Prefeasibility Study LIMBE and Markka
Prefeasibility Study LIMBE and Markka
Prefeasibility Study LIMBE and Markka
PRE-FEASIBILITY STUDY ON
REHABILITATION/RECONSTRUCTION
OF RAILWAY BETWEEN
LIMBE AND BORDER (MARKA)
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
In the Master Plan study, rehabilitation and reconstruction of the railway between Limbe and
Border (Marka) was selected as the second priority project in the medium- and long-term
programme. The evaluation of the Master Plan showed several benefits, such as: reduction of
transport cost by connecting to Beira Port; positive economic and social effects for people living
along the railway line between Luchenza and Makhanga who lost the opportunity to sell
agricultural products in big markets such as in Limbe and Bangula and to commute to school
and receive better health care services; reduction of CO2 emissions; and foreign currency
savings by diesel consumption between trucks/trailers and locomotives. On the other hand,
benefits in Mozambique were not considered because there was uncertainty about the intentions
of the GoMZ for reconstruction of the railway section between Vila Nova de Frontela and Dona
Ana, which is an essential part of the Branch Line of the Sena Railway connecting to the
railway between Border (Marka) and Limbe in Malawi.
After submission of the Interim Report to the GoM, the Study Team held Technology
Transfer Seminars in Lilongwe and Blantyre, as well as discussions with relevant authorities in
Mozambique in early November 2011. In the Technology Transfer Seminars, responses from
business, particularly companies involved in export-oriented products and transport business,
were very positive about connecting the railway to Beira Port in order to reduce transport costs
and raise the reliability of railway operation. During discussions with relevant authorities in
Mozambique, their response toward revival of the Branch Line of the Sena Railway was also
very positive, because of the increase of cargo handling capacity of Beira Port after the
completion of dredging works of the main approach channel, and some shipping companies
have already started to operate direct mail liner services between Beira Port and the Middle East
and Asia.
With this background, the Study Team considers that carrying out the Pre-F/S for the
rehabilitation and reconstruction of the railway between Limbe and Border (Marka) is justified.
To establish the rehabilitation plan on the route alignment, the existing route alignment and
right-of-way will not be changed except at the Chiromo washaway section.
As to the improvement of the horizontal alignment between Border and Limbe (see Figure
9-1
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9-1), the alignment at the Chiromo washaway section will be changed to connect the existing
alignment with the new railway bridge (see Figure 9-3). The minimum radius of curvature of
the new alignment at Chiromo washaway section should be at least 300 m to secure an
operation speed of 50 km/h.
An outline of the vertical alignment between Border and Limbe is shown in Figure 9-2. The
section between the border and Sankhulani is almost flat without small horizontal curves,
however, the section from Sankhulani is a rising gradient of average 10‰ with continuous small
curves.
As to the improvement of the vertical alignment between Border and Limbe, the vertical
alignment at the Chiromo washaway section and the section subject to flooding will be changed
(see Figure 9-4). The maximum gradient at these sections should be designed to be less than
16.7‰ according to the design standards of CEAR, but it is recommended to use less than
15.0‰ for the sections to allow a safety margin.
9-2
Limbe
Chapter 9
Bangula
Border Makhanga
Sankhulani
Nsanje
Luchenza
9-3
Pre-Feasibility Study on Rehabilitation/Improvement of Railway between Limbe and Border (Marka)
9-4
9-5
1:1000
1:1000
DL=00.000
50.000
20.000
(橋長)
9-6
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
only as a domestic service. For the convenience of residents along the line in the Study Area, at
least two passenger trains should be operated weekly.
The passenger train will be operated on the section between Limbe and Bangula in the
medium-term plan. Under the long-term plan, the section will be extended to Border (Marka).
(2) Transportation Volume and Number of Trains
As to the yearly passenger volume, it is not based on forecasted demand; the daily average
transportation volume is assumed to be 1,000 passengers per day per direction, that is not based
on the traffic demand forecast. The train formation is set as six passenger coaches as a standard
intercity train, which can carry approximately 1,200 persons. The number of trains required to
transport passengers is assumed to be one train, which makes round trips.
(3) Number of Locomotives Required
The following conditions are assumed for calculating the train operation plan for the
rehabilitated line. The scheduled speed of the freight train is assumed to be 40 km/h judging
from the actual scheduled speed of other existing lines. At the trunk stations where side tracks
will be installed, a stopping time of 2 hours is assumed for changing the train formation,
locomotives, drivers and crews at Border station.
Examples of train diagrams for the medium and long term for operating one train (1 up and
down) are shown in Figures 9-5 and 9-6.
Table 9-4 Number of DLs and Coaches for Passenger Train
9-7
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Civil railway structures comprise a structure to support the train load directly, a structure to
secure the passage for train operation by retaining external pressure, protective facilities to
secure the safe operation of a train and various structures crossing over/under the track, etc.
Upon establishing the rehabilitation/reconstruction plan, the construction work should be
selected from repair, reinforcement, replacement and new construction after inspecting the
soundness of the existing facilities. Effects on the environment should also be fully considered.
As for maintenance work, preventive maintenance has not been conducted sufficiently in
Malawi. Therefore the inspection and maintenance system on the civil structures should be
established to enhance the operational safety in consideration of the preventive maintenance
scheme.
