SIEMENS Transformer Testing
SIEMENS Transformer Testing
In collaboration with
Siemens Power Transformer Division
Siemens AG
Transformatorenwerk Dresden
Overbeckstraße 44, 01139 Dresden, Germany
Tel: (03 51) 8 44 41 00
Foreword
Special tests
17 Measurement of zero-sequence impedance 95
17.1 Purpose and Standards 95
17.2 General 95
17.3 Measuring circuit 97
17.4 Measuring procedure 97
17.5 Appendix: Measure arrangement of
customized vector group 99
1 Introduction
This booklet is to be understood as a supportive guide, giving a summary about applied electrical
measurements. These electrical tests are essential to estimate and verify the specifications and the
dielectric strength of the transformer. It also provides the sense of manufacturer’s internal quality
protection and aspiration of constructing a valuable product. Although some calculations are necessary
for preparing and analysing the measurements, we are not considering the matter of scientific approach
or any mathematical explanations. The essential content is to inform and give formal explanations by
means of basic formulas.
Followed by chapters with descriptions of each measurement, the initial chapters cover the issue of
relevant Standards and dielectric integrity in general, simplifying the area of testing high voltage devices,
such as power transformers.
Note: All pictured circuits are exemplary and only serve as better understanding. The
corresponding measuring circuits for the transformer´s customized vector group will be
appended in the last subchapter of each section (where it is useful).
Core
On the right track right from the start: The iron core and
windings influence the subsequent efficiency of a
transformer. That’s why we design our transformers as
core types in which the wound and non-wound limbs of the
core are located at the same level and connected by
yokes. The choice of sheet metal also greatly effects the
quality of the core. At Siemens, we use only high-quality,
cold-rolled sheet metal. Depending on your requirements,
we may also opt to laser-treat the sheet metal. Using state-
of-the-art numerical controls, we cut the sheet metal
precisely to the millimeter for step-lap layering. This
ensures favorable flux distribution at joints, providing the
basis for low losses and minimized noise during no-load
operation.
Windings
Transformer windings must be able to withstand high
electrical and mechanical loads in daily operation. Our
windings made from copper wire definitely pass the test of
time. Their high mechanical stability ensures safe
operation, no matter what type of winding you need to
meet your power and voltage requirements. For the
winding we use transposed conductors, consisting of many
enamel-insulated, twisted section wires to minimize losses.
Voltage Variation
To adjust the ratio safely and easily to system conditions,
Siemens Power Transformers have tapped windings. In
this way the ratio of Power Transformers can be changed
gradually - either in no-load condition via off-load tap-
changers or under load by means of on-load tap-changers.
Tank
Another main component besides the core and the winding
is the tank of a Power Transformer: It accomodates the
active part and the oil filling. With the final assembly the
active part (the core, windings, pressed parts, tap-changer
and connecting cables) is installed in the tank and filled
with high-grade insulating oil under vacuum. The
transformer is then ready for testing.
Introduction 9
Every transformer has to comply with national and international standards, which are published by
certain institutions. The primary Standards Organizations are the ANSI and the ISO. They specify the
respective tests that verify compliance with the requirements. It is important to know that in terms of the
electric field, the ANSI has delegated the writing and publication of standards to the IEEE, as similar as
the ISO handed over its authority to the IEC. All tests are referred to the IEC and IEEE standards. The
German Standards, settled in the VDE, are mentioned as well.
specific
IEC 60076-xx IEEE C57.12.xx VDE 0532-xx
Standard
Table 1.3.1: Applied Standards
Usually those standards are used directly to develop national standards. Which standards are valid in
which country can be looked up on the respective websites of IEC and IEEE. The Standards and
requirements based on transformers are settled in IEC 60076 and IEEE Std. C57.12 generally.
Routine tests
Routine tests are tests required for every single transformer.
typical examples: Resistance measurement, Voltage ratio, Loss measurements
1
Terms used in the IEEE Standards
10 Electrical Testing Of Power Transformers
Note: Certain dielectric tests, such as lightning impulse tests for example, can be routine-, type-, or
special tests, depending on the respective standard, the insulation system and the maximum
system voltage.
There are often discussions about how and in which order tests will be conducted. Dielectric tests are
generally fixed in IEC and IEEE Standards. Existing Standard recommendations and regulations
referred to this issue are following below.
This test sequence is a recommendation and not obligatory. It serves quality control purposes, verifying
partial discharge-free operation under operating conditions. There are different categories of windings,
which require different test sequences, specified in the referenced IEC Standard (see Table 1.5.1:
Separation according to IEC Standard).
Introduction 11
Highest voltage
Winding
for equipment Tests
category
[kV]
LI SI ACLD ACSD AC
Single-phase Three-phase
(phase-to-earth) (phase-to-phase)
72,5 T NA NA NA R R
Uniform 72,5 < < 170 R NA S NA R R
insulation 170 < < 300 R R* R NA S* R
300 R R R NA S R
72,5 < < 170 R NA S R R R
Non-uniform
170 < < 300 R R* R S* S* R
insulation
300 R R R S S R
Table 1.5.1: Separation according to IEC Standard
R – routine test * If the ASCD test is specified, the SI test is not required.
S – special test
T – type test
NA – not applicable
After IEEE Standards, power transformers are divided into two different classes due to system voltage
and transformer type insulation. This separation has an influence on the test sequence and its
classification (Routine-, Type- or Other test). For more details the IEEE Standards have to be consulted.
Class I Class II
Winding
category Non-graded Graded
/
isolation isolation
Highest system voltage
< 115 115 < 345 345
[kV]
Table 1.5.2: Separation according to IEEE Standard
2
Term used in IEEE Standard for loss factor (tan )
12 Electrical Testing Of Power Transformers
If required, lightning impulse tests shall precede the AC voltage tests. Switching impulse tests, when
required, shall also precede the AC voltage tests. For class II power transformers, the final dielectric
tests shall be the induced voltage test. This test sequence is a recommendation and not obligatory
either.
Based on our own experience and taking into consideration all IEC and IEEE regulations and
recommendations, we suggest the following test sequence:
Different from the common Standards (IEC and IEEE), we treat the Insulation resistance measurement
as a routine test, which means every single transformer has to comply with that test additionally.
Introduction 13
It is expected that a transformer will experience and survive a number of short circuits during its service
life, but sooner or later one such event will cause slight winding movement, and the ability of the
transformer to survive short circuits in future will then be severely reduced. As the transformer ages, its
components deteriorate and the probability of a failure increases. There are several reasons for
deterioration, summarized in the following.
Tap changer
Moving parts in the tap-changer and electrical joints in the tap-changer deteriorate over the years.
Auxiliary components
Auxiliary components such as bushings deteriorate, e.g. bushing gaskets leak causing ingress of
moisture and insulation deterioration.
Gaskets
Main gaskets and pipe work gaskets leak allowing ingress of moisture to the transformer and oil leaks
from the transformer
Rust
Rust causes deterioration of ferrous materials, especially in high humidity climates.
Voltage stresses & dielectric integrity 15
2.1 General
During their operating time, transformers are exposed to several voltage stresses, which can appear
during normal as well as abnormal operation. In general, over-voltages are distinguished into three
categories:
Over-voltages (C)
with a duration in the
order of seconds to minutes
Dielectric tests are intended to verify transformers integrity in case of over-voltages, as described above.
The different groups of over-voltages have also been considered in a test code. The actual test code for
a particular object, which is specified by a Standard, depends primarily on the size and rated voltages of
the object. Test voltages are primarily sinusoidal AC voltages. DC voltages are usually only relevant for
valve transformers, like HVDC transformers. Today´s test programs have their roots in a test code
based on short time AC-tests only, at voltages considerably higher than normal operating voltages. Test
objects either passed the test or broke down electrically. Later on it was found that other voltage
shapes, which includes transient impulse voltages (e.g. switching- or lightning over-voltages), are more
suitable to describe the stresses during abnormal conditions like lightning strikes. Through the evolution
of electronic diagnostic tools, more tests were added, those like the measurement of partial discharges,
which has become indispensable nowadays.
a) configuration of network
b) equivalent diagram
Figure 2.2.1 shows the relationship of the withstand voltage of conductor insulation to earth and the
duration of the over-voltage. Curve I and II represent the general behaviour of the major insulation to
earth in the area of impulse- and temporary overvoltages. Each area is specified in duration and
magnitude.
A: lightning impulse
overvoltage
B: switching impulse
overvoltage
C: temporary
overvoltage
For each area (A/B/C) tests are specified, verifying the impulse and AC withstand voltage of the
Transformer. The magnitude of the three test voltages depends on the highest voltage for equipment
and is defined in IEC and IEEE. For a comparison diagram I & II show the withstand voltage
characteristics of oil and air insulated transformers. It should be mentioned that a significant decrease in
withstand voltage in the area of switching over-voltages occurs. That is why a switching impulse test is
required here in every case, whereas an additional AC voltage test is not necessary. Even though a
transformer’s durability depends on more factors such as, insulation construction, oil purity, temperature,
partial discharge, etc. If the transformer exceeds or runs close to its major insulation level, the operating
life time may be decreased.
18 Electrical Testing Of Power Transformers
Regarding the standards, an alternating test voltage may either consist of a voltage electrically
energizing a circuit called a separate source, or a voltage across two terminals of a winding, needed to
conduct a test called an Induced voltage test. The duration of the alternating test voltage has been
traditionally 60 seconds, which is called “one-minute test” at low frequency (close to the rated
frequency). For voltages substantially above rated value during an induced voltage test, the core will
saturate unless frequency is increased in proportion.
