Preservation Proceedure (SAMPLE)
Preservation Proceedure (SAMPLE)
REVISION CONTROL
SHEET
Rev
Rev No. Dat Details of Revision
.
e
Shts
.
PRESERVATION PROCEDURE
CONTENTS
2. SCOPE................................................................................................................................... 4
3. DEFINITIONS......................................................................................................................... 4
5. REFERENCE DOCUMENTS.................................................................................................. 5
6. ORDER OF PRECEDENCE................................................................................................... 6
7. RESPONSIBILITIES.............................................................................................................. 6
8. PRESERVATION METHODOLOGY......................................................................................7
PROJECT :
COMPANY :
CONTRACTOR :
SUBCONTRACTOR :
PRESERVATION PROCEDURE
SITE(S) :
5. REFERENCE DOCUMENTS
6. ORDER OF PRECEDENCE
In case of conflict, among any referenced regulations, codes and standards or between any
referenced regulations, codes and standards and technical specifications, CONTRACTOR shall
notify COMPANY of any conflict and confirm resolution of the same in accordance with the
order of precedence specified below:
UAE Statutory Legislation and Regulations inclusive of COMPANY standards and codes of
practice.
Project specifications.
COMPANY Engineering Specifications, Standards, Procedures and HSE Documents.
BP Recommended Standards, Guidance, Practices & Specifications for Engineering.
International Codes and Standards.
7. RESPONSIBILITIES
8.1 SUB-CONTRACTOR Preservation Team
SUB-CONTRACTOR shall nominate a Preservation Coordinator leading a preservation team
and reporting to SUB-CONTRACTOR Commissioning Manager/Engineer. The Preservation
Coordinator shall coordinate with CLIENT preservation team for documentation & guidance for
following the preservation with reference to project requirements. The Preservation Coordinator
is responsible for preservation of project equipment or materials. Preservation team shall consist
of competent and qualified SUB-CONTRACTOR `s Preservation Coordinator, Discipline
Engineers (E&I, Mechanical and Piping), Technicians / labour’s.
Furthermore, the Preservation Team shall establish long term preservation process matrix for
applicable subsystems and tags as follows:
Upon receipt of equipment / materials at the yard / warehouse, the project expeditor shall inform
Preservation Coordinator.
Preservation Coordinator shall prepare and update regularly a spread sheet that indicates arrival
of equipment / materials, description, location & tag number if any
The same list shall be updated by Preservation Coordinator with the required preservation
measures taken including the preservation frequency.
The updated list may be issued to CLIENT`s preservation coordinator for providing the
necessary project specific preservation check sheets if applicable.
SUB-CONTRACTOR Preservation team shall complete the applicable check sheets as per the
preservation frequency and can provide to CLIENT on request.
The preservation check sheets shall be handed over to CLIENT for system update as
required.
The Preservation Coordinator and his team shall be responsible for the preservation activity as
mentioned in the below stages:
Upon receipt of equipment / package at the stores / warehouse.
Movement of equipment / package from the stores / warehouse and stand-by duration (if
applicable) at CONTRACTOR’s yard awaiting installation / hook-up.
During Construction phase at onshore locations.
Transition phase from SUB - CONTRACTOR’s Construction team to CONTRACTOR’s
commissioning team.
During Commissioning phase.
PRESERVATION PROCEDURE
Preparation for load out / sea fastening, during load out and after load out awaiting tow away at
onshore location.
8.2 SUB-CONTRACTOR Project Engineer
Each Project Discipline Engineer who is referred to as the Project Engineer throughout this
document will coordinate activities related to storage and preservation of bulk material, related to
their discipline, procured as part of this project. Project Engineer is also responsible to coordinate
with other departments to get the preservation activities organized and implemented as defined in
this procedure
The preservation activities shall be performed by the store & fabrication yard. Activities shall be
monitored by Project Engineer on regular basis
8.3 SUB-CONTRACTOR Store Keeper (During construction phase until handover)
Storekeeper is responsible to organize the storage locations and preservation consumables for
storage and preservation of materials / equipment at the yard as well as in the warehouse.
With regard to storage of materials, storekeeper shall follow the instruction of Discipline
Engineers and QAQC inspector in order to effectively implement the preservation techniques as
per Manufacturer recommended procedure.
8.4 QAQC Inspector
Ensure that the preservation methods implemented according to the approved procedures
throughout the material receiving, storage, fabrication and installation and until mechanical
completion acceptance by Client. Verify the preservation records prepared and maintained at
different stages as required.
QAQC Inspector along with warehouse personnel and discipline supervisor shall carry out,
periodical survey of equipment and materials as per preservation recommendation provided by
manufacturer or as per this procedure.
8. PRESERVATION METHODOLOGY
Preservation of equipment / package shall be carried out at vendor premises (post FAT (as
applicable) and prior to dispatch from his site) and shall be recorded on vendor preservation log
sheets according to vendor preservation standard procedures.
Preservation check sheets applicable for the project at each stage shall be used after the material
has been delivered.
9.1 Material arrival at SUB-CONTRACTOR /CLIENT Yard Store
SUB-CONTRACTOR receiving section at the ware houses / CLIENT provided storage yard will
carry out the following: -
All items will be inspected upon arrival at SUB-CONTRACTOR warehouse / Yard Store.
For any material that will be stored using hazardous fluids, SUB-CONTRACTOR will obtain
product Material Safety Data Sheet (MSDS) from Supplier.
Store shall provide safe, efficient and orderly laydown areas, warehouses and storage cabinets for
easy access for stocking, retrievals and checking for all materials.
Store shall provide a clean air-conditioned area for storage of Specific material requirement as
per manufacturer instructions.
Store shall provide a safe and environmentally acceptable storage location for all chemicals and
lubrication oil.
PRESERVATION PROCEDURE
Manufacture shall advise on any precautions needed to maintain the packaging in good
condition for the required period.
All delicate surfaces on material shall be carefully protected and painted with protective paint
compound and wrapped to prevent rusting and damage.
All valve sizes are required to be packed in wooden/hard board cases.
All threaded fittings and pipes shall be properly bundled /crated.
All materials shall be preserved as far as possible in the best delivered condition.
All materials shall be protected from atmospheric corrosion or deterioration due to site
conditions during the period between issuance from stores through installation.
All unpackaged materials shall be preserved from the effect of atmospheric corrosion.
9.3 Periodic examination and preservation for the Equipment
Periodic examination and preservation of all equipment shall be performed as described in this
Procedure. If during these examinations any equipment is found to be damaged, if necessary,
Sub-Contractor will notify the equipment manufacturer for proper handling, repair or
replacement procedures. Sub-Contractor shall follow the examination and preservation periods
and activities performed for preservation in accordance with manufacturer’s recommendations
and procedures.
9.4 Storage conditions
9.4.1 Indoor storage
Where "climate controlled environment" storage is called for then, suitable instrumentation
will be used to check the temperature/humidity periodically.
PRESERVATION PROCEDURE
"Indoor" storage is defined as storage area which shall have a roof and with protection from rain,
sunlight and dust and general adverse climatic conditions.
9.4.2 Outdoor storage
Outdoor storage will be as follows: -
Open air storage area under a canopy / shade or covered with tarpaulin sheets
Open air storage area
9.4.3 SUB-CONTRACTOR storage locations
Storage area in Sub-Contractor warehouse, Sub-Contractor yard, Sub-Contractor fabrication shop,
CLIENT provided storage yard and installation location shall be clean and paved or alternatively on
timber blocks/wooden pallets away from construction working areas.
Materials shall be stored in a sheltered environment and protected from moisture, welding, grinding
particles and other construction dust / debris.
If the material needs to be stored at site prior to installation on its final location, Preservation Team
shall ensure the storage location is secure, safe and free from works or activities that might cause
damage to the item.
9. PRESERVATION METHODS (General)
Material delivery should be carefully coordinated with the project schedule to minimize job site-
storage
On receipt of equipment or materials, warehouse personal shall go through the preservation
information and recommendation provided in the manual or catalogue and
maintain the preservation as per manufacturer’s recommendation while storage in the yard.
Upon receipt of materials, care will be taken not to damage the packing, if this has not been
previously opened. Packing shall be opened only during the installation of the items on the platform.If it is
absolutely necessary to remove the packing, then this packing shall be replaced in the same
condition as far as possible and vendor suggested preservation shall be applied.
Packing and preservation provided by manufacturer of equipment shall be kept intact to protect the
equipment against humidity, dust and mechanical strains, which may occur during outdoor storage,
handling and construction. Sensitive equipment shall be stored indoor in a climate controlled storage
area.
Advance information shall be given from the Resources Department to the site supervisors and
Warehouse personnel of any packages / items to arrive and require, dedicated space, special
handling and temperature controlled preservation.