The objectives of defining the standards to be applied to the reconstruction of the railway are
to ensure optimal operating conditions for safety and to keep low maintenance costs. The
construction standards are summarised as follows:
9-8
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Standard 1,067 mm
Curves with 242 m < R < 403 m 1,076 mm
Track gauge
Curves with R ≤ 242 m 1,086 mm
Maximum including side wear 1,092 mm
Minimum radius on existing lines 111 m
Minimum radius on new running lines 244 m
Curves Transition curves Parabolic
Minimum cant 76 mm
Maximum ramp gradient 1 in 480
Existing lines 1 in 44
1 in 60 compensated (=
Maximum gradients New lines (from year 1969 onwards)
including curve resistance)
Stations 1 in 400
Permissible axle load on Design load 13 tonnes
permanent way and Operated at 15 tonnes
structures New line 20 tonnes
Track distance and Structure gauge See below
clearance Track distance ≥4,572 mm
Maximum section speed 50 km/h
Speed
Track distance ≥4,572 mm
Source: CEAR
Source: CEAR
CENTER LINE
OF
TRACK
R8
36
m
m
1524mm
4115mm
3200mm
2699mm
2642mm
2540mm
2134mm
1346mm
978mm
RAIL LEVEL
737mm
864mm
1016mm
76mm
102mm
GAUGE
1067mm
Source: CEAR
9-9
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
STRUCTURE
GAUGE
CENTER LINE
OF
TRACK
m
0m
17
R1
4270mm
RAIL LEVEL
910mm
3050mm
Source: CEAR
4320mm
Figure 9-9 Structure Gauge at Typical Section
CENTER LINE
OF
TRACK
Recommend Building line at
mm
Nearest part of any
70
Pillars,lamps etc.
wayside stations
1
R1
building
4270mm
Max height of platform
Source: CEAR
9 - 10
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
112 112
1 in 30 SUB BALLAST 1 in 30
1 1
TYPICAL CROSS SECTION SHOWING FORMATION ON
FILL AND BALLAST SECTION ON TANGENT TRACK
1 in 30 SUB BALLAST 1 in 30
TYPICAL CROSS SECTION SHOWING FORMATION IN CUT
AND BALLAST SECTION ON CURVED TRACK
Source: CEAR
9.4.2 Earthworks
Earthworks can be carried out economically and easily in comparison with bridge structures
and tunnel structures. It is therefore desirable to use earthworks wherever possible by studying
the alignment of the route plan.
However, the earthworks should consider maintenance and prevention of problems such as
shrinking of the roadbed, flowing out of the slope, collapse of the embankment due to heavy
rainfall and landslide, and mud pumping. As rainfall is especially serious, it is necessary to
construct auxiliary structures such as a drainage system and slope protection. Furthermore, the
earthworks will continuously require maintenance even after completion of the construction
work.
The embankment works will need imported fill, therefore some earth borrow pits are required
alongside the line to minimize the cost of transporting fill material.
(1) Cuttings
There are no cutting sections between Border and Limbe. However, cut batter slopes of 1:1.5
should be applied with intermediate benches at 5.0-m intervals wherever required. For slopes
with high seepage potential and unfavourable rock defects, some slips must be expected.
Horizontal drilled drains will be necessary together with toe buttresses, slope reinforcement and
in some cases mass concrete infill. Well drained slopes can be steepened to some extent, but the
final height/angle relationship will depend on the orientation of defects and the kind of rocks.
(2) Fills
When embankments are reconstructed, fill embankment batter slopes of 1:1.5 with lift
9 - 11
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
benches at 5.0-m vertical intervals should be applied over firm foundation soil bases. Ground
improvement measures will be required where the embankment runs over soft sub-soils such as
will be encountered on low ground.
The embankments between Border and Limbe which should be rehabilitated or reconstructed
are shown in Figure 9-12.
Those between Border and Bangula according to the inventory survey are summarised in
Tables 9-6 and 9-7. The ground height of this section is less than 1.0 m. About 7.2% of the
embankments on the section have some collapses to be repaired (shown as E-). They are
counted as half the amount of required fills, and the washaway sections (shown as W-) are
counted in all of the required fills.
Table 9-6 Fills between Border and Nsanje
9 - 12
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Bangula
E-363
E-362
Section Volume
No. From To of Fills
(km) (km) (m3)
E- 363 64.200 64.350 726
E- 362 63.770 64.200 826
E- 301 44.000 44.080 315
E- 299 43.850 43.960 317
E-301
E-299
E-211
Section Volume
E-170
E-165 No. From To of Fills
E-158 (km) (km) (m3)
E-151 E- 211 34.000 34.200 459
Nsanje
W-11 E- 170 29.800 30.200 1,752
E-148 E- 165 28.800 29.000 312
E- 158 27.400 27.600 313
E- 151 25.538 25.890 479
Section Volume W- 11 25.387 25.538 394
W-7
No. From To of Fills W-6 E- 148 24.850 25.110 286
(km) (km) (m3)
W- 7 15.120 15.160 465
W- 6 15.020 15.060 590
E- 64 8.673 9.000 750
E-64
W- 4 8.420 8.676 2,976
W-4
Border
9 - 13
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
In the section between Bangula and Makhanga, a new embankment should be constructed to
connect the existing railway line to the Chiromo Railway Bridge as shown in Table 9-8. The
average height of the embankment is 3.5 m on the Bangula side and 4.24 m on the Makhanga
side.
In the section between Makhanga and Limbe, the inventory survey was not conducted except
for the flooding area from km 86.7 to 80.0 which was surveyed by MoTPI. In the flooding area,
an embankment with a height of 1 m should be constructed to avoid the track being submerged
with muddy water. Regarding the collapse of embankments on the remaining section, it is
assumed to be half of the rate found on the section between Nsanje and Makhanga. The fills are
summarised in Tables 9-9 and 9-10.