For large high-voltage transformers, the short-time induced voltage test has often been replaced by a
combination of a long-time induced voltage test with measurements of partial discharges, together with
a switching impulse test. The switching impulse is then considered crucially for insulation integrity, while
the level of partial discharges is a qualitative measure of the insulation.
As seen in section: 2.1, there are actually two different types of transient impulse voltages: The
Lightning impulse with a “short” duration and the Switching impulse with a “long” duration. The Lightning
impulse is characterized by a steep voltage rise and a fast decay. On the other hand, the switching
impulse possesses a longer duration for wave front and –tail. The total duration of the switching impulse
is generally ten to twenty times longer than the lightning impulse.
For a lightning impulse, the length of the winding conductor is long compared to the propagation speed
of the impulse along the conductor. The wave characteristics of the winding have to be considered. For
a switching impulse the rate of change in voltage is low enough to permit a model where wave
characteristics can be ignored and transformer behaviour is similar to that under normal AC voltage and
power frequency conditions.
A modern high-voltage test system is mandatory to conduct all common dielectric tests, verifying
transformer’s insulation and integrity. It consists of several parts, which are developed and produced by
only a handful of manufactures. Due to our vicinity to “HighVolt Prüftechnik Dresden“, specialized in
high-voltage test devices, their expertise is very useful in testing of power transformers.
At our grounds we are running two test fields. Because of their spatial dimensions and the installed
equipment, they are not convenient for all high-voltage configurations, which depend on size, rated
power and voltage of the transformer.
Voltage stresses & dielectric integrity 19
1. Control room
1. Control room (1)
Test field 1 is used as the routine test field for Test field 2 is feasible for transformer with
almost every measurement. Because of its less rated voltages. Because of small
larger dimensions (distances to walls etc.), it distances to the walls, lightning impulse
is allowed to conduct measurements with tests are limited to values where no flash
higher voltages than test field 2. overs will occur.
20 Electrical Testing Of Power Transformers
To cover all electric measurements, further devices like AC/DC Peak voltmeter, instrument transformer
controls etc. are installed. In fact there are also portable measuring devices (e.g. winding resistance
meters, voltage ratio meter, etc.), which are not placed in control rooms.
Measurement of winding resistance 21
To know a transformer’s winding resistance is essential. The value is needed for further calculations
and serves a number of functions like:
60076-1
IEC
Clause 10.2: “Measurement of winding resistance”
VDE 0532-76-1
Table 3.1.1: Associated Standards
3.2 General
Winding resistances are always measured in the unit Ohms [ ] and is defined as a direct current
resistance.
Temperature
It is important to know that the resistivity of the conductor material strongly depends on the temperature.
The general statement is with increasing temperature, material’s resistivity also rises. For temperatures
within the normal operating range the following relation between resistance and temperature is
sufficiently accurate:
= resistance at temperature
+ = resistance at temperature
=
+ , = temperature in °C
C = constant (function of material type)
22 Electrical Testing Of Power Transformers
Material IEC [1] IEEE [51] A value of resistance without the respective temperature is
not useful, otherwise the resistance will be considered at
Copper C = 235 C = 234,5 room temperature. The indirect method of establishing the
winding temperature can be achieved by repeating the
Aluminium C = 225 C = 225
resistance measurement at a further random temperature.
Table 3.2.1: Material constants
u =
= · + · i =
L =
There are several methods measuring the winding resistance. The basic methods are the “Kelvin-
Bridge” and the “Voltmeter-ammeter Method”. According to IEEE Standard an accuracy of ± 0,5% is
required for resistance measurement and ± 1°C for temperature measurements.
Our measuring devices are based on the “Voltmeter-ammeter Method” (see Figure 3.3.1), which is
carried out using DC current. The principle is grounded on Ohm’s law, calculating the resistance by the
recorded values. The measurement itself is performed using digital meters (see Figure 3.3.2), but can
also be performed with conventional analog-meters, which requires simultaneous readings and is not
common anymore.
Measurement of winding resistance 23
=
=
=
=
=
=
As noted, the ohmic winding resistances are highly depending on the temperature. For this reason the
measurement is effected with a maximum of 10% of the rated current, in order to avoid an unnecessary
heat-up of the winding. Additionally the winding temperature is measured, which is implemented by
means of a digital thermometer at the bottom of the tank, half way up of the tank’s height and on the
tank cover. The information obtained are averaged and the results taken to be the mean oil temperature
and to be equivalent to the mean winding temperature. An alternative method of test is based on the
direct withdrawal of an oil sample and the measurement of its temperature by means of a precision
mercury thermometer.
24 Electrical Testing Of Power Transformers
Condition
DC-current value, used for measurement:
Maximum value – 10% of the rated winding current, (IEEE Standard permits 15%)
Minimum value – 1,2 times the magnetizing current crest value
Uncertainty in measurements
Using analog instruments the uncertainty is typically ±0,5% (accuracy class 0,2 for instruments and 0,1
for standard resistors used for current measurement). For digital instruments a typical uncertainty is
±0,15%.
Phase
= · = ·
resistance
Line resistance = · = ·
Test circuit
Measuring instruments
TETTEX 2291 Raytech WR50R
The voltage ratio and the phase displacement are principally of interest when it comes up to parallel
operation with two or more transformers.
60076-1
Clause 6: “Connection and voltage displacement symbols for three-phase
IEC transformers”
Clause 10.3: “Measurement of voltage ratio and check of phase
displacement”
Routine test
C57.12.90
IEEE Clause 6: “Polarity and phase relation test”
Clause 7: “Ratio tests”
VDE 0532-76-1
Table 4.1.1: Associated Standards
4.2 General
Voltage ratio
The voltage ratio is considered to be the ratio between the no-load voltages of HV- and LV-side. Vector
groups and their characteristics are only defined for poly-phase transformers. They can be connected in
star-, delta- or zigzag-connection, depending on the requirement. The phase displacement between the
windings can only be influenced within 30° - steps from 0° to 330°, which depends on the connection
method. Transformers parallel operation needs a similar no-load ratio and the same vector group.
Otherwise circulating currents would occur between the parallel transformers, what have to be avoided.
=
=
= =
=
=
28 Electrical Testing Of Power Transformers
Vector groups
The most common vector groups according to IEC 60076-1 (Figure 4.2.1).
IEEE Standard
Vector groups according to IEEE Std.
C57.12.90 are essentially the same as the IEC
vector groups. The designation of the terminals
is H1, H2 and H3 for the high voltage side and
X1, X2 and X3 for the low voltage side.
Figure 4.2.3: Examples of clock numbers
Measuring Circuit
In our test field the digital measuring
instruments are comparing the voltage ratios of
two windings (Voltmeter-method). The principle
measuring circuit is shown in Figure 4.3.1,
which is the same for all transformer vector
groups. If the low voltage side can be measured
without using voltage transformers, it is better to
Figure 4.3.1: Principle Voltmeter-method
feed the high-voltage side, since the voltmeter measuring circuit
is the only load on the transformer to be tested.
30 Electrical Testing Of Power Transformers
Procedure
As a condition, the distribution of magnetic flux in the core has to be the same. This means that only
windings, winding segments and winding combinations which have the same magnetic flux, can be
compared with one another. Normally a reduced voltage is used for the supply. The measurement is
carried out with a minimum of three voltage values (increasing in steps of 10%). The average value
represents the correct measured value and the readings must lie within a range of 1%. Digital
instruments with a sufficiently high resolution are required. They have practically no load to the
transformer because of their high input resistance. A stable voltage source is mandatory to obtain an
accurate measured result.
Measuring circuit
Determining the vector group is only valid for three
phase transformers. This can be applied by
connecting a terminal from the low voltage side to a
terminal on the high voltage side (see bold lined
path in Figure 4.4.1). The terminals 1V and 2V are
then galvanically connected, having the same
potential. If a three-phase supply is connected to the
high voltage winding, potential differences appear Figure 4.4.1: Principal measuring circuit for
verification of the vector group
between the open terminals and are used to
determine the vector group.
Procedure
The measuring instruments, which are the same for
Figure 4.4.2: Graphic display of voltages
voltage ratio, energize the transformer with a
symmetric 3-phase voltage supply and conducts the
procedure (described above) automatically, creating
a chart as a printout, by which the respective vector
group is determined (example in
Figure 4.4.3). Generally both measurement (voltage
ratio & voltage group) can be conducted by the
“Tettex 2793a” or “Raytech TR-Spy Mark III”.
Voltage ratio & verification of vector group or phase displacement 31
Test circuit
Measuring instruments
voltage ratio, vector group (3-phase) voltage ratio, vector group (3-phase)
Knowing the exact load loss and short-circuit voltage is interesting, not only for the operating costs It is
important to know in case of large power transformers (non-permissible temperature rise, see section:
14. Temperature rise measurement). Moreover it gives an indication about the eddy-losses caused by
leakage fluxes in mechanical parts like the tank wall, by comparing the calculated and measured values
For transformers with tapped windings the short-circuit voltage has to be measured in the principal tap
position and the two extreme tap position additionally.
60076-1
Clause 10.1: “General requirement for routine, type and special tests”
IEC Clause 10.4: “Measurement of short-circuit impedance and load loss”
60076-8
Clause 10: “Guide to the measurement of losses in power transformers” Routine test
C57.12.90
IEEE
Clause 9: “Load losses and impedance voltage”
VDE 0532-76-1
Table 5.1.1: Associated Standards
5.2 General
The generally applicable short-circuit equivalent schematic can be seen in Figure 5.2.1.
An AC voltage is connected to one winding system of a transformer with the opposite winding
system short-circuited. When rated current flows in the short-circuited winding system, the
appearing voltage between the terminals is the short-circuit voltage. The absorbed active power
corresponds to the transformer load loss.