Materials arriving at SUB-CONTRACTOR Ware house / site store will undergo a receipt
inspection and the status of the preservation is recorded. This includes, but is not limited to the
condition of external packaging. Inspection of crated items must have its package reinstated in the
event that the materials have been opened for inspection. Any damage which cannot be corrected by
SUB-CONTRACTOR , then needs to be advised to Manufacturers / suppliers for further action and
rectification.
Bulk materials to be permanently installed in enclosed areas shall be stored in a protected
environment. If an item is to be permanently installed in a climate-controlled environment it shall be
stored in a similar climate-controlled environment.
Structural steel items & Carbon steel piping material shall be stored outdoors on timber blocks or
pallets placed on floor.
Filter elements shall be stored in an enclosed environment with protective covers.
PRESERVATION PROCEDURE
Gasket material, pre-formed gaskets are to be stored flat. Spiral wound gaskets are to be stored
separately in the horizontal (flat) plane. Large spiral wound gaskets are to be stored with a
backing support (i.e. cardboard) in the flat position and should avoid contact with subsequent
gaskets.
All openings, inlets, outlets of equipment like skid units etc., shall be kept blanked off to protect
from entry of foreign matters.
Flange connections of compressors, pumps, valves, etc., shall be closed with dummy closures
and full face neoprene gaskets. Valves may be alternatively provided with plastic covers to
protect flanges and close the opening. All connections shall be plugged, capped or blinded as
applicable, using metallic / plastic plugs or covers.
During Mechanical Completion, Pre-Commissioning and Commissioning, it shall be ensured
that manufacturer recommended preservation techniques for all equipment, are applied.
Sub-CONTRACTOR / Vendor shall identify manual rotating / operation requirements for
valves, impellers, motor bearing etc.
Threaded part of the equipment, piping materials shall be closed by appropriate plugs.
General clean up routine and good housekeeping is a prerequisite for successful execution of
preservation.
Sub-Contractor supplied and installed materials / equipment are mainly Architectural items
including, Insulation, Panelling for wall and ceiling, Doors internal and external, Flooring
material, Painting material, Furniture, Electrical and instrumentation fittings, Electrical and
instrumentation cables, Control panel & Distribution Boards, HVAC package Unit, fans,
dampers, Plumbing & piping material etc.
Monitoring of Preservation activities & checks shall be done Bi- weekly with reference to the
procedures described for each item below.
10.1 Architectural Material
10.1.1 Insulation
Storage location:- Storage area allocated for Sub-Contractor in CLIENT yard.(outdoor)
Insulation material is typically shipped to the jobsite protected by a plastic wrap, plastic bag or
in cardboard cartons. This factory packaging is intended for handling the Insulation in the
manufacturing plant and during transit; it should not be relied upon as job site protection from
the elements unless specified otherwise by the manufacturer.
During storage following precautions should be observed:
Place the package on raised pallets or platforms (100 mm) above ground and store flat.
Unless specified otherwise by the manufacturer, cover the package and pallet with tarpaulin
sheets.
Care to be taken during handling of insulation to prevent damages.
Insulation should always be installed on dry, clean conditions. Follow the manufacturer’s
recommendations regarding product application.
Temporary protection shall be provided for the insulated bulkheads / deck heads where a
potential of repeated damages due to material handling etc. exists. These protections shall be
removed prior to the panel installation / fabric application / cladding application whichever is
applicable.
Since the damage repair is easy compare to any other system, most of the cases the insulation
left unprotected after the installation and before concealing it.
10.1.2 Wall/Ceiling panels
PRESERVATION PROCEDURE
Furniture shall only be installed after all major construction work has been completed and at
the time of it is safe to install or position.
All Stainless steel furniture shall be delivered with a protection film and it shall be maintained
throughout the installation and until handover / if it is safe to remove. If the protective
covering provided by the manufacturer is removed during installation, such protection shall be
reinstated after the installation activity.
Stainless Steel materials shall be protected from moisture / welding / grinding particles
throughout the construction phase to avoid ferrous contamination.
Furniture items shall be installed only when heavy construction works in the room is over.
All installed furniture shall be protected appropriately to avoid any damage or unnecessary
usage.
Furniture usage by unauthorized occupants until the handover shall be strictly avoided or
discouraged.
10.2 Electrical and Instrumentation Material
10.2.1 Electrical and instrumentation cables
Storage location:- Storage area allocated for Sub-Contractor in CLIENT yard.(outdoor)
When handling drums, reasonable precautions should be taken to avoid damage to the cable
and injury to people. Due regard should be paid to the mass of the drum, the method and
direction of rolling and the method of lifting.
Cables shall be stored under cover as far as practically possible. If cables are not fully
protected (with battens or plastic foils for example), storing should be in a protected area and
not weather-beaten.
