Or Notes (Unit-V)
Or Notes (Unit-V)
Assumption
Generally, the criteria for measuring efficiency is the discounted value of all future costs
associated with each policy.
Let
C = the capital cost of a certain item, say a machine
S(t) = the selling or scrap value of the item after t years.
F(t) = operating cost of the item at time t
n = optimal replacement period of the time
Now, the annual cost of the machine at time t is given by C – S(t) + F(t) and since the total
maintenance cost incurred on the machine during n years is F(t) dt, the total cost T, incurred
on the machine during n years is given by:
T = C – S(t) + F(t) dt
Thus, the average annual total cost incurred on the machine per year during n years is given by
1
TA = —– C – S(t) + F(t) dt
n
To determine the optimal period for replacing the machine, the above function is differentiated
with respect to n and equated to zero.
dTA -1 -1 F(n)
—— = —– C – S(t) —– F(t) dt + ——
dn n2 n2 n
dTA
Equating —— = 0, we get
dn
1
F(n) = —– C – S(t) + F(t) dt
n
Example
The initial cost of a machine is Rs. 7100 and scrap value is Rs. 100. The maintenance costs
found from experience are as follows:
Year 1 2 3 4 5 6 7 8
Solution.
Differen
ce Averag
Cumulati Scra Average
Runnin between e Average
Yea ve p investme
g initial runnin annual
r running valu nt cost /
cost cost and g cost / total cost
cost e year
scrap year
value
G= H=F
A B C D E F = E/A
C/A +G
200 + 350
2 350 100 7000 3500 225 3775
= 550
1750 +
5 1000 1000 = 100 7000 1400 550 1950
2750
2750 +
1841.6
6 1300 1300 = 100 7000 1166.67 675
7
4050
4050 +
1821.4
7 1700 1700 = 100 7000 1000 821.42
2
5750
5750 +
1856.2
8 2100 2100 = 100 7000 875 981.25
5
7850
This table shows that the average annual total cost during the seventh year is minimum. Hence,
the machine should be replaced after the 7th year.
The failure of the item may result in complete breakdown of the system. The breakdown
implies loss of production, idle inventory, idle labour, etc. Therefore, an organization must
prepare itself against these failures.
In situations where the items fail completely, the formulation of replacement policy depends
upon the probability of failure. Mortality tables or Life testing techniques may be used to obtain
a probability distribution of the failure of items in a system.
Mortality Tables
M(t – 1) – M(t)
—————-
N
The conditional probability that any item survived upto age (t – 1) and will fail in the next
period is given by
M(t – 1) – M(t)
—————-
M(t – 1)
Example 1
Following mortality rates have been observed for certain type of light bulbs.
Time (weeks) 0 1 2 3 4 5 6 7 8 9 10
Solution.
Here, t is the time (weeks) and M (t) is the number of bulbs still operating. The probability of
failure can be calculated as shown in the following table.
Table
Probability of failure
Time
M (t) pi = [ M (t – 1)- M (t) ] /
(t)
N
0 100 —-
9 3 (7 – 3)/100 = 0.04
10 0 (3 – 0)/100 = 0.03
Example 2
Following mortality rates have been observed for a certain type of electronic component.
Month 0 1 2 3 4 5 6
% surviving at the end of the month 100 97 90 70 30 15 0
There are 10000 items in operation. It costs Re 1 to replace an individual item and 35 paise per
item, if all items are replaced simultaneously. It is decided to replace all items at fixed intervals
& to continue replacing individual items as and when they fail. At what intervals should all
items be replaced? Assume that the items failing during a month are replaced at the end of the
month.
Solution.
Probability of
% surviving at the end of the
Month failure
month
pi
0 100 —-
1. Individual replacement.
2. Group replacement.
Case I
It should be noted that no item survives for more than 6 months. Thus, an item which has
survived for 5 months is sure to fail during sixth month.
The expected life of each item is given by
Case II
Let Ni denote the number of items replaced at the end of ith month.
of items replaced in first month X probability that these items will fail during second month)
=N0P2 + N1P1
=(10000 X 0.07) + (300 X 0.03) = 709
N3 = N 0P 3 + N1P2 + N2P1
= (10000 X 0.20) + (300 X 0.07)+ (709 X 0.03) = 2042
From the above calculations, it is observed that Ni increases upto fourth month and then
decreases. It can also be seen that Ni will later tend to increase and the value of Ni will oscillate
till the system acquires a steady state.
The optimum replacement cycle under group replacement is given in the following table.
The above table shows that the average cost during the third month is minimum. Thus, it would
be economical to replace all the items every three months.
Meaning of Networking
This technique provides an effective management, determines the project duration more
accurately, identifies the activities which are critical at different stages of project completion
to enable to pay more attention on these activities, analyse the scheduling at regular interval
for taking corrective action well in advance, facilitates in optimistic resources utilisation, helps
management for taking timely and better decisions for effective monitoring and control during
execution of the project.