9 - 14
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Section
Ground Volume
Distance
No. From To Height of Fills Remarks
(m)
(km) (km) (m) (m3)
9 - 15
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Section Volume
No. From To of Fills Remarks
(km) (km) (m3)
2 86.700 89.000 317 Flooding area from km 86.7 to km 89.0.
Makhanga
Section Volume
E-380-2 No. From To of Fills
E-380-1 (km) (km) (m3)
E- 380-2 73.900 74.352 19,708
Bangula E- 380-1 73.284 73.670 11,221
Figure 9-13 Fills and Flooding Area between Bangula and Luchenza
(4) Revetment for Protection of Embankment along the New Shire River
In order to prevent scouring of the foot of the embankment from the discharge force of the
New Shire River, it is planned to install revetments between the point where the New Shire
9 - 16
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
River starts to flow along the railway embankment and the Chiromo washaway section (length
of 750 m) using the Type C revetment described in Section 7.2.3.
The earthworks are summarised in Table 9-11.
Table 9-11 Summary of Earthworks
9 - 17
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Limbe
Section
Proposed Bridge
No. From To
Type
(km) (km)
C- 537 195.250 195.288 PC Girder (2x20m)
C- 526 192.800 192.823 PC Girder (24m)
C- 475 177.250 177.274 PC Girder (25m)
C- 443 167.350 167.363 RC Girder (14m)
Luchenza
Section
Proposed Bridge
No. From To
Type
(km) (km)
C- 403 150.500 150.523 PC Girder (23m)
C- 384 145.100 145.124 PC Girder (25m)
C- 347 137.200 137.237 PC Girder (2x19m)
Section
Proposed Bridge
No. From To
Type
Makhanga (km) (km)
W- 14 77.550 77.590 PC Girder (2x20m)
Steel Truss (80m) +
W- 13 73.517 73.900
Bangula PC Girder (5x30m)
Section
Proposed Bridge
No. From To
Type
(km) (km)
B- 139 68.400 68.405 RC Slab Bridge (5m)
B- 134 65.500 65.508 RC Slab Bridge (8m)
B- 124 61.950 61.965 RC Girder (15m)
B- 119 60.100 60.211 PC Girder (3x28m)
B- 63 31.700 31.703 RC Box Culvert (4m)
Section
Proposed Bridge
No. From To
Type
(km) (km)
B- 27 15.450 15.453 RC Box Culvert (3m)
Nsanje
B- 18 11.050 11.053 RC Box Culvert (3m)
B- 15 9.700 9.715 RC Girder (15m)
W- 3 7.330 7.361 PC Girder (30m)
B- 11a 6.150 6.153 RC Box Culvert (3m)
B- 11 5.000 5.020 PC Girder (20m)
W- 2 4.890 4.910 PC Girder (20m)
W- 1 3.800 3.950 PC Girder (5x30m)
B- 6 2.550 2.554 RC Slab Bridge (5m)
Border
9 - 18
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Section Original
Proposed Bridge
No. From To Structure Size Remarks
Type
(km) (km) Type
B- 6 2.550 2.554 Bridge 1 × 4.450 m span RC Slab Bridge (5 m) Structure cracked
W- 1 3.800 3.950 Embankment PC Girder (5 × 30 m) River changed course
Embankment,
railway line and
W- 2 4.890 4.910 Embankment PC Girder (20 m)
2-span bridge washed
away
Structure washed
Not measurable i.e.
away. 20 m opening
B- 11 5.000 5.020 Bridge structure washed PC Girder (20 m)
requires new
away
structure
B- 11a 6.150 6.153 Bridge 1 × 2.500 m span RC Slab Bridge (3 m) No abutment walls
Bridge and approach
W- 3 7.330 7.361 Embankment PC Girder (30 m) embankment washed
away
Both abutments
Not measurable i.e.
collapsed. New 15m
B- 15 9.700 9.715 Bridge structure washed RC Girder (15 m)
opening bridge
away
required
Had walls knocked
B- 18 11.050 11.053 Bridge 1 × 2.700 m span RC Slab Bridge (3 m)
off
B- 27 15.450 15.453 Bridge 1 × 2.550 m span RC Slab Bridge (3 m) Cracked
Source: Study Team
Section Original
Proposed Bridge
No. From To Structure Size Remarks
Type
(km) (km) Type
RC Box Culvert (4
B- 63 31.700 31.703 Bridge 1 × 3.400 m span
m)
B- 119 60.100 60.211 Bridge 4 × 18.450 m spans PC Girder (3 × 28 m)
B- 124 61.950 61.965 Bridge 2 × 7.350 m spans RC Girder (15 m) Pier sunk
RC Slab Bridge (8
B- 134 65.500 65.508 Bridge 1 × 7.600 m span
m)
RC Slab Bridge (5
B- 139 68.400 68.405 Bridge 1 × 4.500 m span
m)
Source: Study Team
9 - 19
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Section Original
Proposed Bridge
No. From To Structure Size Remarks
Type
(km) (km) Type
Embankment height
taken on the edge.