The cable end should be sealed to prevent ingress of moisture during transport and storage.
End of all cable drums shall be protected with end cap, shrink fit shroud or with tight
insulation tape.
Cable drums should be stored so that the drum flanges do not damage the cables
All cable installed shall be protected from any possible damage due to falling object / hitting
by material movements during other construction activities.
All outdoor installation of cables shall be protected from mechanical damage and direct
sunlight.
10.2.2 Electrical and Instrumentation equipment
Storage location:- Storage area allocated for Sub-Contractor in CLIENT yard.(indoor/outdoor)
Electrical and Electronic equipment shall be stored indoor as far as possible, large items like
HVAC Package Units, Power Panels, DBs, large motors etc. may be stored out door with its
original packing (if safe and permitted by manufacturer recommendation to do so).
Care shall be taken for all the electrical and electronic items stored out door have to be
properly covered to protect from sand, dust humidity, direct sunlight, temperature and
moisture.
During and after installation, all electrical equipment shall be preserved as per the supplier’s
instructions.
All spare cable entrances in panels and boxes shall be plugged with plastic caps or with
appropriate grommets. For electrical equipment with IP rating openings shall be properly
closed with appropriate grommets or plugs.
PRESERVATION PROCEDURE
Cover all glasses in instruments and panel fronts, with minimum 4mm plywood or hardboard
sheet. Care shall be taken to avoid any scratches during such hardboard protection.
Cutting or grinding debris from ferrous steels should not be allowed to settle on stainless steel
items. Necessary segregation and cleaning precautions shall be ensured to avoid contamination.
All open ends of duct / duct elements shall be closed with dust blinds of 100 micron polyethylene
or plywood immediately after fabrication. Stainless steel ducts are not to be stored directly on
floor. They are to be separated from floor with plywood or wooden pallets. Dust blinds and
protection shall remain in place until the installation.
10.4.2 Protection during transport
Proper equipment and unloading methods shall be used to prevent damage to material during
handling operations and transportation.
During transportation of raw materials, manufacturer / Supplier shall follow their preservation
procedure.
Fabricated duct spools preservation shall be maintained throughout, during handling and
transportation to the construction site by taking suitable care during loading and stacking them on
supports. Suitable measures (such as blinding at ends) shall be ensured so that duct spools
protected from the ingress of sand and foreign material.
10.4.3 Preservation of insulation and ducting
Insulation should always be installed in dry, clean conditions. Temporary protection with fire
blanket shall be provided for the insulated ductwork, where a potential hazard of fire or
mechanical damages due to material handling exists. HVAC ducting shall be covered with fire
blanket / GI sheet prior to commencing any hot work at nearby area inside the building. Such
protection shall be the responsibilities of hot work performing department. Periodic surveillance
inspection shall be carried out by Quality control / Fabrication supervisor in order to ensure the
installation is free of damages. These protections shall be removed prior to the cladding
application, where applicable.
Insulation is self-protected by vapour barrier from humidity and dust, therefore no additional
preservation is required for insulated ducting, other than protection from hot work and mechanical
damages when needed.
As far as possible, HVAC Ductwork shall be installed after all intensive construction work like
structural welding, blasting and grinding activities has been completed. In the event of duct
installation to be carried out inside the building prior to any major hot works; such ductworks
shall be protected with fire blankets / GI sheets by the hot work performing department. SUB-
CONTRACTOR shall protect their ducting and other items / equipments against any sand
blasting or painting activities. SUB-CONTRACTOR shall protect their ducts and their other
items/equipments which are installed / stored outside the enclosed building against any hot works.
External surface of ductwork will be left as it is, without any additional protection unless any hot
work or blasting coating activities in the nearby area. Ductwork terminated for later hook- up shall
be protected with a blind at the open end immediately after installation. All protective covers on
inline equipment shall be left in place as long as possible during erection. If any damages found,
to be rectified immediately.
For internal surfaces of HVAC Duct, absorption of moisture and dust shall be minimized during
the idle period by closing of the open ends. Installation personnel shall carry out visual checks
during installation and ensure the ducting are free from oil, moisture and debris. Where necessary
the ducts shall be cleaned before installation. Internal cleanliness of the duct work shall be
randomly verified by QC during the installation stage.
10.4.4 Dampers
PRESERVATION PROCEDURE
PRESERVATION TAG
SYSTEM EQ. TAG NUMBER EQ. DESCRIPTION PRES. INTERVAL
DATE
SIGNATUR
E
END OF THE
DOCUMENT