Techno-Commercial Offer Survey & Design RC
Techno-Commercial Offer Survey & Design RC
Techno-Commercial Offer Survey & Design RC
8 MWp Projects
Daniel Gnanaselvam
30th May 2022
Chennai
Scope of Work
Survey
S.No Deliverables Qty UOM Unit Rate Total Cost
1 Drone Based Survey (Rooftop) 1 site 30,000 30,000.00
Drone Based Survey (Ground Mount) upto 10
2 1 site 60,000 60,000.00
MW
Drone Based Survey (Ground Mount) above
3 1 Site 1,20,000.00 1,20,000.00
10MW – 25 MW
Design
1 MMS Design (Drawings – GA & Fabrication) 1 Set 10,000.00 10,000.00
MMS Design (Drawings & Calculation with STAAD
2 1 Set 25,000.00 25,000.00
report)
Detailed Design (Rooftop)
a. Array Layout with LA
b. Equipment Layout
c. Earthing Layout Min 25,000 /
3 1 Site -
d. String Layout 0.10 /Wp
e. AC SLD
f. DC SLD
g. Project BOQ
Detailed Design (Ground Mount) upto 5MWp
a. Array Layout with LA
b. Equipment Layout
c. Earthing Layout
d. String Layout
4 1 Site 0.10 / Wp -
e. AC SLD
f. DC SLD
g. Project BOQ
h. Other deliverables as per project MDL (to
be finalized as per client requirements)
Detailed Design (Ground Mount) above 5MWp
a. Array Layout with LA
b. Equipment Layout
c. Earthing Layout
d. String Layout
5 1 Site 0.08 / Wp -
e. AC SLD
f. DC SLD
g. Project BOQ
Other deliverables as per project MDL (to be
finalized as per client requirements)
1|P a ge
I&C - Rooftop
Installation & Commissioning (Rooftop – Sheet
roof) upto 200 kWp
a. Unloading of material at site
b. Installation of MMS & Modules
c. Solar Cable Laying
d. AJB Installation
1 e. Inverter Installation 1 Site 1 /Wp
f. ACDB Installation
g. AC Cable Installation
h. Other equipment (WMS, LA, datalogger)
installation
i. Testing – (String voltage & grid voltage
measurement) before charging
Installation & Commissioning (Rooftop – Sheet
roof) above 200 kWp
a. Unloading of material at site
b. Installation of MMS & Modules
c. Solar Cable Laying
d. AJB Installation
2 e. Inverter Installation 1 Site 0.9/Wp
f. ACDB Installation
g. AC Cable Installation
h. Other equipment (WMS, LA, datalogger)
installation
Testing – (String voltage & grid voltage
measurement) before charging
Installation & Commissioning (Rooftop – RCC roof)
upto 200 kWp
a. Unloading of material at site
b. MMS Foundation (0.3x0.3x0.3)
c. Installation of MMS & Modules
d. Solar Cable Laying
e. AJB Installation
3 1 Site 2 /Wp
f. Inverter Installation
g. ACDB Installation
h. AC Cable Installation
i. Other equipment (WMS, LA, datalogger)
installation
Testing – (String voltage & grid voltage
measurement) before charging
Installation & Commissioning (Rooftop – Sheet
roof) above 200 kWp
a. Unloading of material at site
b. MMS Foundation (0.3x0.3x0.3)
c. Installation of MMS & Modules
d. Solar Cable Laying
e. AJB Installation
4 1 Site 1.8/Wp
f. Inverter Installation
g. ACDB Installation
h. AC Cable Installation
i. Other equipment (WMS, LA, datalogger)
installation
Testing – (String voltage & grid voltage
measurement) before charging
2|P a ge
I&C – Ground Mount
Installation & Commissioning (Ground Mount As per scope of work
1
Project) (can be finalized after design)
*GST extra
Payment Schedule
Survey
50 % Advance against Performa invoice
40 % against first submission.
10 % against final acceptance.
Design
30 % Advance against Performa invoice
50 % against first submission.
20 % against final acceptance.
I&C
30 % Advance against Performa invoice
60 % against RA bills
10 % against Commissioning
3|P a ge