Tutorial 04 - Project Scheduling
Tutorial 04 - Project Scheduling
Tutorial 04 Questions
2. You have a partial network for your project, and you are about to conduct a forward pass through
it. Explain why the early start (ES) for activity G is 23 days, not 19 days. Remember, activity
G is a merge activity.
3. Referring to the figure above in question 2, suppose that Activity G was the last activity in the
network and you were about the start a backward pass.
a. What is the project’s duration? (Hint: complete the forward pass)
b. What are the late finish (LF) and late start (LS) values for Activities E, F, and G?
c. Which activity has slack time? How many days?
4. Referring to the figure shown below, suppose that Activity O was the last activity in the network
and you were about to start a backward pass.
a. What is the project’s duration? (Hint: complete the forward pass)
b. What are the late finish (LF) and late start (LS) values for activities L, M, N, and O?
c. Which activities have slack time? How many days?
The University of the South Pacific IS333 Tutorial 03 Questions and Possible Solutions Page 1 of 3
IS333: Project Management Tutorial 04 Questions and Answers
5. Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You
have been selected to serve as the event project manager and have created a Work Breakdown
Structure and duration estimates for the activities involved in site preparation for the event.
Construct a network activity diagram based on the following information:
a. Conduct both a forward and backward pass using AON notation. What is the estimated
total duration for the project?
b. Identify all paths through the network. Which is the critical path?
c. Which activities have slack time?
d. Identify all burst activities and merge activities.
6. Explain the concept of a “dummy variable.” Why is this concept employed in AOA notation?
Why is there no need to use dummy variables in an AON network?
7. Using the following information about Project A, its activities and predecessor activities below:
Activity Predecessors
A -
B A
C B
D B
E C, D
F C
G E, F
H D, G
a. Create the Activity Network Diagram using the (AoN) technique. (Question repeated
from Tutorial 3, remove any redundant member)
9. Develop a Gantt chart with the following information. What is the expected duration of the
project? What is the critical path?
10. Consider a project with the following information. Construct the project activity network using
AOA methodology and label each node and arrow appropriately. Identify all dummy activities
required to complete the network.
The University of the South Pacific IS333 Tutorial 03 Questions and Possible Solutions Page 3 of 3