34 Electrical Testing Of Power Transformers
a)
= 1
= 2
= 1
= 2
=
=
=
b)
Because of the short-circuit, the iron
losses and the main reactance don’t
have to be considered.
c)
= +
= +
=
=
A component of the transformer’s no-load losses ( + ) will also be measured. It can be neglected,
since the short-circuit voltage is minimal compared to the rated voltage (exceptions are starting
transformers with an air gap, reactor transformers, etc.). The manufacturer ensures all data about short-
circuit voltage and load loss.
Short-circuit voltage
According to Figure 5.2.1 c) the short-circuit voltage can be determined as follows:
=
( )
=
=
=
=
= + = · %
describes the relative short-circuit voltage. It is given as a percent of the rated voltage. With this
value it can be determined which current flows in case of a short-circuit during operation.
=
= ·
=
For power transformers a small value of relative short-circuit is requested unlike furnace arc
transformers which have higher relative short-circuit values.
Load loss
The total losses occurring within the transformer when rated current and frequency is applied are
represented in the load loss. It is made up of the ohmic losses of the windings and internal connections,
as well as the stray losses (eddy current losses) caused by leakage fields in the windings and the
mechanical parts. The load loss is referenced to the winding temperature (75°C according to IEC and
85°C according to IEEE).
=
= + =
=
36 Electrical Testing Of Power Transformers
Figure 5.3.2 and Figure 5.3.1 showing the measuring circuit for load loss measurements on single-
phase and three-phase transformers. Usually the short-circuit is applied on the low voltage side of the
transformer, because it is more practicable to adapt the test equipment in the test field.
In case of testing three-phase transformers there are principally two different wattmeter configurations
possible: the two- and the three-wattmeter method. The three-wattmeter method is preferred, because it
more accurate and allows to determine the power per phase (for investigation tests).
Figure 5.3.2: Measuring circuit for single-phase Figure 5.3.1: Three-wattmeter method for
transformers three-phase transformers
Winding resistance and winding temperature measurements must be carried out before the actual load
loss measurement. If there are built-in current transformers, they must be shorted during the test to
avoid saturation of their iron cores and prevent over-voltages at their secondary terminals. The bushing
taps must be earthed. If the transformer is equipped with an on-load tap-changer, the first loss
measurement is carried out at the principal tap and subsequently at the highest and lowest taps.
During the test, the current is adjusted steadily upwards (from zero to full measuring current) in order to
avoid inrush currents. Its DC component can lead to instrument transformer errors, which cannot be
corrected (pre-magnetization of the current transformers).The duration of the test should be as short as
possible avoiding any significant heating in the windings. Therefore the measuring time at rated current
should be about 30 seconds (rule of thumb).
Moreover the measuring current should be as close as possible to the rated current, although IEC
specifies that the current should not be below 50% of rated current. To confirm the measured results a
second measurement with approximately 10% lower current, is recommended. The values should be
agreed by extrapolating the two points.
Short-circuit voltage & load loss 37
1-3 1 3 2
2-3 2 3 1
Table 5.4.1
+
=
+
=
+
=
38 Electrical Testing Of Power Transformers
Test circuit
Measuring instruments
Tettex TMS-PT-581
Voltage transducer
Output voltage: 100 V
0,5, 1, 2, 5, 10, 20, 50,
Measuring range:
100, 200, 400, 800 kV
0,04 % (5-800 kV)
Overall accuracy: 0,1% (1-2 kV)
0,15% (0,2-0,5 kV)
Tettex TMS-CT-582
Current transducer
Test field 1 Test field 2
Output current: 1A 1A
1, 2, 10, 20, 40, 100, 1, 2, 5, 10, 20, 50, 100,
Measuring range:
500, 1000, 2000, 4000A 500, 1000, 2000 A
0,005% (40-4000 A) 0,005% (20-2000 A)
0,01% (10-20 A) 0,01% (5-10 A)
Overall accuracy:
0,03% (4 A) 0,03% (2 A)
0,05% (2 A) 0,05% (1 A)
Measuring the no-load loss & no-load current 39
The no-load loss is a very important value, representing a considerable amount of energy during the
life-time of the transformer. The no-load losses are caused by the no-load current which is necessary to
excite the transformers core. The actual loss figure has to be guaranteed and depends on the sheet
material of the core and its manufacturing process.
60076-1
Clause 10.1: “General requirement for routine, type and special tests”
IEC Clause 10.5: “Measurement of no-load loss and current”
60076-8
Clause 10: “Guide to the measurement of losses in power transformers” Routine test
C57.12.90
IEEE
Clause 8: “No-load losses and excitation current”
VDE 0532-76-1
Table 6.1.1: Associated Standards
6.2 General
Unloaded Transformer
An energized but not loaded transformer can be seen as an iron core reactor. The equivalent diagram
for this case is shown in Figure 6.2.1. The secondary winding can be neglected, because there is no
current flow.
=
=
=
=
=
E =
Figure 6.2.1: No-load equivalent diagram
40 Electrical Testing Of Power Transformers
B =
H =
=
=
No-load current
The no-load current express the sum of the current
needed for the magnetization of the core and a
capacitive current reflecting the capacitances
between the windings. Because of the non-linear
magnetization characteristic of the iron core, the
corresponding no-load current is naturally distorted
when a sinusoidal voltage is applied (see Figure
6.2.3). The measured no-load current is as RMS
value. It is generally expressed in percentage of
the rated current and is about 1 to 5 % for small
power transformers and 0,1 to 0,3% for large
power transformers. For three-phase transformers
Figure 6.2.3: No-load current
the value is the average of the three windings.
No-load loss
The no-load loss of a transformer consists of several components:
a) Iron losses = +
b) Dielectric losses = · · ( )
c) Winding losses = ·
+
Measuring the no-load loss & no-load current 41
Usually dielectric and winding losses are negligible, because for power transformer they are several
orders of magnitude smaller. That means that the no-load losses are equal to the iron losses ,
which consist of hysteresis losses (depending on sheet metal of the core) and eddy losses (depending
on sheet thickness). There’re exceptions like starting transformers with an air gap.
Those voltage distortions do not occur during operation because the impedance of the supply system is
much smaller than the transformers main inductance . Comparing the losses of different transformers,
the no-load losses are guaranteed using a sinusoidal supply. Losses measured with distorted voltage
must be recalculated.
If the above conditions cannot be met, the measured no-load loss can be referred to the above
reference temperature of 20°C using the following empirical formula:
= ·( +( )· )
= 20°
=
=
=
42 Electrical Testing Of Power Transformers
Single-phase transformer
The position of the circuit-earthing may create an error on the measured no-load loss figure when
measuring no-load loss on single-phase transformers. The source of the error is a capacitive earth
current caused by parasitic cable capacitances and generator and matching transformer windings.
Normally the three capacitive currents , and are approximately of the same magnitude and
shifted in phase by 120°. In this case the resulting current is zero. If the supply voltages do not have
the same potentials to earth, there will be a residual current , which can affect the no-load current,
depending on the location of the earth termination. This source of error can be eliminated by placing the
earth ahead of the current transformers (seen from the supply side, see Figure 6.3.1).
=
=
=
AT =
Three-phase transformer
When testing three-phase transformers, the voltages induced in the individual windings (phase voltages)
must be measured to determine the form factor of the voltage. The form factor for star-connected
windings is different, because it cannot include harmonics divisible by three. The individual elements of
the measuring circuit should fulfil the following requirements:
Yyn
Voltmeters must measure
YNyn the phase voltages
Typically, measurements are taken starting at 110 and decreasing to 100, 90 and 80% of rated voltage.
When testing large three-phase units the three watt-meters may show differing figures. It is even
possible for one wattmeter reading to be negative. The magnetic asymmetry of the iron core causes
asymmetrical no-load currents. Depending on the flux density in the core, the phase displacement
between current and voltage in one phase is greater than 90°, which will be seen as a negative power
in one wattmeter. After all, the actual input power is the sum of the readings of three watt-meters. The
measuring instrument “Yokogawa WT3000” does this automatically, since it has more than three input
channels.
Measuring the no-load loss & no-load current 45
Test circuit
Measuring instruments
Tettex TMS-PT-581
Voltage transducer
Output voltage: 100 V
0,5, 1, 2, 5, 10, 20, 50,
Measuring range:
100, 200, 400, 800 kV
0,04 % (5-800 kV)
Overall accuracy: 0,1% (1-2 kV)
0,15% (0,2-0,5 kV)
Tettex TMS-CT-582
Current transducer
Test field 1 Test field 2
Output current: 2, 4, 8 A 2, 4, 8 A
1, 2, 10, 20, 40, 100, 1, 2, 5, 10, 20, 50, 100,
Measuring range:
500, 1000, 2000, 4000A 500, 1000, 2000 A
0,005% (40-4000 A) 0,005% (20-2000 A)
0,01% (10-20 A) 0,01% (5-10 A)
Overall accuracy:
0,03% (4 A) 0,03% (2 A)
0,05% (2 A) 0,05% (1 A)
46 Electrical Testing Of Power Transformers
Separate source AC withstand voltage test (Applied voltage test) 47
The test is designed to check the main insulation of the transformer. This main insulation is generally
understood as the insulation system between two windings (major insulation), but also the insulation
between the winding and earth (end insulation) and all connections to earth.
