Checklist For Technical Evaluation (Contract Review) of Infrastructure Contracts
Checklist For Technical Evaluation (Contract Review) of Infrastructure Contracts
SCOPE OF TECHNICAL EVALUATION: Determination of the reasonableness of the contract cost and
duration. Technical Aspect of contracts for infrastructure projects which shall include, but not limited to,
construction, improvement/rehabilitation/repair, demolition, restoration and/or maintenance of: roads,
bridges, railways, airports, seaports, communication facilities, civil works components of information
technology projects, irrigation, flood control and drainage, water supply, sanitation, sewerage and solid
waste management systems, shore protection, energy/power/electrification facilities, national school
buildings including schools and hospitals, and other related construction projects of the government.
1 Copy of the approved contract
Special Condition of Contract
General Condition of contract
2 Notice to Proceed
3 Program of work and Detailed Estimates
Copy of the document containing the Detailed Breakdown of the Approved Budget for the
4 Contract (ABC) including the detailed breakdown of estimates and/or unit cost
analysis/derivation for each work item expressed in volume / area / lump sum/ lot.
5
Copy of the complete set of duly approved plans/drawings, showing all details and
dimensions,, including the following:
Plan drawn to scale and legible
profile sheet (showing horizontal and vertical alignment of the road), typical section and
details : broken down,as:
For Horizontal Construction (roads, canals, footbridges, slope protection and related structures)
Location Plan/Site Development Plan
Profile sheet of the road (showing horizontal and vertical alignment of the road)
Typical sections and details of roadway
Cross-section of the roadway (by 20m or 50m distances up to the end of the project)
straight line diagram showing the location/ stationing of the items of work.
Slope Protection - details - (thickness, height, length, location)
Structural plans of footbridges, showing details and sections
drainage details where applicable
structural plans at appropriate scale indicating all details necessary in order that the
complete structure can be set out and constructed
other necessary details
For vertical construction (bldg)
Location Plan/Site Development Plan
structural plans at appropriate scale indicating all details necessary in order that the
complete structure can be set out and constructed
Electrical Plans
Plumbing and Sanitary Layout with details
Doors and windows details
Septic Vault Details
other necessary details
For water supply system
Location Plan/Site Development Plan
Profile sheet
structural plans for reservoir, intake tanks, etc., at appropriate scale indicating all details
necessary in order that the complete structure can be set out and constructed
water system layout / pipe lines layout with details
Details of Pipe Laying
other necessary details
6 Copy of complete Technical specifications, including the following:
Items not included in DPWH Specification should have an approved construction
procedures and technical specification.
Disposal location of unsuitable / excavated materials
Classification of materials in Removal of Structures
Kinds of paint materials for every surfaces
Copy of the document containing the Detailed Breakdown of the Contract Cost including the
7 detailed breakdown of estimates and/or unit cost analysis/derivation for each work item
expressed in volume / area / lump sum/ lot.
Quantity sheet - mathematical computations on how each quantity under every item of work
8 were derived at. Derivation of area (length x width x thickness; end area method; of the items
of work: Removal of Structures, Structure Excavation, Structural Concrete, Reinforcing Steel
Bars, Hand Laid Rock Embankment, Embankment, PCCP, etc)
Example:
Structural Concrete volume derivation: length x width x thickness of = foundation, column,
slab on fill, concrete slab, beams, girders, canopy
Reinforcing Steel = number of pieces per structure (foundation, column, slab, beam,
girder, etc) x unit weight per sizes of reinforcing bars
Structural Steel = number of pieces per structure (roofing system, etc) x unit weight per
sizes of structural steel
Embankment, grouted riprap, hand laid rock embankment, etc by End Area Method
Paint = Surface area - concrete, masonry x production rate of paint (gallons / cans)
Paint = Surface area - wood, lumber x production rate of paint (gallons / cans)
Paint = Surface area - metal x production rate of paint (gallons / cans)
Masonry : Area of walls, fences,septic tank
Aggregate Sub Base & Base Course =( Area of shoulders + Area below pavement)x
length
Copy of the Approved PERT/CPM Network Diagram by Head of Office and detailed
9 computations of contract time: Annex "A" 3.j: actual working days; holidays/weekends;
unworkable/rainy days
10 Dated Pictures taken of site "before" construction of items of work:
canals
riprap
clearing and grubbing
roadways and drainage excavation
location of building
For Demolition of old building/ structures
Certification from concerned government officials who prepared and approved the detailed
engineering that the detailed engineering surveys and designs have been conducted
11
according to the prescribed agency standards and specifications in conformance with the
provisions of this Annex, and that the detailed engineering outputs are adequate for the
procurement at hand. (Annex "A" 4.)
12 Site Inspection
13 Hauling Computatation / Analysis, when applicable
PREPARED BY:
PREPARED BY: