PMD 913 - Module 4 - Earned Value Management May22
PMD 913 - Module 4 - Earned Value Management May22
May 2022
Introduction
◼ Earned Value Analysis (EVA) or Earned Value
Management (EVM) is a project management
technique for measuring project progress in an
objective manner.
◼ EVM has the ability to combine measurements of
scope, schedule, and cost in a single integrated
system.
◼ EVM provides an early warning system for project
performance.
Significance
Detail
or
ig
R
d
an
EVM rigor is scaled in
k
is
◼
R
terms of frequency and
detail (granularity) to fit
the project risk Low Low
Performance Schedule
Measures SV>0 & SPI>1 SV=0 & SPI=1 SV<0 & SPI<1
Ahead of
CV>0 & Schedule
On Schedule Behind Schedule
CPI>1 Under Budget Under Budget
Under Budget
Ahead of
CV=0 & On Schedule Behind Schedule
Cost CPI=1
Schedule
On Budget On Budget
On Budget
Ahead of
CV<0 & Schedule
On Schedule Behind Schedule
CPI<1 Over Budget Over Budget
Over Budget
◼ Schedule Forecasting
➢ Time Estimate at Completion (EACT) provides a rough estimate
when the project will be completed
EACT = Planned Project Duration / SPI
➢ EACT can provide differing results from schedule updating???
CV SV
= EV - AC = EV - PV
CPI SPI
= EV / AC = EV / PV
ETC
= (BAC – EV) / CPI
EAC EACT
= AC + ETC = BAC/CPI = PD / SPI
VAC
= BAC - EAC
TCPI
= (BAC – EV) / (BAC – AC)
1.6
1.5
1.4
1.3 Month 2
Month 3 1.2
1.1
Month 1 SPI
0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.1 1.2 1.3 1.4 1.5 1.6 1.7
0.9
0.8
Month 4
0.7
0.6
0.5
0.4
0.3