Part IV Earthwork Quantities
Part IV Earthwork Quantities
Zeleke D.
[email protected]
May , 2019
what do you inspect?
Earth work
Earth work: is the phase during a highways
construction when the right of way is
converted from its natural condition and
configuration to the section and the grades
prescribed in the plans.
Earth Work Activities
• Clearing : removing all trees, brush, buildings, and other
objectionable material and obstructions that may interfere with
the construction of the roadway from area marked on the plan.
• Grubbing: provides for additional preparation of the work area
by removal of remaining stumps, roots, and other obstructions
which exist on or in the ground in all areas designated for
grubbing.
• Removal of Structures and Obstructions:
Buildings, foundations, structures, fences, and other
obstructions which are on the right of way and are not selected
to remain, shall be removed and disposed of in accordance with
the Standard Specifications.
• Roadway and drainage excavation:
• Excavating roadway and ditches, Formation of
embankment
• Grading operation: road bed, shoulder, slopes, ditches
• Excavation for structures:
• Pipe or Concrete box culverts, foundation for bridge, retaining
walls
• Borrow excavation:
• Excavation of quality material from borrow pits
• Loading, Hauling, Placing, Compacting, Grading, Finishing
Earth work equipment
• The basic equipment that will be used:
moisture properties of the soil being placed, but they are also
Borrows Grading
Earthwork Quantity
• Quantity and Cost are calculated in m3 either in its
original form or by allowing for shrinkage and swell.
• The rate of payment generally includes full compensation for
– excavation,
– formation of embankment,
compaction.
• After placing the excavated earth in a fill and compacting, volume will
become less than the original. Difference b/n original volume in cut and
final volume in fill – Shrinkage
– For example, ordinary earth is less by about 10% after filling, whilst
rock bulks by some 20% to 30%. To allow for this, a correction factor
is generally applied to the cut or fill volumes.
Cont‘d
Focus
Example:
if you are given shrinkage of 10%. then the shrinkage factor will be 1 – 0.1 = 0.9
adjusted volume = compacted volume at any station * 0.9
If you are given swell of 20%. Then your load (swelling ) factor is 1/(1+ 0.2) = 1/(1.2).
Adjusted volume = fill volume at any station * 1/(1.2)
Road Bed Sections
• A highway sub-grade is usually formed with
shoulders and a trench section upon which the
pavement will be constructed, the finished surface
being crowned to facilitate drainage.
Methods
a. Trapezoidal rule
b. Simpson rule
a c S=(a+b+c)/2
Thus, we have
Cont‘d
• First, multiply along (downward) the diagonals and
add the products (all positive),
where,
1 X1 Y1 - X2Y1
2 X2 Y2 X1 Y2 X3Y2
3 X3 Y3 X2Y3 X4Y3
4 X4 Y4 X3Y4 X1Y4
1 X1 Y1 X4Y1 -
Sum 1 Sum 2
100m
(14.4, 0) (44.4, 0)
(0, 7.2)
(29.4, 11.5) (69.8, 12.7)
Solutions
1 13.8 0 - 0 14.4 0 - 0
2 0 6.9 95.22 164.22 0 7.2 103.68 211.68
3 23.8 7.8 0 427.44 29.4 11.5 0 802.7
4 54.8 10.5 249.9 354.9 69.8 12.7 373.38 563.88
5 33.8 0 0 0 44.4 0 0 0
1 13.8 0 0 - 14.4 0 0 -
A1 A2 100m
V12 l
2
300.72 550.6
V12 *100
2
= 42,566 m3
2. Prismodal Formula
Average End Area/ trapezoidal/ Method
•Volume of a right prism equals the average area multiplied by the
length. i.e. the mean of the two end areas multiplied by the length
between them.
Vab L 6(A1 4A m A 2 )
• This equation is correct only
when the mid-area of the prismoid
is the mean of the two end areas.
V13 l 3 (A1 4A 2 A 3 )
V35 l 3(A 3 4A 4 A 5 )
V15 l 3(A1 A 5 2A 3 4(A 2 A 4 ))
V l 3(A1 A N 2(remaining odd areas) 4(even areas))
A1 & A2 = parallel end areas a distance l apart and
M= the area at the mid-length, found out by interpolating the linear dimensions.
L = distance between cross sections,
n = an odd number
Examples
1. Determine the quantity of earth work for the portion of a road
between chain age 50 and 60 from the following data. Length
being measured with a standard 20m chain. The formation level
of chain age 50 is 130m and the road is in rising gradient of
1:200. the width of formation level is 10m and the side slope of
3/2:1(H:V) in embankment and cutting. The lateral slope of the
ground may be assumed as level. Apply the trapezoidal formula
for the computation.