C57.12.90
Clause 10.6: “Applied voltage tests”
IEEE Routine test
C57.12.00
Clause 5.10: “Insulation levels”
VDE 0532-76-3
Tabelle 7.1.1: Associated Standards
7.2 General
In this test a separate AC source is applied to the transformer (“applied-voltage test”). For transformers
with uniform insulation every part of the winding is exposed to the test voltage , which relates to the
insulation level of the transformer between the windings and earth. In case of transformers with graded
insulation between their windings, the test voltage must be adjusted to the lowest insulation
requirements (usually the winding end or neutral).
48 Electrical Testing Of Power Transformers
The principle test circuit is shown in Figure 7.3.1. The equivalent diagram of the transformer under test
is an R-C parallel circuit consisting of the effective capacitance , representing the capacitance
between the winding under test and earth (including the bushing capacitance) or between the other
windings, and the resistor R, representing the insulation (Figure 7.3.2). The used principle measuring
circuit in test laboratory is shown in Figure 7.3.3.
G =
=
=
=
= Figure 7.3.1: Test connection for
a three-phase transformer
=
K =
=
=
=
HM =
VT =
Figure 7.3.2: Capacitances of the transformer
ransformer
CT =
Before the test can be carried out, it must be ensured that the whole winding insulation is calculated
properly for the test voltage. Care must be taken for transformers with graded insulation (non-uniform),
where the voltage level must be adjusted to the insulation of the transformer neutral. In this case each
phase will be tested individually, see test connections in Induced voltage tests for non-uniform
transformers
The Buchholz-relay and all bushings must be degassed before the test; any surge arresters and
bushings arcing horns must be removed. Electrodes, such as spheres or similar protection shields
mounted on the outer terminal of the bushing are permitted because they increase the external electric
strength, whereas the applied voltage test verifies the internal electric strength. Generally the test must
be carried out at ambient temperature (at least 10°C). During the test, the voltage is applied directly to
the bushings of the transformer windings by a single-phase source. All other windings and the tank
must be earthed (see Figure 7.3.1).
Acceptance criteria
The test is successful if the test voltage does not collapse or if there is no indication of other faults
(smoke, bubbles, sudden current increase).
50 Electrical Testing Of Power Transformers
Measuring
; 2; RMS -value
quantities:
Accuracy: max. ±0.5%
Reactor
The purpose of the test is to verify the integrity of the insulation for transient voltages, which are caused
by atmospheric phenomena (lightning strikes), switching operations or network flaws.
60076-4
“Guide to lightning impulse and switching impulse testing of power
transformers and reactors”
Routine tests
C57.12.90 LI for
Clause 10: “Dielectric tests” > 115 kV
SI for
IEEE
C57.98 > 345 kV
“Guide to impulse testing techniques, interpretation of oscillograms and
failure detection criteria” for the rest:
Other tests
0532-76-3
VDE acc. to IEC
0532-76-4
Table 8.1.1: Associated Standards
8.2 General
Because impulse tests always mean high dielectric stresses for the insulation system, it is possible that
hidden damages occur, which will be identified during the voltage insulation tests. That is why, if not
otherwise specified, the impulse test (SI and LI) precede the insulation tests (applied voltage test and
induced voltage test in combination with PD measurements).
Impulse shapes
Switching impulses as well as lightning impulses have standardized wave shapes. The following table
shows the essential differences.
52 Electrical Testing Of Power Transformers
Polarity: negative2
chopped waves
peak should be 10% higher full wave
value
chopping after =2–6 s
overshoot not higher than 30% of test
amplitude
impulse at about 60% of the specified one reduced level full impulse (calibration)
insulation level one full level full impulse
three impulses at the specified insulation one reduced level chopped impulses
level (if requested)
two full level chopped impulses
Consider: It may force the core into saturation, (if requested)
because switching impulse represents a time two full level full impulses
integral of the applied voltage to the transformer.
(Chopped wave should have an amplitude of
110% of full wave amplitude)
Table 8.2.1: Characteristics of Switching- and Lightning impulse
1
time above 90% of peak voltage
2
for oil insulated transformers
Switching impulse test & Lightning impulse test 53
To prevent flashovers on the air-side of the transformer bushings, the polarity of the impulse voltages is
generally negative. Because of their unusual aperiodic waveform transient voltages cannot be
generated perfectly. Therefore the definition of rise time needs additional specification: A straight line
from the bottom to the peak, passing through the voltage values 0,3 and 0,9 times the crest value, gives
the rise time (see figures in Table 8.2.1; SI and LI). The rise time is then 1,67 times the time between
these two voltage values.
The following figure shows the impulse test circuit with all its components. It is illustrated in three ways
to make out the different parts of the circuit:
= =
= =
= =
SFS = , =
TFS = =
= SG =
= CG =
= MK =
= IPV =
= IMS =
54 Electrical Testing Of Power Transformers
=
R = Figure 8.3.1: Common test connections
O =
Preparation
Before conducting the impulse tests (Lightning- and Switching impulse), the transformer will be checked
for the following points:
standing time
confirming measurement of voltage ratio, polarity and winding resistance
oil level and quality
vent the Buchholz relay and porcelain bushings
short-circuit and earth any built-in transformers
earth the capacitive bushing taps
check on-load or off-load tap changer positions
Switching impulse test & Lightning impulse test 55
Steps
The actual impulse tests:
Acceptance criteria
The switching and lightning impulse tests are successfully if the recordings of the oscillographics do not
show any changes (close similarity in wave form; between calibrated voltage and applied test voltage).
If the waveforms are deviated from each other, the reasons have to be determined.
In this section the most important components of our high-voltage test field are introduced. They are
mandatory to simulate Switching- and Lighting impulse voltages.
IG 300/2000G IG 120/1600G
Number of stages: n = 10 Number of stages: n = 10 (extended)
Capacitance per stage: = 1500 nF Capacitance per stage: = 1500 nF
Charging voltage per stage: = 190 kV Charging voltage per stage: = 190 kV
Total charging voltage: = 1900 kV Total charging voltage: = 1900 kV
Total charging energy: 300 kJ Total cha ging energy: 150 kJ
Lightning impulse voltage: Lightning impulse voltage:
= 1675 kV = 650 kV
(permitted) (permitted)
Switching impulse voltage: Switching impulse voltage:
= 1100 kV = 350 kV
(permitted) (permitted)
56 Electrical Testing Of Power Transformers
=
+
Switching impulse test & Lightning impulse test 57
Test circuit
58 Electrical Testing Of Power Transformers
Lightning and Switching surges can be transferred from one voltage level to another through
transformer couplings. A distribution system, which may not be directly exposed to the overvoltages of
atmospheric origin, but is connected to a utility system through a transformer of high turns ratio will be
exposed to overvoltages on the secondary side due to overvoltages on the primary windings. The
resulting stresses on the distribution system may exceed the basic insulation levels (BIL). The
inspection of transferred overvoltages is only justified for large generator step-up transformers, which
have a large voltage ratio and high-voltage network transformers with a low-voltage tertiary winding.
The issue of transferred overvoltage is also treated from a system viewpoint in IEC 60071-2 Annex A.
Procedure
When the low-voltage winding cannot be subjected to lightning over-voltages from the low-voltage
system, this winding may be impulse tested with surges transferred from the high-voltage winding. This
method is also be preferred when the design is such that an impulse directly applied to the low-voltage
winding could result in unrealistic stressing of higher voltage windings, particularly when there is a large
tapping winding physically neighbouring to the low-voltage winding.
With the transferred surge method, the tests on the low-voltage winding are carried out by applying the
impulses, at lower impulse levels (approximately 25% of original impulse level) to the neighbouring
higher voltage winding. The line terminals of the low-voltage winding are connected to earth through
resistances of such value that the amplitude of transferred impulse voltage between line terminals and
earth, or between different line terminals or across a phase winding, should be as high as possible but
not exceeding the rated impulse withstand voltage. The magnitude of the applied impulses shall not
exceed the impulse level of the winding to which the impulses are applied.
Test circuit
The impulse voltage will be applied on each High-voltage terminal Low-voltage terminal
high-voltage terminal (except neutral). The (impulse applied) (transferred overvoltage)
transferred overvoltage will be measured on 2U
each low-voltage terminal separately, which 1U 2V
means that nine measurements have to be 2W
taken in total. The acceptance criteria are the 2U
same as for the standard impulse voltages.
1V 2V
2W
2U
1W 2V
2W
Partial Discharge Measurement 61
A partial discharge measurement is another important way to verify the transformers insulation system,
ensuring that no harmful PD sources exist. The purpose of a PD-measurement is to detect and localize
areas where partial discharges are about to occur, typically cavities or conducting particles inside the
insulating material. Those areas are exposed to higher dielectric stresses, which in the long run can be
very harmful to transformers insulation (e.g. electric breakdown). So usually PD-measurements are
carried out in conjunction with dielectric tests (Induced voltage test).
60076-3
Annex A “Application guide for partial discharge measurements during AC Routine test
IEC withstand voltage test on transformers according to 12.2, 12.3 and 12.4” for
60270 > 72,5 kV
“Partial discharge measurements”
Routine test
C57.12.90
IEEE for
Clause 10.8/10.9: “Induced voltage tests”
115 kV
Because the partial discharge measurement and the induced voltage test are carried out
simultaneously, the corresponding measuring circuit of the customized vector group is consolidated in
the next section (“Induced voltage test”, see 10.5 Appendix: Measure arrangement of customized vector
group).
62 Electrical Testing Of Power Transformers
9.2 General
BU =
HV =
NT =
, , = Figure 9.2.1: Schematic representation of
( ) a part of the transformer
insulation
=
= ( )
HV =
LV =
RW =
NT =
G =
Q(t) = Q( ) + ( ) dt Z =
=
=
Q(t) = =
Q( ) = i(t) =
~ ,~ =
Worth mentioning is the different approach of PD q =
measuring by the IEEE, transforming the signal =
to a Radio Interference Voltage (RIV), generally
measured in microvolts ( V). Most PD systems
available on the market perform a “quasi-
integration” of the PD current impulses in the
frequency domain using wide-band filter.