Distance measured
Steel Truss (80 m) +
W- 13 73.517 73.900 Embankment from end of rail
PC Girder (5 × 30 m)
(Makhanga side) and
end of rail (Bangula
side)
Between Makhanga
W- 14 77.550 77.590 Embankment PC Girder (2 × 20 m) Station and Chiromo
Station
Source: Study Team
Section Original
Proposed Bridge
No. From To Structure Size Remarks
Type
(km) (km) Type
Plate Girder (2 × 19
C- 347 137.200 137.237 Bridge 4 × 9.144 m spans
m)
A long span in
2 × 6.096 m spans
C- 384 145.100 145.124 Bridge PC Girder (25 m) between shorter
1 × 12.192 m span
spans
A long span in
2 × 4.600 m spans
C- 403 150.500 150.523 Bridge PC Girder (23 m) between shorter
1 × 13.500m span
spans
Source: Study Team
Section Original
Proposed Bridge
No. From To Structure Size Remarks
Type
(km) (km) Type
A long span in
2 × 3.660 m spans
C- 443 167.350 167.363 Bridge RC Girder (14 m) between shorter
1 × 6.096 m span
spans
A long span in
2 × 6.096 m spans
C- 475 177.250 177.274 Bridge PC Girder (25 m) between shorter
1 × 12.192 m span
spans
A long span in
2 × 4.420 m spans
C- 526 192.800 192.823 Bridge PC Girder (24 m) between shorter
1 × 14.410 m span
spans
A long span in
4 × 7.010 m spans PC Girder
C- 537 195.250 195.288 Bridge between shorter
1 × 10.360 m span (2 × 20 m)
spans
Source: Study Team
9 - 20
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 21
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 22
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 23
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
d) Span less 5m
The RC box culvert is used for original bridges with a span of less 5m.
9 - 24
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Hydraulic/hydrological analysis
Entry of three alternative routes
Calculation of the design flood discharge
Study for the selection of the best horizontal alignment
Calculation of H.W.L.
Study on environmental and social considerations Study on profiles of the bridge and embankment
NG Comparative study on NG
the final route design
and road profile
OK
Decision on bridge construction position and profile of the embankment
9 - 25
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
a situation was not anticipated before the embankment was constructed for rail installation.
It is considered that the large-scale flood of 1997 hit the embankment which had been
weakened by the water overflowing from the Shire River, and washed it away.
Railway embankment
Collapsed embankment
9 - 26
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
upstream of the Shire River flowed from the Makhanga side to the Bangula side of the
embankment area.
c) Study on Bridge Construction Position and Embankment
The best bridge construction position shall be selected from the three alternatives mentioned
below using the results of a comparative study on bridge construction position and embankment.
In the comparison, the three alternatives shall be analysed comprehensively, with bridge length,
cost performance, alignment of embankment, impact on the embankments of the New Shire
River, flood control measures, land acquisition, construction efficiency and impact on the
natural and social environments taken into full consideration, and the best alternative shall be
identified from the results of the analysis.
1) Alternative 1 (Construct a bridge on the alignment of the existing embankment)
A section longer than 360 m of the railway embankment was washed away on the Bangula
side. This alternative is to construct a bridge on the alignment of the washaway embankment.
Since the bridge is to cross a deep section of the New Shire River the bridge will be
significantly affected by flood, a survey is to be conducted to study and confirm the condition of
the river.
2) Alternative 2 (Use the existing road embankment)
This alternative is to construct a bridge on the existing road embankment on the Bangula side.
Although this alternative requires a bridge with a long span length to cross the New Shire River,
it allows flexibility in the selection of spans as part of the construction work can be
implemented on land since it is to be implemented on the existing road embankment.
However, since the position of the bridge will be away from the alignment of the existing
embankment, this alternative requires the construction of a new embankment to connect the new
bridge to the remaining embankment.
3) Alternative 3 (Construct a bridge adjacent to the alignment of the new road)
This alternative is to construct a railway bridge adjacent to the planned Chiromo Road Bridge.
Since piers can only be constructed on the islands, this alternative requires the construction of a
bridge with long spans. Since the bridge position will be further away from the existing
alignment of the embankment compared to that of Alternative 2, this alternative requires the
construction of a new long embankment to connect the bridge to the remaining embankment.
Table 9-18 shows result of comparing the three alternatives mentioned above on the basis of
the results of field reconnaissance and a topographical survey.
d) Comparative Study of Bridge Types
Three bridge types shall be compared for construction at a provisional position selected as the
best in above. While steel bridge structures are used in most cases of railway bridge
construction, concrete bridges can be a potent candidate depending on the span lengths because
of the versatility and low cost of the material. Thus, a concrete bridge shall be considered as the
candidate structure. The scale of a bridge, bridge length and span length shall be decided based
on the results of the hydrological survey and analysis of the survey results, and in consideration
of the bridge width, the railway track shall be at least 4,572 mm apart, and the structure gauge
9 - 27
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 28
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
← To Bangula
To Makhanga
Existing road
Existing road
Alternative 2
Alternative Alternative 1 (existing alignment position) Alternative 2 (using the existing road embankment) Alternative 3 (Matching the new road alignment)
Overview of alternative ・ The existing railway alignment position will be followed. ・ The route will pass on the existing road embankment on the Bangula side. ・ The route will match the new road alignment.
・ An S-curve will be needed to shift the route to the existing road ・ Two S-curves will be needed because the route will be significantly shifted
Alignment of access road ・ The existing alignment is straight and the best horizontal alignment.
embankment position. from the existing railway position, resulting in the worst horizontal alignment.
・ Simple steel truss bridge: 80.0 m.
