𝑙 = 100
∗ (3.5 ∗ 180)2 + ( 100 ) ∗ ( ) + 102.25=100.64 m
2∗180 3.5
9. What is the minimum radius of curvature allowable for a roadway with a 100 km/h design
speed, assuming that the maximum allowable superelevation rate is 0.10? Compare this
with the minimum curve radius recommended by ERA..
Solution:
10. A vertical crest ( summit curve is formed at the intersection of two grades + 3/100 and
-1/20. Design the length of the crest curve to provide a stopping sight distance for a
design speed of 80 km/h. Take any assumptions.
solution
𝑉2
𝑆𝑆𝐷 = 0.278𝑉𝑡 + 254𝑓
As there is ascending gradient on one side of the summit and descending gradient on
the other side, the effect of gradient on SDD is assumed to get compensated and
hence ignored in the calculation.
12. A horizontal curve on a 4-lane highway (two lanes each direction with no median) has a
superelevation of 6% and a central angle of 40 degrees. The PT of the curve is at station
10+080 and the PI is at 10+000. The road has 3-meter lanes and 2.4-meter shoulders on
both sides with high retaining walls going up immediately next to the shoulders. What is
the highest safe speed of this curve (highest in 5 km/h increments) and what is the station
of the PC?
Solution:
T = 10+000 – PC.
The length of the curve will be equal to the PT – PC so
L = 10+080 – PC.
With the equations for the tangent and length of curve both put in terms of the PC,
We know that also
𝜋𝑅∆ ∆
𝐿= and 𝑇 = 𝑅𝑡𝑎𝑛(2)
180
10,080 – 𝑃𝐶 10,000 – 𝑃𝐶
=
𝜋∆ ∆
𝑡𝑎𝑛 (2)
180
∆ 𝜋∆
𝑡𝑎𝑛 ( ) ∗ (10,080 – 𝑃𝐶) = ∗ (10,000 – 𝑃𝐶)
2 180
87.136
𝑅= = 239.4 m
40
𝑡𝑎𝑛 ( 2 )
Because the curve radius is usually taken to the centerline of the roadway and there are two 3 m
lanes before the centerline (working from the inside of the curve to the outside),
Rv =R –Lw-LW/2 = 239.4-3-3/2=234.9 m.
From Table 8-1 with a superelevation of 6%, at 80 km/h a radius of 270 m is needed; and at 70
km/h a radius of 195 m is needed. Therefore, the highest deign speed for centripetal force is 70
km/h (since 234.9 m > 195 m, the design is acceptable for 70 km/h because more than the needed
radius is available, but with 270 > 234.9 the design is not acceptable for 80 km/h since
insufficient radius is available).
To check for adequate sight distance, Ms is going to be the shoulder width plus half of the inside
lane width or 2.4+ 3/2 = 3.9 m . Consider the SSD required at 70 km/h. 70 km/h, by assuming
the road grade, g is 10% the required SSD is 140 m (from Table 7-2).
90𝑆𝑆𝐷
𝑀𝑠 = 𝑅𝑣 [1 − cos( )]
𝛱𝑅𝑣
90∗140
𝑀𝑠 = 234.9 [1 − cos( 𝛱∗234.9)]=10.35 m
Because 10.35 m is greater than the 3.9 of available Ms, 70 km/h is too fast. Consider a speed of
60 km/h, 50 km/h etc…
Because 2.99 m is less than 3.9 m, the highway is safe at 50 km/h. Considering both
the maximum safe speeds for centripetal force (70 km/h) and sight distance (50 km/h), the lower
of the two speeds will govern. Thus, 50 km/h (the highest safe speed for sight distance) is the
lower of the two speeds and is the highest safe speed for this curve.
In addition, let’s check for 55 km /h even it is not included in the table and by interpolation for
Ms from the above values (from 60 km/h and 50 km/h) the Ms for 55 km/ h is (0.5*(5.84+2.99)
=4.41 m which is greater than 3.9 m, so it fails.
13. An existing tunnel needs to be connected to a newly constructed bridge with sag and
crest vertical curves. The profile view of the tunnel and bridge is shown in Figure below.
Develop a vertical alignment to connect the tunnel and bridge by determining the highest
possible common design speed for the sag and crest (equal-tangent) vertical curves
needed. Compute the stationing and elevations of PVC, PVI, and PVT curve points.