= (= )
=
=
=
= Figure 9.3.2: Calibration circuit for PD measurement
= (bushings with capacitive tap)
64 Electrical Testing Of Power Transformers
= (= )
=
= Figure 9.3.3: Calibration circuit for
= PD measurement (bushings
without capacitive tap)
=
Although there are some differences between the IEC and IEEE Standard, the PD measurement is
basically integrated in the Induced voltage tests (see section: 10 Induced voltage tests). Considering
the IEC Standard, PD measurement is mandatory for long- and short duration induced voltage tests
(ACLD and ACSD). The time sequences are shown in Figure 10.4.1 and Figure 10.4.2, according to
IEC. PD activity will be checked on all bushings where the system voltage is higher than > 72,5kV.
The measurements (in pC) are carried out at each voltage level, except the enhanced level (part C) and
should be documented.
Acceptance criteria
The PD test is considered successful if no partial discharges activity greater than the specified apparent
charge amplitude in pC is detected at any bushing, and if there is no rising trend in the apparent charge
amplitude during the long duration test. The recommended acceptable values of apparent charge,
according to IEC Standards are:
300 pC at 130%
500 pC at 150%
the level of continuous PD activity does not exceed 100 pC at 1,1
If the PD activity cannot comply with the requirements, the type and the location (external or internal
insulation system) of the PD source has to be detected. In
Table 9.4.1 typical PD sources are shown, which is just for a better visualization. Those PD pattern can
be regarded as a fingerprint of the partial discharge activity of a specific defect in the transformers
insulation system. For getting more details about the subject of PD source investigation, professional
literature has to be consulted.
Partial Discharge Measurement 65
Conducting material
(tip electrode) with
direct contact to
metallic electrode
Conducting material
without any contact to
metallic electrode
Non-conducting
material (cavity) with
direct contact to
metallic electrode
Non-conducting
material (cavity)
without any contact to
metallic electrode
Non-conducting
material (cavity)
without any contact to
metallic electrode with
changing surface due
to the partial
discharge
The induced voltage test verifies the AC withstand strength of each line terminal and its connected
windings to earth and to other windings, but also between phases and along the winding (turn-to-turn
insulation).
VDE 0532-76-3
Table 10.1.1: Associated Standards
10.2 General
The testvoltages of this measurement are nearly the same as for the Applied Voltage Test (see
section 7). The difference is the measuring procedure and the possibility to conduct a Partial Discharge
Measurement (during the whole test duration), which can indicate insulation faults before an electric
breakdown occur. There are essential differences between the IEC and IEEE understanding of induced
voltage tests. Generally IEC distinguishes between:
Note: Partial discharge measurements (PD; see section: 9 Partial Discharge Measurement) has to be
conducted simultaneously, except for transformers with < 72,5kV.
IEEE distinguishes only between class I ( < 115kV) and class II ( 115kV) transformers. For class
II transformers a long duration test in combination with a PD measurement is always required. Table
10.2.1 gives an overview about the separation, according to IEC and IEEE Standards.
68 Electrical Testing Of Power Transformers
Three-phase Single-phase
Highest voltage
ACLD ACSD ACLD ACSD
Category of winding for equipment
[kV] Phase- Phase- Phase-
to-earth to-phase to-earth
test test test
According IEC
< 72,5 X X
72,5 < < 170 PD PD
Uniform
insulation 170 < < 300 PD PD
> 300 PD PD
72,5 < < 170 PD PD PD
Class II 115 PD PD
Table 10.2.1: Induced voltage tests for three- and single-phase transformers
Preparations
The actual test should not be carried out until the impregnation of the windings has been completed.
The necessarily “standing-time” depends on the rated voltage of the transformer (e.g. about 3 days for a
220 kV transformer).
The Buchholz-relay and all bushings must be degassed before the test; any surge arresters and
bushings arcing horns must be removed. Unlike in the applied voltage test: Electrodes, such as spheres
or similar protection shields mounted on the outer terminal of the bushing are highly recommended,
especially for high voltage tests. These electrodes are mandatory for partial discharge measurements in
combination with the induced voltage test.
Test voltage
The test voltage depends on the highest voltage for equipment and can be looked up in the
Standards. Generally these are the same values used in the separate source AC withstand voltage test
(except ACLD) and is about twice the rated voltage.
= (C)
= · =
=
= 1,3 · ( )
= 1,3 · ( )
3
= 60076 3, 7
C =
Long-duration AC withstand
voltage test (ACLD)
= 1,5 · ( )
3
= 1,7 · ( )
3
C =
30 min < 300
=
60 min > 300
Figure 10.4.2: Voltage level sequence (ACLD)
Long-duration AC withstand
voltage test (ACLD)
The voltage shall first be raised to the 1h level and held for a minimum of 1 min or until a stable partial
discharge level is obtained to verify that there are no indications of partial discharges (voltage level of A
and C are the same). The level of partial discharges shall be recorded just before raising the voltage to
the enhancement level (B), which is held for 7200 cycles. Then the voltage shall be reduced directly to
the 1h level (C). Partial discharge measurements shall be made at 5 min intervals.
Acceptance criteria
The test is successful if the test voltage does not collapse. In combination with PD measurements the
criteria for success of the test are further explained in section: 9 Partial Discharge Measurement.
Induced voltage tests 71
In case of ACLD tests, single-phase connection (phase-to-phase) are possible as well, but are not
obligatory. Recommended test connections which avoid excessive overvoltage between line terminals
are shown below. Other separate windings shall generally be earthed at the neutral if they are star-
connected and at one of the terminals if they are delta-connected. Depending on the low-voltage
winding, three different generator connections are possible.
Test circuit 1 (with capacitive tap) Test circuit 2 (without capacitive tap)
Measuring instruments
Note: The power analyser “Yokogowa WT3000” is used additionally, observing applied voltage and current
Insulation resistance measurement 73
The insulation resistance test (also commonly known as a “Megger test”) is a spot insulation test which
uses an applied DC voltage and is performed to determine the insulation resistance from a winding to
earth or between individual windings. This value is important to know, when assessing the transformers
insulation condition. The measured insulation resistance is to be understood as a reference value used
for comparison in measurements made at a later stage. In our test field the Insulation resistance
measurement is treated as a routine test, different from the applied Standards.
Routine test
> 72,5 kV
60076-1
IEC
Power transformers – Part 1: “General”
Special test
< 72,5 kV
Routine test
for class II transformers
C57.12.90
IEEE
Clause 10.11 “Insulation resistance tests”
Other test
for class I transformers
Table 11.1.1: Associated Standards
11.2 General
Although there are more sophisticated measuring methods, like the FDS measurement (section: 20
FDS measurement for moisture estimation), the advantage of this method is the very easy procedure.
The value the insulation resistance is generally measured in megohms (M ), which depends strongly
on transformers design, temperature, dryness and cleanliness (especially bushings). Considering those
factors can help to explain and find existing insulation uncertainties. It has to be noted that insulation
measurement varies with the applied voltage. To compare measurements with each other, the applied
voltage should always be the
74 Electrical Testing Of Power Transformers
In accordance with the IEC Standard, the duration for the measurement is 1 minute. The readings take
place after 15 seconds ( ) and 60 seconds ( ). The ratio of / is a criteria for the insulation
condition and should be in the range of 1,3 – 3.
The IEEE defines the measurement with a third reading of the resistance after 600 seconds ( ).
With that value the “Polarisation Index (PI)” can be determined, which serves as an evaluation of the
insulation as well. PI values < 1 stand for unsatisfactory condition, whereas PI values > 2 indicate a
really good condition.
Polarisation Index: =
The number of measurements increases with the presents of a tertiary winding, because more
combinations of connections are possible. The temperature of the transformer should be close to the
reference temperature of 20°C.
Insulation resistance measurement 75
Test circuit
Measuring instruments
Although all on-load tap-changers are tested individually during the manufacturing process, it is
necessary to check the correct operation in combination with the fully assembled transformer, verifying
a proper performance without failure during operation.
60076-1
Clause 10.8: “Test on on-load tap-changers”
IEC Routine tests
60076-3
Clause 10: “Insulation of auxiliary wiring”
Routine tests
for class II
C57.12.00
transformers
Table 19 and clause 8.2.3: “Dielectric test for low voltage control wiring,
IEEE
associated control equipment and current transformer secondary circuits, on
Other tests
Class II power transformers”
for class I
transformers
Specified by the IEC Standards, the following tests for tap-changers have to be conducted:
The test circuits with rated voltage is similar to that for measurement of no-load loss (see section: 6
Measuring the no-load loss & no-load current) and the test circuit for the operation test with rated
current is similar to that for measurement of load loss (see section: 5 Short-circuit voltage & load loss).
The tap-changer should be observed and checked for any abnormal activities during the test.
78 Electrical Testing Of Power Transformers
In addition to the on-load tap-changer test, the auxiliary equipment have to be tested. Therefore all
wirings for auxiliary power and control circuits are subjected to an AC separate source test (2kV RMS to
earth for 1 minute, acc. IEC). The IEEE Standard specifies an AC applied voltage test at 1,5kV RMS for
the auxiliary equipment, excluding current transformer circuits, which are tested at 2,5kV RMS. If some
of the auxiliary devices (e.g. motors and other apparatus) have a lower test voltage than specified for
the wiring alone, they have to be disconnected before the test. This test will be carried out with the high-
voltage testing unit “Schleich GLP1-g”. The test is successful when voltage breakdowns occur.
IEC IEEE
Schleich GLP1-g
manual adjustable AC high-voltage source
arc detection
Current transformers, together with voltage transformers (VT), are known as instrument transformers.
They are used for measuring alternating currents and voltages, operating on the same principle of
common transformers. Because measuring and recording instruments are really sensitive, they are not
allowed to be exposed to high currents. Therefor the current transformer produces a reduced current
accurately proportional to the current in the circuit, which can be conveniently connected to measuring
system. Additionally current transformers isolate the measuring instruments and protect them from
over-voltage in the monitored circuit.
60044-1
IEC Routine test
Instrument transformers - Part 1: Current transformers
C57.13
“…current and inductively coupled voltage transformers used in
IEEE Routine test
measurement of electricity and the control of equipment associated with the
generation, transmission, and distribution of alternating current.”
13.2 General
The portable Omicron CT-Analyzer performs excitation, ratio and polarity tests on current transformers
using the voltage-comparison method. Current transformers can be tested in their equipment
configuration, such as being mounted in transformers, oil circuit breakers or switchgear. It is necessary
for the equipment to be totally isolated from the electrical system prior to testing.
Polarity Test
Connected to the high voltage winding, the method is used will be conducted by switching on a DC
current source briefly. The polarity can be checked on a polarized voltmeter, connected to secondary
winding (low voltage side). The voltmeter must be calibrated to be sure that the deflection is correct.
Usually a series resistor is applied in the circuit to protect the instrument. If the polarity of the
transformer is correct, the deflection must be in the same direction when the DC current is switched on.
Saturation Test
Measuring the excitation voltage and excitation current that results as the voltage applied to the CT
under test increased. As the CT under test begins to saturate, a large increase in current will be
detected for a small increase in voltage. With this test the magnetization curve and magnetization
characteristics will be confirmed. Saturation test shall be conducted before ratio test and after polarity
test, since residual magnetism left in the core due to DC test (polarity, resistance), which leads
additional error in ratio test.
Ratio Test
The ratio test is performed by comparing a voltage applied to the secondary winding to the resulting
voltage produced on the primary winding. For example, if 1 volt per turn is applied to the secondary
winding, the voltage present on the primary winding would be 1 volt. More specifically, if 120V were
applied to the secondary of a 600/5 current transformer (120:1 ratio), 1V should be present on the
primary winding.
Omicron CT-Analyzer
Primary Secondary Testing of current transformer
(Transformer (CT Conductor)
Conductor)
Automatic evaluation according to IEC & IEEE
Measuring of polarity, ratio, excitation/saturation,
winding resistance, burden impedance
Accuracy: 0,02% of readings
Temperature rise measurement 81
The rate of aging or decomposition depends strongly on the temperature the insulation material is
exposed to. At a temperature of 100°C is already a noticeable degree of decomposition. According to
Montsinger´s law, on which different loading guides are based, the aging rate doubles with each
temperature increase of about 6 K in the range from 80°C to 140°C. As a result, the Standards have not
only established the highest permissible temperature values for the windings and oil, but also rules for
permissible overloads, including their influence on life expectancy. Defined by IEC, the term
temperature rise is the difference between the temperature of the average winding temperature and the
temperature of the external cooling medium. It confirms the guaranteed temperature rises of oil and
windings. It is also useful for detecting possible hot-spots in- and outside the winding. Measuring the
average- and top oil temperature rise, as well as knowing the winding-oil gradient, may be really
important in terms of future upgrades (overload considerations).
14.2 General
The temperature inside the transformer has to comply with certain temperature limits, specified by IEC
and IEEE Standards. Those limits are necessary to guarantee a long and reliable service of the
transformer. To compare between different transformer concepts and suppliers properly, the
permissible temperature rise above the cooling medium (winding-oil gradient), as well as the ambient
temperature, have to be regarded.
mineral oil or
synthetic insulating natural convection flow through
O N A air N natural convection
liquid with fire point cooling equipment and in windings
300°C
A common example:
ONAN/ONAF
The transformer has a set of fans which may be put into service if required at high loading. The
insulating liquid circulation is by thermosiphon-effect only, in both cases.
Measuring principle
During the temperature rise test only , , and can be measured directly. The winding
temperature will be determined indirectly by calculation (resistance measurement). Measuring the
winding temperature, using sensors directly attached to the winding are carried out with fiber optics and
useful, detecting possible hot-spots and predict transformer´s operational life span. A simplified
temperature distribution model is shown in Figure 14.2.1.
Temperature rise measurement 83
= =
( ) =
= =
= = ( )
( ) C =
= 1, 2 =
( ) g =
Short-circuit method
There are several methods to determine
the temperature rise. Because of practical
reasons the short-circuit method has been
established for the determination of
steady-state temperature rises. As seen in
Figure 14.3.1 the principle of short-circuit
connection is applied. During this test the
transformer is not subjected to rated
voltage and rated current simultaneously,
Figure 14.3.1: Principal test connection (three-phase)
but to the calculated total losses, with matching transformer
previously obtained by two separate
determinations of losses, namely load loss
at reference temperature and no-load loss.
84 Electrical Testing Of Power Transformers
The supply voltage is about the same as the short-circuit voltage, which means there are no losses in
the iron core practically. But to obtain the correct top-oil temperature rise, the total losses are required.
That’s why the no-load losses must be simulated in the windings by injecting a current slightly higher
than rated current.
=
= ·
=
+ =
=
=
=
= · · %
=
Preparations
The transformer has to be placed that the cooling system (inlet and outlet) will not be affected by any
objects in the test field. Besides protective devices like the Buchholz relay must be equipped. Any
indication from these devices during the test shall be noted and investigated. All cold resistance
measurements have to be performed before the test, in exactly the same measuring configuration as
the one used for the warm resistance measurement.
Procedure
The purpose of the short circuit-method is to establish several values:
Additionally to the short-circuit method, a winding resistance measurement will be carried out before the
temperature rise test (reference values: and ) and after disconnection of power supply. To get
correct values for the winding resistance after shutdown, the winding temperature variation have to be
extrapolated backwards in time to the instant of shutdown. Therefore the resistance measurement
should be conducted as soon as possible after short-circuit method was applied.
Temperature rise measurement 85
°C
A temperature rise
Short-circuit Total loss injection B settling time
Connection C 3h test time
Rated current injection D 1h test time
Winding resistance winding resistance
DC current E
measurement measurement
A B C D E
As seen in Figure 14.3.2 the whole measurement is divided in several steps. Unless otherwise specified,
the temperature rise test is conducted with the transformer connected on the maximum current tapping.
Acceptance criteria
IEC specifies the maximum permitted ambient temperature with 40°C, and the corresponding permitted
temperature rise of the winding with 65 K. The maximum average winding temperature is therefore:
65 + 40 = 105°C.
= ,
=
=
=
= Figure 14.4.1: Principle test circuit for
temperature rise
Test circuit
Measuring instruments
Yokogawa MV100/MV1000
data acquisition recorder/system
(for thermal sensors)
12 channels (MV100)/
24 channels (MV1000)
data collection over
Ethernet network
external storage media (floppy
disk, zip disk, ATA flash memory)
MV 100 built-in control room
The arrangement is similar to the short-circuit voltage & load loss measurement. The respective measuring
equipment (power analyzer: Yokogawa WT3000, instrument transformers), which is needed for power
observation, has been illustrated before.
88 Electrical Testing Of Power Transformers
The hot-spot temperature ( ) is the hottest temperature of winding conductors in contact with solid
insulation or insulating liquid. The hot-spot winding temperature rise ( ) is the difference between
hot-spot winding temperature and the external cooling medium temperature. It can be determined
through calculation based on the result of the temperature rise test (at rated power <20MVA) or by
direct measurement, as a special test and by agreement between manufacturer and purchaser (at rated
power >20MVA). Usually we are only considering the direct measuring method.
VDE 0532-76-2
Table 14.6.1: Associated Standards
Thermal
= + sensor
=
=
1
=
Dissolved gas-in-oil-analysis
For large mineral oil-immersed power transformers, in which additional flux effects are potential risk
factors, a chromatographic analysis of dissolved gas-in-oil may allow the detection of possible local
overheating. Therefore the gas-in-oil analysis gives another opportunity of hot-spot indication and is a
routine test for transformers with > 72,5kV (IEC 60072-2, Appendix D), conducted by intern or
extern laboratory.
Measurement of cooling losses 89
15.1 General
The value of cooling losses will be determined to get a completion of the overall losses of the
transformer (additionally to winding and core losses). The cooling losses are defined as the power
which is taken by the installed cooling system (fans, liquid pump motor). These losses will be measured
by means of the power analyser “Yokogowa WT3000”.
Figure 15.2.1 shows a simplified extract of the electric cabinet’ circuit layout (only essential parts).
Generally the electric cabinet is a box for electrical or electronic equipment to mount switches, knobs
and displays, to control and monitor auxiliary equipment (e.g. fans, liquid pumps, sensors) of the
transformer. Moreover it has an important function in preventing electrical shock to equipment users
and protects the contents from the environment. In the figure below only fans are pictured exemplary
and for better comprehension.
400V/50H
Electric cabinet
Fans
The power, which is taken by fans and liquid pump motors, is measured with the digital precision power
analyzer “Yokogawa WT3000”. It is switched in between power supply and load and is not part of the
actual circuit layout. Because there is a three-phase power supply different measuring configurations
are feasible. An appropriate setup is the three-wire system, measuring three voltages and three
currents (one for each phase), illustrated below.