Characteristics of new bridge ・ 4-span continuous steel truss bridge: 4@90.0 m=360.0 m. ・ 3-span continuous steel truss bridge: 3@76.667 m=230.0 m.
・ 5-span PC post-tensioned bridge: 5@30.0 m=150.0 m.
・ There will be little impact from a flood of the new Shire River because of the
Impact of the new Shire ・ The existing railway embankment is in a condition to receive a significant ・ The existing road embankment on the Bangula side is in a condition to
existing road embankment on the Bangula side and the railway embankment on
River on access road impact from a flood of the new Shire River. receive direct impact from flooding of the New Shire River.
the Makhanga side.
Evaluation of alternative
・ Large-scale bank protection will be required for the existing railway ・ Bank protection will be needed if the existing road embankment is to be ・ Bank protection will be needed for the approach to the existing railway
Flood control measure
embankment on the Makhanga side. retained. embankment.
・ Due to illegal huts on the railway site, there will be problems such as ・ Problems such as resettlement and building removal will not occur as there
・ Same as left.
Environmental and social resettlement and demolition of the huts. are no hut on this alignment.
・ Land acquisition will be needed for the approach to the existing railway
considerations ・ Since the route is on the existing railway alignment, no land acquisition ・ Land acquisition will be needed for the approach to the existing road
embankment, resulting in the largest expropriation area.
will be necessary. embankment.
Target work ・ Bridgework, approach embankment work for 510 m, bank protection work ・ Bridgework, approach embankment work for 450 m, bank protection work ・ Bridgework, approach embankment work for 540 m, bank protection work
(Ratio of costs) (3.33). (1.00). (1.64).
・ Straight with the best horizontal alignment. ・ The best horizontal alignment because the new alignment is approximately ・ The worst horizontal alignment because of the two S-curves.
・ Significant impact from flooding of the New Shire River. straight. ・ Difficulty of construction in a practical manner due to overlapping with the
The highest construction costs because of a large-scale bridge and bank ・ Some impact from flooding of the New Shire River but not as significant as road alignment.
Overall evaluation
protection work. Alternative 1. ・ Much higher construction costs than Alternative 2 because of the high
・ The lowest construction costs because of a small-scale bridge construction costs for the bridge and approach embankment.
× and bank protection work. ×
Source: Study Team
9 - 29
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
・Medium cost performance of the three alternatives. (Construction cost ratio: 1.08)
Cost performance
・The construction of bridge piers in the river is very difficult due to the deep water.
・This bridge type should not be adopted due to the river cross-section reduction
Overall evaluation
×
exceeding the standard value.
Alternative 2: Steel 3-span continuous truss bridge ・A steel truss type is appropriate for long spans and has been adopted the most for past
Structural features constructions.
・The continuous structure offers superior earthquake resistance.
・Since the bridge has no piers in the river, they are easy to construct.
Construction ・Adopting the cantilever method enables the superstructure to be constructed without influence
efficiency from the river.
Maintenance
・Being a steel bridge, maintenance such as recoating is needed.
performance
・Having no pier in the river, it has no impact on the river.
River characteristics
・Being a steel truss bridge, the cost performance is low. (Construction cost ratio: 1.37)
Cost performance
Alternative 3: Steel simple truss bridge + PC 5-span post-tensioned T-girder bridge ・A steel truss type is appropriate for long spans and is often used at the river-crossing point.
Structural features ・A PC-girder bridge can be applied to the existing road embankment.
・Adopting a cable suspended erection method enables the construction of the steel truss bridge
Construction section without influence from the river.
efficiency ・Adoption of an erection girder or support enables the construction of the PC girder bridge
section.
・The truss bridge section is a steel bridge that needs recoating.
Maintenance
・The PC girder bridge section is a concrete bridge that does not need any maintenance.
performance
・Although the cost for the steel truss bridge section is high, the cost for the PC girder bridge
section is the lowest. The overall construction cost is the lowest of the three alternatives
Cost performance
(Construction cost ratio: 1.00).
・For the river-crossing point the truss type is used which is appropriate for long spans and does
not need any construction in the river.
Overall evaluation
・The best cost performance.
・The most desirable alternative in overall evaluation.
Source: Study Team
9 - 30
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 31
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 32
roject for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 33
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
15
JIS: Japanese Industrial Standard
16
UIS: International Union of Railways
9 - 34
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
two types of sleeper: mono-block type PC and two-block type RC sleepers. The former is
recommended for the narrow gauge track, because it is more stable for the track than the latter.
JIS50N UIC54
Source: Nippon Steel Corporation
Figure 9-23 Cross-section of Rails (JIS50N and UIC54)
The Japanese Railway Standard recommends the rail type by line class as shown in Tables
9-20 and 9-21. However, 40 kg rail is now seldom used to construct a new line other than
depots, and so the market price of 40 kg rail is higher than that of 50 kg rail. Therefore, it is
recommended to use 50kg rail for rehabilitation of the line in terms of cost, mechanical stiffness
and durability.
As to the number of sleepers per 25 m rail, 39 sleepers should be provided per 25 m rail
considering an axle load of 20 tonnes, as shown in Figure 9-24.
Table 9-20 Recommended Rail Type
9 - 35
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 36
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
(5) Ballast
Ballast with a nominal depth of 300 mm is to be laid on the track bed to support the sleepers
and rails. The depth is based on the use of an appropriate ballast material and a well-compacted
sub-ballast formation.
The sub-ballast formation slopes so that rain water drains to both sides of the alignment. A
cross-fall of 1:30 will provide satisfactory drainage under heavy rainfall and will minimize the
risk of erosion of the surface of the foundation.
(6) Roadbed
The critical matters for the roadbed are mud pumping, roadbed settlement, slope collapse, etc.
The countermeasures for mud pumping are: a) increment of ballast pressure, b) improvement of
drainage, c) roadbed substitution method, and d) roadbed covering method. As settlement of the
roadbed is caused by soft ground, proper countermeasures should be taken considering the
importance of the line. Slope collapse should be prevented by vegetation, covering with
concrete blocks, etc.
(7) Track Works
Track works by section are summarised in Table 9-22.
Table 9-22 Outline of Track Works
9 - 37
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Station layouts
Legend
: Through track
: Track layout
630
540
480
445
61 m spur BOG Level
Notes
crossing
- Spur has no sleepers to hold rails together.
to Rulwe
- Loop 4 has no sleepers to hold rails together. mission 6m
- Loop 3 at 0+800 has no sleepers to hold rails together. Offices
Railway Warehouse
Workshop
Loop with flyover bridge used for loading coal fuel
stopped functioning when diesel locomotives
Water tower replaced steam locomotives
510
Level crossing
house to Mpepe Station house
school
94.6 m spur
9 - 38
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Admark warehouse
Bangula (km 71+774)
To WFP
Dilapidated
Culvert structures (houses)
i.e. not habitable To Admark
To Railways
Staff houses Offices
343
480
525
585
Station
329
Dilapidated
structures (houses)
i.e. not habitable
505
565
479
479
383
383
314
Station
9 - 39
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
354
292
220
152
231
175
175
9 - 40
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Facilities Description
1) Station office A station office is installed near the entrance for station staff to
work, take a rest or for standby persons.
2) Signalling and telecommunication A signalling/telecommunication equipment room is installed. The
equipment room room contains electrical equipment, signalling/telecommunication
equipment, etc.
3) Ticket window Tickets are sold at ticket offices by station staff. The space of the
ticket window to be constructed will be sufficient to install a ticket
vending machine (TVM) in future.
4) Passenger information system (PIS) and In future, a passenger information system (PIS) and public address
public address system (PA) system (PA) should be installed for passenger convenience.
5) Waiting room A waiting room is installed for passengers. In future, air
conditioners should be installed in the station office and waiting
room.
6) Warehouse A warehouse is installed adjacent to the station building to keep
materials for station business and emergency supplies.
7) Toilet At each station, toilets should be installed adjacent to the station
building.
Source: Study Team
9 - 41
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 42
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Classification Description
Level crossing with automatic barrier Blocks the road traffic automatically when trains pass
Type 1
through the crossing.
Level crossing with manual barrier Blocks the road traffic by a security guard when train
Type 2
pass through the crossing.
Level crossing with alarm Sounds an alarm for road traffic automatically when
Type 3
trains pass through the crossing.
Type 4 Level crossing without safety equipment Has no safety equipment.
Source: Study Team
9 - 43
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Outer Plate
Inner Plate
Wheel Guide
PC Sleeper
9 - 44
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
The current signalling and telecommunication system is not working at all. A new signalling
and telecommunication system should be planned for the line.
The concept of the proposed signalling and telecommunication system is described below.
The signalling system will ensure the safety and efficient control of train operations. The
system will include the following devices and facilities for signalling and train control in a
pattern designed to meet the requirements of long-distance freight transportation.
The signalling system will consist of a combination of signals, interlocking devices, electric
switch machines and track circuits. The electronic logic and interlocking devices will be
installed in the signalling of each station.
(1) Signals
As the signals are to be installed on the ground, the following types are assumed:
a) Fixed type signal
The fixed type signal is a simple metallic panel installed on a concrete pole and used for
indicating stop, speed and special danger.
b) Signals
Coloured light signals will be used to indicate the running condition or whether the section
ahead is clear to train drivers and will consist of green, yellow and red for each signal unit. The
signals will be categorized as follows:
• Home signal: will be installed at the entrance of each station to instruct approaching trains
whether they can enter the station or not.
• Starting signal: will be installed at the departure tracks of each station to give permission for
outgoing trains to depart from the station.
9 - 45
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
• Repeating signal: will be installed where home signals are not easily visible, will repeat the
home signals on the main signals.
• Shunting signal: will be installed to give permission for shunting operation in the stations
where the shunting will be performed, and will include route indicators to show a train
operation destination to the train driver.
(2) Electronic Interlocking Device
Signals and electrical turnout switches will be installed to ensure safe and efficient operations
for leaving, arriving and shunting of trains in the stations. To provide overall control of the
equipment, the electronic interlocking device will be installed to perform electrical interlocking
between signals. The electronic interlocking devices are operated by microcomputer.
(3) Track Circuit
Track circuits will be provided to detect track sections occupied by trains in each station only.
Considering the train operation plan in Section 9.2, sections between stations will form one
block system without a continuous track circuit, and a token-less block instrument system will
be installed outside of the signals to check trains in and out.
(4) Automatic train protection (ATP)
ATP will be provided inside the station to compensate for errors by train drivers. The ATP
will automatically make a warning sign to the train driver when the train is approaching a red
light and then if the driver does not apply brake, the train will be automatically stopped by the
ATP system.
(5) Operation Control Centre (OCC)
The OCC will be installed at Limbe station which is almost the mid point of the mainline in
Malawi, and will be fitted with control and indication panels. The control panel will be used to
operate the turnout switch machines in each station, and will be fitted with telecommunications
equipment including train dispatching telephone and train radio. The indication panel will
schematically display the operating conditions and faults of signalling devices and train
locations between stations.