Solution:
From left to right (see Figure above), a sag vertical curve (with subscript s) and a crest vertical
curve (with subscript c) are needed to connect the tunnel and bridge.
From the given information, it is known that G1s = 0% (the initial slope of the sag vertical curve)
and G2c = 0% (the final slope of the crest vertical curve).
To obtain the highest possible design speed, we want to use all of the horizontal distance
available.
This means we want to connect the curve so that the PVT of the sag curve (PVTs) will be the
PVC of the crest curve (PVCc).
If this is the case, G2s = G1c and since G1s = G2c = 0, As = Ac = A, the common algebraic
difference in the grades.
Solving for A gives, A = 6.667%. The problem now becomes one of finding K-values that allow
Ls + Lc = 366. Since L = KA , we can write
𝐾𝑠 𝐴 + 𝐾𝑐 𝐴 = 366
(𝐾𝑠 + 𝐾𝑐 )𝐴 = 366
366 366
𝐾𝑠 + 𝐾𝑐 = = 6.667 = 54.90 (m and Km/h)
𝐴
To find the highest possible design speed, Tables 3.2 and 3.3 are used to arrive at K-values to
solve Ks + Kc = 44.652.
From Tables 3.2 and 3.3, it is apparent that the highest possible design speed is 50 mi/h, at
which speed Kc = 84 and Ks = 96 (the summation of K’s is 180).
Since the station of the PVCs is 10 + 000 (given), it is clear that the PVIs = 10+097.6,
PVTs = PVCc = 10+195.2, PVIc = 10+280.60, and PVTc = 10+366.
For elevations,
PVCs = PVIs = 1530 m and PVIc = PVTc = 1542.2 m. Finally, the elevation of PVTs and
PVCc can be computed as
𝐴𝐿 195.2
1530 + 200𝑠 = 1530 + 6.66 ∗ =1536.507 m
200
14. A horizontal curve has a central angle of 45o and a Point of Intersection (PI) at Station 1+000.00
and radius of 1000.00 m. What is the station of the Point of Tangency (PT)?
Solution:
T R tan
2
45
T 1000 * tan 1000 * .41421 414.21
2
L *R* * 1000 * 45 785.398m
180 180
PI 1 000.00
414.21
PC 0 585.79
785.40
PT 1 371.19
15. The design speed of asphalt concrete paved highway designed for construction is 80kph with
e=8%& f=0.14 . During right-of-way reservation period it was found out that the space available
for horizontal curve is only adequate for provision of maximum 200m radius. Can this speed be
safely maintained on the road? If not, what should be done?
Solution:
16. A horizontal curve has a radius of 1000.00 ft. If the grade is flat and the distance between
the centerline and object is 30 ft, what is the maximum stopping distance (assume no
adjustment to center of the inside lane). Remember the arc length is proportional to the
circumference of a circle.
Solution:
30 R R cos
2
30 1000(1 cos )
2
.030 1 cos
2
cos 1 .030 .97
2
14.07
2
28.13
S
360 2R
2 *1000 * 28.13
S 491 ft
360
17. The stopping distance (rounded for design) of a two lane road (12 ft lanes) is 450 ft. What is the
required clear distance between the drivers location and the edge of the forest (level terrain
and no back slope) if the radius to the centerline is 1000 ft?
Solution:
18. A highway reconstruction project is being undertaken to reduce accident rates on the
highway. The reconstruction involves a major re-alignment of the highway such that a
100kph design speed is attained. At one point on the highway, a 240m equal tangent
crest vertical curve exists. Measurements show that, at 106m from the PVC, the
vertical curve offset is 0.9m. Assess the adequacy of the existing curve in light of the
reconstruction designs peed of 100kph and, if the existing curve is inadequate,
compute a satisfactory curve length.
Solution:
Use K=52 from the table and take a correction on the Ans.
19. A horizontal curve is being designed through mountainous terrain for a 4-lane road with
3m lanes. The central angle is known to be 40 degrees, the tangent distance is 153m,
and the tangent intersection PI is located at chainage 5+650m. If the roadway has a
coefficient of side friction of 0.082 and a superelevation rate of 0.09m/m, determine
whether this is appropriate for a design speed of 80kph. If not, re-design the curve and
indicate the location of the PC and PT.
Solution: