Alaoji Pre-Comm & Comm Procedure
Alaoji Pre-Comm & Comm Procedure
DOCUMENT TITLE:
PRE-COMMISSIONING AND COMMISSIONING
PROCEDURE
CONTRACTOR:
MORPOL ENGINEERING SERVICES LIMITED
For: MORPOL ENGINEERING SERVICE LIMITED For: NIGERIAN GAS COMPANY. (NGC )
1
TABLE OF CONTENTS
1.2 RECORDS....................................................................................................................................................
1.5 BACKGROUND...........................................................................................................................................
2.0 PRECOMMISSIONING........................................................................................................................
3.0 COMMISSIONING............................................................................................................................
2
3.1.1 PRESSURE TESTING...............................................................................................................................
3
1.1 GENERAL REQUIREMENTS
Upon completion of the installation and fabrication works, instruments, wiring systems and
equipment shall be checked and tested. It is intended to ensure that all components of the
instruments and equipment satisfactorily perform their intended function and conform to standards.
1.2 RECORDS
1.2.1 Contractor shall maintain and make available to Client, as may be requested, suitable records
indicating the performance and results of instrument Check-Out.
1.2.2 As-built drawings incorporating field revisions in piping and wiring shall be issued by Contractor at
the conclusion of the job.
1.3.1 Client has supplied the instruments specified; and that the instruments have been properly
installed.
1.3.2 Verification will be made to ensure that all instruments associated with the project are properly
tagged.
1.3.3 After loop check is completed, all junction boxes and panels through which loop wiring passes, will
be Locked.
1.3.4 A copy of the loop diagrams will be provided as a formal record of each loop test performed and
shall be witnessed and signed by the client.
The purpose of the commissioning is to introduce product into the plant. At this stage all the Pre-
Commissioning activities have been completed. And all the loops and electrical equipment
4
described in the Pre-commissioning specification shall be completed and signed. The following
systems must be operational:
1.4.1 The electrical power must be fully operational. Instruments, controls, and electrical equipment shall
have the appropriate voltage to operate safely.
1.4. 2 All the pipes, tubing’s shall be tested for leaks, dried, cleaned and free from any Debris.
1.4.3 The station shall be fully purged and pressurized with Nitrogen to 5 bar for a period of 24 hour.
1.4.5 The commissioning of the plant will be performed in multiple phases. Each portion of the plant will
be commissioned and carefully tested separately. Testing will be performed in two steps of
operational pressures and shall include use of Soap solution around flanges, welded joints, and
other connections to ensure there is no leakage.
1.5 BACKGROUND
The Alaoji PRMS project is scheduled to be completed in January 2015 and considering the
readiness of Alaoji power plant for full gas off-take so as to meet Federal Government’s drive to increase
power generation to 5,000MW by November 2014, it is considered expedient to relocate the 138MMSCFD
Geregu Early Gas supply facility, to Alaoji metering station as a stopgap measure pending the availability of
the Alaoji PRMS. Similarly, there is need to also relocate and install a gas heating system from the
upgrade project at Ewekoro metering station in order to enhance the quality of gas to be delivered to the
power plant.
The contract of this relocation and installation was awarded to us at Morpol Engineering Services
Limted to be executed to standards.
The proposed modification will interconnect the existing 18inch inlet and outlet flanges to NDPHC power
plant to replace the existing make-shift 30MMSCFD PRMS skid already supplying gas to the power plant
since 2011.
5
1.5.1 SCOPE OF WORKS
This procedure covers the commissioning of the relocated Geregu Early Gas 138MSCFD PRMS and
the boiler/heat exchanger package from Ewekoro to Alaoji metering station.
Commissioning is a procedure involving Morpol and NGC representatives.
NGC and Morpol will cooperate closely to ensure the commissioning is carried out under safe conditions.
6
through the work regulator. This regulator senses the pressure of the gas downstream of regulating valve
and then adjusts the travel of the valve as required to maintain the desired outlet pressure to a low enough
level, the monitor regulator automatically start to close and assist in the pressure reduction. Finally, if there
is a failure in both regulators to maintain a low enough outlet pressure, the slam shut valve will initiate and
shut off all flow through the system thereby protect the downstream systems from over pressurization.
7
INLET SIZE 12” X 600#
OUTLET SIZE 18” X 300#
2.0 PRECOMMISSIONING
Pre-commissioning note provides procedures for final loop test to ensure compliance with process
conditions and engineering requirements.
The tests described in this section are to be performed in dry mode and the station shall not contain the
product.
Pre-Commissioning is performed prior to start up of the plant by the vendor and contractor, and witnessed
by the client. For safety and operational reasons, client personnel shall witness the Pre-Commissioning
exercise, thereafter commissioning shall be carried out in line with the standards.