(6) Proposed Signalling System
The relationship between traffic density and required functions is shown in Figure 9-33. On
the Sena railway, there are not many trains and the traffic density is low. In addition, the train
operation control does not require advanced technology. The "Train Control System for
Secondary Lines using Radio Communications in Specific Area (TCS/SL/RC)” developed by
the Railway Technical Research Institute (RTRI) of Japan for intermittent and continuous
control would be suitable for the line. The system configuration charts of the wayside and
on-board equipment are shown in Figures 9-34 and 9-35, respectively.
The block system based on electronic tokens called COMBAT (Computer and Microwave
Balise Aided Train control system) has been used for secondary lines since the 1980s in Japan,
and has contributed to efficient administration. However, an alternative advanced system needs
9 - 46
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
to be developed because spare parts are no longer available. Therefore, a new train control
system applying the 2.4-GHz band radio has been developed, which does not require a license.
Replacement of the whole system is not required and system migration is simple, because
conventional equipment is used wherever possible. Simultaneously, it is easy to introduce
additional functions and to solve the problems of the conventional system.
Function
Block Speed
control control
ATACS
Moving block ERTMS CARAT
Regional
Continuous
control
ERTMS/ETCS
TCS/SL/RC (Train Level2
control system for
Fixed block secondary lines using
radio communications
in specific area)
Point control
COMBAT
Train density
Source: Railway Technical Research Institute in Japan
Note:
- COMBAT (Computer and Microwave Balise Aided Train control system):
COMBAT is a computer and microwave Balise (composed of onboard transmitter and wayside train detector) aided train control
system which can detect trains without contact. It provides high safety and reliable train operation with low cost on low-density
lines.
- ERTMS Regional (European Rail Traffic Management System-Regional):
The basic aim of the ERTMS REGIONAL concept is to enable cost-saving solutions for signalling on regional and local lines
when renewing or introducing signalling equipment on such lines.
- ATACS CARAT (Advanced Train Administration and Communications System, Computer and Radio Aided Train control system):
ATACS CARAT is being developed to reduce the amount of equipment and permit on-board detection of train locations without
using track circuits.
- ERTMS/ETCS Level 2 (European Rail Traffic Management System/European Train Control System):
ERTMS is a signalling and traffic management system developed with the backing of the European Union. The objective of
ERTMS is to allow interoperability across international borders without the problem of having incompatible signalling systems on
either side. ETCS is the train control element of ERTMS.
9 - 47
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Station Crossing
radio control device Wayside
(optional) radio
Communication network
Central control
device
Radio antenna
Onboard device
ATP with speed check function
Tachometer generator
Source: Railway Technical Research Institute in Japan
9 - 48
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
(1) Outline
In general, a railway telecommunication network is installed along the railway line. The
network is composed of general stations with few transactions and junctions/terminals with
many transactions.
To meet these requirements, the railway telecommunication network consists of a
combination of transmission network deployed along the rail line using voice cables, multiplex
carrier, radio systems, or other forms of transmission media, which are suitable for transmission
between terminals, and voice/data exchange equipment, data processing equipment, etc.
Another feature of railway communication is that it requires a higher degree of real-time
communication and communication accuracy than common carriers as telephone companies in
Malawi, because it handles the operation of trains, rolling stock allocation and freight
movement. For this reason, dedicated transmission lines or direct transmission lines should be
installed on the whole line. The radio communication system between the OCC and trains will
be another requirement unique to the railway operation.
(2) Proposed Telecommunication System
a) Backbone System
A fibre-optic communication system with redundancy, expandability and high
cost-performance should be installed along the whole route as a backbone communication
system.
A Network Management System (NMS) will be installed at the OCC and highly reliable
dedicated circuits will be provided not only for communication sub-systems but also for the
OCC.
b) PABX System
The automatic telephone system is composed of a Private Automatic Branch Exchange
(PABX) and telephones, which will be installed to allow general communications between the
offices and stations for operation and administration of the railway.
The PABX equipment will be installed in the equipment room in the buildings at Limbe,
Luchenza, Bangula, Nsanje and Border stations, and will be able to communicate with common
carriers.
c) Dispatching Telephone System
The dispatching telephone system will be installed to send essential control information for
train operation. Using the dispatching circuits, the dispatching telephone system will connect a
dispatch console to be installed in the OCC and individual telephone sets to be installed in every
station and the maintenance depot. Also, a recording facility will be mounted on the dispatch
consoles to record voice communications on this system.
d) Train Radio System
The train radio system provides a communication link between the OCC and the trains
9 - 49
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
running on the line for the purpose of regulating train operations on a daily basis. In an
emergency, the system is used to provide quick and reliable communication for taking suitable
countermeasures. Possible technologies for the train radio are a dedicated UHF/VHF band or
GSM-R (Global System for Mobile communications - Railway).
The train radio system offers individual calls, group calls, and general telephone calls from
the OCC. The system also enables each train to communicate with nearby stations, if necessary.
By employing the GPS system and a map system, train locations could easily be detected.
e) Clock System
The clock system will be a maintenance-free type with self-adjusting function based on a
GPS receiver.
9 - 50
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
car and the axle load exceed the current vehicle gauge and axle load respectively.