Objectives of Network Analysis:
Network analysis entails a group of techniques for presenting information relating to time and
resources so as to assist in the planning, scheduling, and controlling of projects. The infor-
mation, usually represented by a network, includes the sequences, interdependencies, interre-
lationships, and criticality of various activities of the project.
(i) Planning,
(i) Network technique is simply a tool to help the management; hence its effectiveness depends
on how well it is used by the management.
(ii) Its accuracy depends on the estimation of the data used in the network.
(iii) It is useful only if it is updated regularly and decisions for corrective actions are taken
timely.
The method was developed by the US Navy in 1957 on the Polaris nuclear submarine
project.
To conduct PERT Analysis, three time estimates are obtained (optimistic, pessimistic, and
most likely) for every activity along the Critical Path. Then use those estimates in the
formula below to calculate how much time for each project stage:
Formula: (P+4M+O)/6
• Optimistic Time (O):the minimum possible time required to accomplish a task, assuming
everything proceeds better than is normally expected.
• Pessimistic Time (P):the maximum possible time required to accomplish a task,
assuming everything goes wrong (excluding major catastrophes).
• Most likely Time (M): the best estimate of the time required to accomplish a task,
assuming everything proceeds as normal.
The Critical Path is the longest path of scheduled activities that must be met in order to
execute a project. This is important for Program Managers (PM) to know since any
problems that occur on the critical path can prevent a project from moving forward and be
delayed. Earned Value Management (EVM) analysis focuses on the critical path and near
critical paths to identify cost and schedule risks. Other schedule paths might have slack
time in them to avoid delaying the entire project unlike the critical path. There might be
multiple critical paths on a project.
The Critical Path is determined when analyze a projects schedule or network logic diagram
and uses the Critical Path Method (CPM). The CPM provides a graphical view of the
project, predicts the time required for the project, and shows which activities are critical to
maintain the schedule.
1. List of all activities required to complete the project (see Work Breakdown Structure
(WBS)),
2. Determine the sequence of activities
3. Draw a network diagram
4. Determine the time that each activity will take to completion
5. Determine the dependencies between the activities
6. Determine the critical path
7. Update the network diagram as the project progresses
The CPM calculates the longest path of planned activities to the end of the project, and
the earliest and latest that each activity can start and finish without making the project
longer. This process determines which activities are “critical” (i.e., on the longest path)
and which have “total float” (i.e., can be delayed without making the project longer). [1]
The CPM is a project modeling technique developed in the late 1950s by Morgan R.
Walker of DuPont and James E. Kelley, Jr. of Remington Rand.
REPORT THIS AD
Resource Planning
Resource planning refers to the strategy for planned and judicious utilisation of resources.
Resource planning is essential for sustainable existence of all forms of life.
Resource planning is essential for India as there is enormous diversity in the availability of
resources. For example the state of Rajasthan has vast potential for the development of solar
and wind energy but is deficient in water resources.
The cold desert of Ladakh has rich cultural heritage but is deficient in water and some strategic
minerals.
The state of Arunachal Pradesh has abundance of water resources but lacks infrastructure which
shows mere availability of resources in the absence of technology and institutions hinders
development.
This shows that the resource planning is needed at the national, regional, state and local levels
for balanced development of a country.
Meaning of Crashing
Crashing is a schedule compression technique used to reduce or shorten the project schedule.
The PM can various measures to accomplish this goal. Some of the common methods used are
After applying the crashing, the critical path might have changed and result in creating a
different critical path. Always revisit the project schedule to ensure the schedule has been
crashed.
Other Definitions
1. Crashing is the technique to use when fast tracking has not saved enough time on the schedule.
It is a technique in which resources are added to the project for the least cost possible. Cost and
schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression
for the least incremental cost.
2. Crashing refers to a particular variety of project schedule compression which is performed for
the purposes of decreasing total period of time (also known as the total project schedule
duration). The diminishing of the project duration typically take place after a careful and
thorough analysis of all possible project duration minimization alternatives in which any and
all methods to attain the maximum schedule duration for the least additional cost.
3. When we say that an activity will take a certain number of days or weeks, what we really mean
is this activity normally takes this many Project Management Triangle days or weeks. We could
make it take less time, but to do so would cost more money. Spending more money to get
something done more quickly is called “crashing”. There are various methods of project
schedule crashing, and the decision to crash should only take place after you’ve carefully
analyzed all of the possible alternatives.The key is to attain maximum decrease in schedule
time with minimum cost.
4. Crashing the schedule means to throw additional resources to the critical path without
necessarily getting the highest level of efficiency.
5. Crashing is another schedule compression technique where you add extra resources to the
project to compress the schedule. In crashing, you review the critical path and see which
activities can be completed by adding extra resources. You try to find the activities that can be
reduced the most by adding the least amount of cost. Once you find those activities, you will
apply the crashing technique.