Verify installation of all components of system are installed erected in accordance with P&IDs and
design drawings
Using Pen or Pencil, update P&IDs to show any details that have changed from that shown on the
factory As-Built Drawings. Save for permanent record.
Check all mechanical, electrical and tubing connections for completeness
Verify installation of boiler’s control panel
Verify mini water treatment plant for the boilers functionality
Verify that boiler is filled with water to the top of the sight glass
Determine that volume of make-up water is available for use once operations commence.
Check instrument/fuel gas line pressure reduction devices PCV-101A, PCV-101B.
Verify all gauges are installed and ready for operations
8
Confirm the tagging of equipment in accordance with the P&ID
Verify installation of the Temperature Control Valve (TCV-101).
Verify installation of all system and components in accordance with design drawings, best practices
and appropriate completion prior to commissioning.
Check all mechanical, electrical and tubing connections for completeness
Verify site readiness to commence commissioning including Closure of all open pits and trenches,
activation of adequate lighting / illumination for night operations of gas equipment, installation of all
safety items deemed necessary including fire fighting devices, ESD controls and operator
communications with management.
Verify that gas operators, site management and equipment commissioning technical staff hold a
communications meeting discussing pending gas purging and gas system commissioning
activities, all safety issues and concerns.
Verify issuance and review of Gas Hazards and Safety Training Guidelines to all Operators and
Maintenance personnel
Verify implementation of Operator Training program in advance of Commissioning.
Verify existence and execution of Civil/Structural Certificate of Completion between Owner and
General Contractor
Verify existence and execution of Mechanical Certificate of Completion between Owner and
General Contractor
Verify existence and execution of Electrical and Instrumentation Certificate of Completion between
Owner and General Contractor
Once the above are complete, pre-commissioning activities are complete and progress can
advance to Commissioning activities and to start of gas flow.
9
2.4 Pre-Commissioning Check List
MORPOL NGC
A. ELECTRICAL : GENERAL
2. Check the tag for each instrument, the relevant data sheet
and certificate of calibration
5.
11. Ensure that all equipment connected to the control panel are
10
energized and working. After verifying their efficiency, switch
off any equipment that requires the presence of process
fluids to work (water and gas)
Pressure)
• Pressure switches
C Manual valves
D Actuated valves
15. Verify the absence of any slack on the actuator shaft during
movement. Check the complete opening and closing of the
valve, in case set the limits
11
16. Check electric feeding of the solenoid valves and their
effective functioning
F Pressure regulators
G MECHANICAL : GENERAL
21. Check the input voltage to the electric motors and the
phases sense
22. Start the engine and check for proper rotation. Make any
speed calibrations (e.g. pumps with variable speed). Once
the activity have been done switch off the engine until the
station have been put in service
12
3.0 COMMISSIONING
The PRMS will be divided into two sections for the pressure testing activities:
To pressure test each of the sections, the valves at the beginning and the tail end of each section will be
closed and Nitrogen introduced through an instrument tube in the section. This will continue until pressure
of 20bar is achieved after which all the joints (flanged, welded, threaded etc) in this section will be tested for
leakages using soap solution.
When all leakages, if any, are arrested at this stage, Nitrogen introduction will continue until pressure of
40bar is attained. All the joints will be tested again for leakages and the section made to retain Nitrogen at
this pressure for about 12hrs. Whit the 40bar retained for this period, section 1 shall be raised to a pressure
of 60bar and leak test carried out again on all the joints. When all leakages are arrested at this stage and
the section retains Nitrogen at this pressure for 12hrs, the section shall be certified ok.
The section 2 shall be tested in this manner up to a pressure of 40bar as the expected maximum pressure
after reduction is 35bar.
13
3.1.2 Nitrogen Purging
Once all systems have been successfully pre-commissioned, PRMS facilities can be purged with Nitrogen
to remove oxygen from inside the entire station piping.
The goal of these Nitrogen Purging and Pressurization Procedures is to make ready all equipment for the
start-up of gas flow to the power generating plant downstream of the PRMS.
Nitrogen Purging is done in a sequential and logical manner so as to displace all air (oxygen) from inside
the equipment and piping. The process of purging with Nitrogen to displace all oxygen will be subdivided
into purge “segments/sections” with the source of Nitrogen at the front-end and a VENT location at the tail-
end of the segment. Once a segment is successfully purged, the VENT valve will be CLOSED, the block
valve into the next segment will be OPENED and the vent valve at the tail end of the next segment
OPENED.
The purging of any segment shall be deemed successful when a valid Oxygen Sensor, placed in the flow of
vapors at the segment vent, reads 0.5% or less of oxygen content. This oxygen content is an allowable
percentage as it cannot support or sustain a flame or an explosion.
14
3.3 Start Up Of The Steam Boiler
The boiler start up procedure is as follows:
15