U
V
W U
Load
V
W
Yokogawa WT3000
Voltage inputs
Digital Precision Power Analyzer
Current inputs
4 Input terminals available
Accuracy: 0,01% of basic readings
back surface
0,02% of basic power readings
Direct Current Input: up to 30 A
Direct Voltage Input: up to 1000 V
Sound level measurement 91
Today sound emissions, caused by electric installations such as transformers, have to be considered,
especially in populated areas. To protect from these noise inconveniences, electric components are
required to operate within specified noise limits. For this reason knowledge about sound emissions from
the transformer is really important.
VDE 0532-76-10
Table 16.1.1: Associated Standard
16.2 General
Operating transformers generate sound, or more correctly noise. Sources of a transformers sound are:
According to IEC, the transformer has to be energized during the test. The condition of “energized” will
be agreed between manufacturer and customer. It means either no-load or load condition in the
following permissible combinations:
(1) Transformer energized; cooling equipment and any pumps out of service
(2) Transformer energized; cooling equipment and any pumps in service
(3) Transformer energized: cooling equipment out of service, pumps in service
(4) Transformer not energized: cooling equipment and any pumps in service
The measuring circuit for load noise measurement is the same for load loss measurement (see section:
5 Short-circuit voltage & load loss), just like the circuit for no-load noise measurement is similar to no-
load loss measurement (section: 6 Measuring the no-load loss & no-load current). To get the total
sound level, load- and no-load noises have to be sum up.
Test conditions
During the entire measurement the excitation voltage should be sinusoidal and keep its rated
magnitude and frequency. It is important to allow enough time for any DC magnetization to decay
before starting the test, because the remaining DC flux causes odd harmonics in the sound spectrum
and increases the total sound level. Moreover the transformer under test should be placed as far as
possible from reflecting walls, especially parallel to walls, or other equipment to minimize reflections.
Calibration
The measuring equipment has to be checked with a calibrator before and after the test. The test
instruments are not allowed to differ more than 0,3dB (acc. IEC) or 1dB (acc. IEEE).
Test sequence
The A-weighted sound pressure level of the background will be measured right away before and after
the actual transformers sound level test (A-weighted means all hearable frequencies for humans; 20Hz
- 20kHz). The positions of the microphones are therefore the same as for the actual sound level
measurement. The background level is the arithmetic average of these measuring points, if the variation
is 5dB or less (acc. IEC) or 3dB or less (acc. IEEE). Otherwise a certain formula will be used to get the
average background sound level. The actual sound measurement will be conducted similar to
background noise level with transformer permissible conditions (see 16.3).
Acceptance criteria
The sound level measurement is valid if the difference between the first and second background
measurement is below 3dB (acc. IEC).
Measuring instruments
linear operating range: wide dynamic ranges: from calibration accuracy ±0.2dB
80dB adjustable to give 14.2dB(A) to 146dB and 20dB(A)
full-scale readings from to 162 dB (3% distortion limit) conforms IEC Standard
80dB to 130dB in 10dB
steps very wide operating temperature
range and low ambient-
max. peak level: 3dB temperature coefficient
above full scale reading
It is usual in performing system design calculations, particularly those involving unbalanced loadings
and for system earth fault conditions, to use the principle of symmetrical components. This system is
described in positive, negative and zero-sequence impedance values to the components of the
electrical system. For a three-phase transformer, the positive and negative sequence impedance values
are identical to that value described above, but the zero-sequence impedance varies considerably
according to the construction of the transformer.
60076-1
IEC Clause 10.7 “Measurement of the zero-sequence impedance(s) on
three-phase transformers”
Special- or
C57.12.90 other test
IEEE
Clause 9.5 “Zero-phase-sequence impedance”
VDE 0532-76-1
Table 17.1.1: Associated Standards
17.2 General
Calculations in a symmetrical three-phase system are only possible as far as the values of the phases
are simply shifted by 120° and have the same magnitude. Otherwise each phase has to be considered
and calculated separately, which is relevant in case of single short-circuits for instance (impedances
differ from those in a symmetrical network). Generally it is necessary to convert the given unbalanced
three-phase system into a balanced three-phase system. It will be distinguished in:
Corresponding with voltage- and current components, the transformers positive- and negative-
sequence impedances are the same, whereas the zero-sequence impedance can differ significantly,
depending on winding connection and design. An example for an unbalanced three-phase system
consisting of positive-, negative- and zero-sequence system is shown in Figure 17.2.1.
96 Electrical Testing Of Power Transformers
Zero-sequence impedance
After definition the zero-sequence impedance is the impedance measured between phase terminal
(three phases connected) and neutral, which is only possible in star- or zig-zag- connected windings.
The zero-sequence impedance, attributed to each phase, is three times the measured value.
= ·
= ( )
=
Figure 17.2.2: Zero-sequence impedance
Normally it is given as a percentage value of the basic impedance , which can be calculated
as follows:
= · =
= ( )
=
Measurement of zero-sequence impedance 97
It should be noted that the directly measured impedances are not used. For further calculation
equivalent zero-sequence circuits are more preferred. The equivalent circuits and principal test
connections for different neutral- and network conditions are shown in Figure 17.4.1 respectively.
= =
= =
The measurement must be carried out at rated frequency and always with the active part in the tank,
because of its high influence on the zero-sequence impedance. The zero-sequence flux may cause
excessive heating in metallic structural parts such as tank, cover or clamping construction. That’s why
the measuring current must not be higher than 30% of nominal current . Currents up to nominal
current are only permitted for a very short time. The applied voltage must not exceed the phase-to-
neutral voltage, which occurs during normal operation.
98 Electrical Testing Of Power Transformers
Figure 17.4.1: Examples of test connections for zero sequence impedance measurement
Measurement of zero-sequence impedance 99
Test circuit
Measuring instruments
Tettex TMS-PT-581
Voltage transducer
Output voltage: 100 V
0,5, 1, 2, 5, 10, 20, 50,
Measuring range:
100, 200, 400, 800 kV
0,04 % (5-800 kV)
Overall accuracy: 0,1% (1-2 kV)
0,15% (0,2-0,5 kV)
Tettex TMS-CT-582
Current transducer
Test field 1 Test field 2
Output current: 1A 1A
1, 2,10, 20, 40, 100, 1, 2, 5, 10, 20, 50, 100,
Measuring range:
500, 1000, 2000, 4000A 500, 1000, 2000 A
0,005% (40-4000 A) 0,005% (20-2000 A)
0,01% (10-20 A) 0,01% (5-10 A)
Overall accuracy:
0,03% (4 A) 0,03% (2 A)
0,05% (2 A) 0,05% (1 A)
100 Electrical Testing Of Power Transformers
Measurement of the harmonics of the no-load current 101
Generally it is of interest to keep the amount of harmonics as low as possible. For modern power
transformers the harmonic content of the no-load current is actually of little interest, because the no-
load current is only about 0,1 – 0,5 % of the rated current, which does not affect the grid effectively
enough. It could be interesting in case of old transformers. It has to be noted that there are no
applicable Standards according this measurement.
18.2 General
Additionally to the measuring circuit, which is exactly the same as for the measurement of no-load
losses and no-load current (see sections: 5 and 6), a harmonic-analyzer (Fluke 41B) is used in one of
the ammeter circuits. The possibility of voltage distortion should be excluded. Therefore the generators
and matching transformers have to be large enough, obtaining a linear magnetizing characteristic and a
voltage free of distortion.
The measuring is conducted at 90%, 100% and 110% of the transformers rated voltage for each of the
three phases. The voltage is increased gradually from zero to the full values. Switching on directly
would create transient inrushes including DC components, which could saturate the iron core and
increase the measuring uncertainty.
Measurement of the harmonics of the no-load current 103
Test circuit
Measuring instruments
Fluke 41B
Fundamental (phase):
± 2 degrees
1
referred to harmonics measurement
Frequency response analysis measurement (FRA) 105
Frequency response analysis is a major advance in transformer and reactor condition analysis, allowing
you to “see” inside transformers without costly de-tanking. Since the FRA test is used to detect
mechanical movement or damage in a transformer, it is most appropriately used after some event or
condition that has the possibility of causing mechanical movement or electrical damage to the
transformer assembly (e.g. earth quake). Some of the typical scenarios where FRA - measurements
may be used include:
60076-18
“…when a frequency response measurement is required either on-site or
IEC in the factory either when the test object is new or at a later stage. This
standard is applicable to power transformers, reactors, phase shifting
transformers and similar equipment”
Special test
C57.149
IEEE “Guide for the Application and Interpretation of Frequency Response
Analysis for Oil-Immersed Transformers”
VDE 0532-76-18
Table 19.1.1: Associated Standard
19.2 General
The most common cause of failure in the 20-400 MVA transformer group is general ageing of insulating
material. It is therefore desirable to periodically check the mechanical condition of transformers during
their service life, particularly for older units and after significant short-circuit events, to provide an early
warning of impending failure. Such a capability is perhaps just as important as the ability to diagnose
suspected short-circuit failures.
106 Electrical Testing Of Power Transformers
Conventional condition monitoring techniques such as dissolved gas analysis (DGA) are unlikely to
detect such damage until it develops into a dielectric or thermal fault, so a specialist technique is clearly
required for the monitoring and assessment of mechanical condition. Thus the most important
monitoring technique is one that can give the information about insulating condition for ageing or
insulating deterioration products.