chain age 50 51 52 53 54 55 56 57 58 59 60
ground level 131.1 131.2 130.9 131.2 130.8 130.7 130.6 130.4 129.1 129.5 129.7
formation
level 130
Solutions
ground level
131.4
131.3
131.2
131.1
131
130.9
130.8
130.7
Elevations (m)
130.6
130.5
130.4
130.3 1m
130.2
130.1
130
129.9 200m
129.8
129.7
129.6
129.5
129.4
129.3
129.2
129.1
129
128.9
50.5 51 51.5 52 52.5 53 53.5 54 54.5 55 55.5 56 56.5 57 57.5 58 58.5 59 59.5 60 60.5 61
chainages
h = 0.1 m/station
chain age 50 51 52 53 54 55 56 57 58 59 60
Ground
level 131.1 131.2 130.9 131.2 130.8 130.7 130.6 130.4 129.1 129.5 129.7
Formation
level 130 130.1 130.2 130.3 130.4 130.5 130.6 130.7 130.8 130.9 131
Depth of
cut/fill -1.1 -1.1 -0.7 -0.9 -0.4 -0.2 0.0 0.3 1.7 1.4 1.3
5*20=100
Solutions
• Quantity of earth work
B = 10 m, s:1 = 1.5:1
Chain L Earth work quantity
Depth B*d S*d2 A Am=[A1+A2]/2
age (m) Cut (m3) Fill (m3)
50 -1.1 11 1.82 12.82 -
51 -1.1 11 1.82 12.82 12.82 20 256.4
52 -0.7 7 0.735 7.735 10.28 20 205.4
53 -0.9 9 1.215 10.215 8.98 20 179.6
54 -0.4 4 0.24 4.24 7.23 20 144.6
55 -0.2 2 0.06 2.06 3.15 20 63.0
56 0.0 0 0.00 0.00 1.03 20 20.6
57 0.3 3 0.14 3.14 1.57 20 31.4
58 1.7 17 4.34 21.34 12.24 20 244.8
59 1.4 14 2.94 16.96 19.14 20 382.8
60 1.3 13 2.54 15.54 16.20 20 324.8
Total volume 836.20 983.8
Exercise 1
• A 100-m length of earthwork volume for a
proposed road has a constant cross section of
cut and fill, in which the cut area equals the fill
area. The level formation is 30 m
wide, transverse ground slope is 20° and the
side slopes in cut-and-fill are 1/2 horizontal to 1
vertical and 1 horizontal to 1
vertical, respectively. Calculate the volume of
excavation in the 100-m length.
Exercise 2
• A length of existing road of formation width 20 m lies in a cutting
having side slopes of 1 vertical to 2 horizontal. The centre-line of the
road forms part of a circular curve having a radius of 750 m. For any
cross-section along this part of the road the ground surface and
formation are horizontal. At chain age 5+400 m the depth to
formation at the centre-line is 10 m, and at chain age 5+500 m the
corresponding depth is 18 m. The formation width is to be increased
by 20 m to allow for widening the carriageway and for constructing a
parking area. The whole of the widening is to take place on the side
of the cross section remote from the centre of the arc, the new side
slope being 1 vertical to 2 horizontal. Using the prismoidal
rule, calculate the volume of excavation between the chainages
5+400 m and 5+500 m.
– Net fill values are plotted below the X-axis (negative Y value)
iii. The highest or the lowest points of the mass haul diagram
represents the crossing points between the grade line
(roadway level) and natural ground level. OR Points of zero
slope represent points where roadway goes from cut to fill or
from fill to cut. i.e. Peaks indicate a change from cut to fill and
valleys occur when the earthwork changes from fill to cut.
Cont‘d
v. Any horizontal line cutting a loop of a mass curve, intersects the
curve at two points between which the cut is equal to the fill
(adjusted for shrinkage); such a line is called a balance line.
vi. The loop convex upward indicates that the haul from cut to fill is
to be in one direction.
vii. Steep slopes reflect heavy cuts & Fills, while flat slopes
indicate areas fro small amount of earthwork.
Mass-haul Diagram - Example
cumulative volume or
mass ordinate ,or
Drawing a mass-haul diagram Procedures
1. Calculate areas at cross-sections
2. Calculate the volume of fill and cut; cut is + ve and fill –ve.
5. Plot the mass haul diagram i.e. Aggregate volume Vs. stations
2500
2000
1500
1000
500
0
0 100 200 300 400 500 600 700 800 900 1000 1100
-500
-1000
Example 2
• Calculate the cumulative volume with Shrinkage Factor 10%.
+ cut
1 2 3 4 5=3+4 - fill
0 0 0
40000
35000
30000
Cumulative volume (m3)
25000
20000
15000
10000
5000
0
0 100 200 300 400 500 600 700
-5000
– On the mass-haul diagram, it is the area contained b/n the curve and
the balance line.
distance.
the Bill of Quantities) over which a charge is paid only for the
• Overhaul Distance
• OHD = HD ‐ FHD.
Cont‘d
• For example a contractor may offer to haul
overhaul distance.
Cont‘d
• Economical Overhaul Distance:
Let Ce = cost of excavation per unit volume (including free haul)
Cb = cost to excavate borrow pit (including free haul)
Coh = cost of overhaul per m3m
EOH (Le) = Economical Length of over-haul
4
3.6 3.74
Cumulative/aggregate/ Volume,m3
3 3.09
2.88
2.65
2
1.8 1.75
1.59
1 1.05
0.39
0 0 0.05
-0.41
0+000 0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+800 0+900 1+000 1+100 1+200 1+300 1+400 1+500 1+600 1+700
-1 -0.95
-2 -2.01
-2.21
-3
-3.81
-4
-5
Chainage
Exercise 1
1. Given the following end areas for cut & fill, complete the earthwork
calculation using a shrinkage of 10%. Then draw the M.H.D. and the
longitudinal profile of the earthworks & find the following:
d) Waste volume.
e) Borrow volume.
Given that:
- Cost of overhaul = 30 birr/m3.station.
If rate of the
– cost of roadway excavation, Ce, is 800 cents/m3,
100m long.
Exercise 3
1. The tabulated data given below is
the volume of cut and fill for a
given road bed preparation.
Thank you !!!