Resonance circuits
The image on the right-hand side shows the
complex electrical relationship which exists
between the transformer’s windings, its core,
the tank, the oil, the insulation, and the tank
wall. At the first approximation a transformer
windings can be represented by a complex
ladder network with series inductance and
capacitance as well as the parallel capacitance
to ground. These circumstances lead to
Resonance circuits (RLC - circuits), Series- as
well as Parallel resonance circuits with resonant
properties.
Figure 19.2.1: Illustration of resonance circuits
The transfer function of such networks,
inside the transformer
calculated by the FRA – measurement, shows
a number of poles at the resonance frequency
of the local L and C circuits. A breakdown between the turns or coils of the transformer under test
corresponds to a short circuit of one or more of these local LC - networks. This will result in shifting the
resonant pole to another frequency or the creation of a new pole, which can be interpreted as an
indication of failure in transformer’s structure.
Generally there are four different measuring configurations, which are explained briefly in the following.
The measurements are conducted on each of the transformer HV-windings (A,B,C) with the principle
tapping position.
End-to-end measurement
A frequency response measurement made on a single coil
(phase winding) with the source lead ( ) connected to one end
and the response lead ( ) connected to the other end.
End-to-end (YNd1)
The Frequency Response Analysis is a test measurement made to the winding structures of a power
transformer, performed by an instrument injecting a voltage signal into the top of the selected winding
structure and measuring the voltage signal appearing at the bottom of the same or neighbouring
selected winding structure, calculating the transfer function. This is performed for each winding
structure of the transformer. Values of impedance and phase angle are measured over the given
frequency range and are available as logarithmic graphs, for each of the tested winding structures. This
graph is a representation of the frequency response of the windings at different frequencies (example in
Figure 19.4.1).
Any transformer under test should be completely isolated from any high-voltage source or power
system source. The transformer tank should be grounded. Two of the bushings will be used. The
measurement (most accepted: End-to-end measurement) will be conducted for all windings in
maximum tapping position. The stabilizing winding (if existing) remains and will not be earthed.
Axial collapse
Medium Frequency Range
Localized winding movement
(50 – 500 kHz)
Winding asymmetry
Traditional oil sampling methods requires the use of an equilibrium diagram for evaluating moisture in
transformers and can result in errors in the assessment. The application of conventional equilibrium
charts causes inaccurate results due to the uncertainties during the sampling and water-in-oil
measurement. Together with very long time constants for equilibrium processes, it leads to a very poor
accuracy. The dielectric response method, in contrast, is a very reliable method providing a high degree
of accuracy in assessing the moisture content in the paper insulation.
Moisture in the solid part of power transformer insulation (paper, pressboard) is one of the most critical
condition parameters. Water enters transformers from the atmosphere (breathing, leaky seals) and
during installation and repair. Aging of the oil-paper insulation also increases the moisture level.
Typically, the solid part of the insulation structures holds most part of the water, i.e. 2000 times more
than the oil. Measurement of the water content in oil-paper insulation is therefore a helpful tool for
making an assessment of the ageing of the cellulose and a key factor to ensure transformer’s reliability
and longevity.
20.2 General
Today transformers are not automatically replaced, if they have reached the end of their life span, but
left in service as long as possible. In contradiction to the past, power transformers are operated
nowadays at or above rated power. This accelerates the ageing process of the inner insulation,
particularly of the insulation paper, which cannot be easily replaced.
It is important to have reliable tools for measuring the water content in the oilpaper insulation. This way
unexpected breakdowns can be avoided and the maintenance, repair or replacement can be scheduled
in time. Those faults are often indicated by the oil analysis, which is a proven and meaningful tool.
Dielectric spectroscopy methods are used to determine the moisture in the solid insulation of power
transformers.
Although the results of PDC and FDS methods are comparable and can be transformed from the time
domain into the frequency domain and reversely, both methods have advantages and disadvantages. A
new approach combines both methods. The FDS measurement is replaced by the PDC method in the
low frequency range and the results are transformed into the frequency domain, whereas the FDS is
used for higher frequencies, which can be done rather quickly.
The measuring instrument OMICRON Dirana makes use of this principle and shortens the
measurement time to a minimum. Two input channels for simultaneous measurement of two insulation
gaps make it even faster. The software takes also the conductivity of the oil into account. This makes
the results for aged transformers much more reliable compared to the standard model curves which
were used in the past. The analysis of the gas in oil is a well-proven method of analysis but must be
complemented by efforts to locate any faults. This way important maintenance can be performed in time
to avoid a sudden total failure. The fault location can be successfully performed using modern type test
equipment for resistance, winding ratio, short circuit impedance, capacitances and dissipation factor
(tan ), FRA and PD measurements.
Test object
Measuring instrument
OMICRON Dirana
The OMICRON instrument derives the moisture content in paper or pressboard from properties such as
polarization current, complex capacitance, and dissipation factor. Each of these parameters is strongly
affected by moisture.
The dissipation factor plotted against frequency shows a typical S-shaped curve (see example in Figure
20.4.1). With increasing moisture content, temperature or aging the curve shifts towards the higher
frequencies. Moisture influences the low and the high frequency areas. The linear, middle section of the
curve with the steep gradient reflects oil conductivity.
Measurement steps
For e.g. a two-winding transformer which has been disconnected from the network:
Unlike the conventional equilibrium method, the measurement can be taken right away. There is no
requirement to allow the transformer to cool, or wait until moisture equilibrium between paper and oil
has been reached.
112 Electrical Testing Of Power Transformers
Similar to the Insulation resistance measurement, the determination of the loss factor (tan ) allows
certain conclusions about the condition of the transformer insulation and serves as a reference value for
later measurements, especially for comparisons during operation at later stage.
Routine test
60076-1
> 72,5 kV
Clause 10.1.3: Power transformers – Part 1: General,
IEC
“Measurement of the dissipation factor (tan ) of the
Special test
insulation resistance capacitances”
72,5 kV
Routine test
for class II
transformers
C57.12.90
IEEE
Clause 10.10 “Insulation power-factor tests”
Other test
for class I
transformers
Table 21.1.1: Associated Standards
21.2 General
These special tests include the determination of the winding capacitance with respect to ground and
also the loss factor. The loss factor is defined (by IEC; also known as power factor in IEEE Standards)
as the ratio between the absorbed active power and the absolute value of the reactive power, which
corresponds to tan . In the ideal insulator, the angle would be 90°C as it is purely capacitive and non-
conducting. However in real insulators, there will be some leakage current and resistive losses through
the dielectric. There is no relationship between the loss factor and the transformers withstand (dielectric
test). Moreover its dependence on temperature is substantial and erratic. The various insulation
materials and liquids used in the transformer result in large variations of loss factor as well. That`s why
it indicates to information about the condition of the oil.
114 Electrical Testing Of Power Transformers
The loss factor will be generally measured in special bridge circuits, based on comparing the
capacitance and balancing them. The measuring instrument Tettex MiDAS 2880 does this automatically.
External influences must be reduced by a coaxial cable. In the figures below examples of the measuring
circuit are given.
Accuracy:
± 0,5% of readings ± 0,01% of resolution
(Dissipation Factor)
Accuracy:
± 0,3% of readings ± 0,3 pF
(Capacitance)
Figure 21.3.2: Test connection for HV side Figure 21.3.1: Test connection for LV side
against tank and LV side against tank and HV side
A 10kV voltage at 50Hz is applied to the test object. Depending on the number of windings and whether
there exists a stabilizing winding, the number of measurements will differ. Usually measurements will be
taken of:
The winding of the test object that is not measured and the tank are in each case grounded via the
measuring equipment. If a stabilizing winding exist more measuring combinations are applicable. The
gathered values are relevant for later measurement as reference values.
Measurement of excitation current with 400V 115
22.1 General
This test will be performed with portable instruments (common digital multimeter), carried out at the
jobsite before the transformer will be connected to the power supply. The excitation current, measured
with a 400V supply in the field, allows an evaluation of the transformer’s condition and serves as a final
check. Because the value is already known before dispatch, possible rough damage (internal
winding/core faults) caused by shipping can be detected quickly this way. That’s why the measured
excitation current, which has a fixed value, is also understood as a “fingerprint” for the respective
transformer.
Note: Usually known as “no-load measurement”, the gathered results can be used to obtained further
basic parameters like transformer turns ratio or polarity.
The excitation current is the current flowing into the high voltage winding with the low voltage side open.
This current should be proportional to the no-load acceptance test, regarding the use of test voltages
different from nominal values. Therefor an alternating voltage of 400V will be applied to the high voltage
winding of the transformer in each of its phases (low voltage side open).
Care have to be taken that the core is fully unsaturated before the measuring the excitation current.
Otherwise a distorted value will be measured, leading to false conclusion about transformer’s condition.
To avoid saturation of the core, a slightly higher voltage than system voltage will be applied to the
transformer terminals and will be then reduced to zero. The core should be free of any residual
magnetism after that.
Calibration of the Winding Temperature Indicator (WTI) 117
23.1 General
The Winding Temperature Indicator (WTI) is supposed to indicate the hottest spot in the winding. An
alternative are fiber optic temperature sensors can be imbedded directly into the winding (14.6 Hot-spot
measurement) and are more accurate, which may be worth it, since exact values for hot-spot
temperatures are essential when higher loading is required. They can be used as monitoring device or
turn on additional cooling or activate alarms, as top oil thermometers do.
Bushing CT input
MESSKO Transformer
temperature transmitter (WTI)
23.2 Calibration
As mentioned, the adjustment value for the calibration is calculated by means of the temperature rise
gradient and the bushing current transformer’s rated current, which are known data of the transformer
at rated power. By injecting the rated CT current and by means of a specific curve (thermal replica or
formula) of the heating resistance, the Winding temperature indicator can be calibrated before
installation.
Steps