Note: The type DF200 is a diesel electric locomotive equipped with diesel generators and developed for use on the main line of the Japan
Freight Railway Company, to solve the insufficient output power of the former Type DD51 diesel hydraulic locomotive. It has six drive
shafts and adopts induction motors with VVVF control system to realize high acceleration, high speed, and large torque, which resulted in a
quick-response generator brake system. The adoption of induction motors has saved labour for maintenance and diesel fuel.
Source: Kawasaki Heavy Industries, Ltd.
Specifications
Item
DF200 GE Dash 9-40BBW
Maximum Operating Speed 110 km/h 80 km/h
Traction Control System VVVF Inverter Control Electric AC/DC
Adhesive Mass 96 tonnes 160 tonnes
Rated Output 1,700 HP 3,990 HP
Output of Traction Motor 320 KW x 6=1,920 KW n.a.
Dimensions 19,600 x 2,805 x 4,078 mm 23,076 x 3,340 x 4,900 mm
Axle Arrangement BoBoBo BoBoBoBo
Gauge 1,067 mm 1,067 mm
Source: Kawasaki Heavy Industries, Ltd., GE
The depot is used not only for repair, maintenance and storage but also as the base for the
operator. The current depot/workshop is located at Limbe as shown in Figure 9-36 and it should
be improved and extended according the following matters:
• To accommodate future demand
• To manage equipment and operators effectively
• To easily obtain the land for expansion
9 - 51
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Source: CEAR
Maintenance
Inspection/Repair
9 - 52
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
The main facilities of the workshop should be arranged in order to carry out the works
effectively and safely. In the workshop, there are many facilities or inspection and repair and the
arrangement of each facility shall take into account functionality and safety. The sufficient
space shall be considered around the factory building to mitigate the effect of noise and dust.
The following shops should be located in the workshop.
• Carbody jack-up/Repair Shop
• Carbody Panel Shop
• Bogie Shop
• Wheelset Shop
• Bearing Shop
• Engine Shop
• Generator/Motor Shop
• Electric Shop
• Coupler Shop
• Spring Shop
• Air Valve Shop
• Mechanical Shop
• Iron Shop
• Engine Test Shop
• Traverser
9 - 53
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Process of Body
Entrance Body Body Participation
Dismantlement Equipment
inspection mending painting inspection
Vehicle shunting
Main control equipment / Inspection and repair
Brake
Spare Part transportation
part
Power management
Bogie
Wheel set / Inspection and repair
Machine preservation
Main motor
An estimate of the cost of rehabilitating/reconstructing the railway at least cost has been
prepared to enable a decision to be made. However, before making a decision on the actual
investment, a detailed feasibility study including a geotechnical investigation and development
of the preliminary design should be conducted.
9 - 54
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
The unit costs applied in the study are based on the following:
• Various unit cost data provided by CEAR through MoTPI
• Construction costs of ongoing and previous highway and road bridge construction projects
by RA
• Adjusted international rates specific to railway equipment
• Consultant’s past experience with similar projects elsewhere
To derive the quantities of each component of the project, Section 9.3 describes the
earthworks, bridge works, etc. which have been included in the cost estimate.
The quantities have been prepared for the following items:
- Earth works
- Bridge
- Track
- Station
9 - 55
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
- Level Crossing
- Signal & Telecommunication System
- Rolling stock (Diesel Locomotive, Freight Wagon, Passenger Coach)
- Land Acquisition Cost
- Engineering Cost
- Contingency
The engineering cost is the cost for the detailed design and construction supervision, and is
assumed to be 10% of the total construction cost.
Meanwhile, the contingency is an integral part of the expected total project cost and normally
is necessary for all project items involving significant expenditures. For this study, it is assumed
to be 10% of the total construction cost as a physical contingency.
The estimation of construction cost is calculated based on the condition mentioned below.
The construction cost includes 10% contingency and does not include tax in Malawi.
(1) Bridge
Based on the consideration of construction site and structures for Chiromo Railway Bridge
and other small scale bridges, those costs are calculated with comparison to similar construction
projects abroad. An truss bridge is applied for the Chiromo Railway Bridge.
(2) Railway Rehabilitation and Reconstruction
Cost estimation for earthworks and concrete works is calculated based on the previous
contract data in Malawi in consideration of the escalation of construction costs. Cost estimation
for the bridges are calculated with comparison to similar construction projects carried out by
RA and abroad.
(3) Others
The present situation to accomplish the project due to the shortage of fuel, cement and steel
material is clearly difficult due to the delay of two Japanese grand aid road and bridge projects
which are still on going. If such difficult conditions could not be solved, the project cannot be
completed within the budget and in this situation the start of the project could be put into
jeopady. The project costs are summarised in Table 9-28.
9 - 56
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
can be considered and the procurement conditions will be the same as for the superstructure of
the bridges. For RC girder bridges, only the reinforcement bars will need to be imported from
other countries. Fabrication and procurement of Steel trusses shall be made abroad including the
launching equipment.
Table 9-28 Summary of Preliminary Cost Estimate
Unit: US$ million
Section Border– Nsanje– Bangula– Makhanga– Luchenza–
Total
Route Length Nsanje Bangula Makhanga Luchenza Limbe
Item 25.6 km 45.4 km 8.7 km 76.6 km 44.0 km 200.3 km
Earth Works 0.186 0.161 0.789 0.683 0.155 1.974
Bridge 10.232 4.480 17.550 3.911 4.407 40.579
Chiromo Railway Bridge - - 15.350 - - 15.350
Other bridges 10.232 4.480 2.200 3.911 4.407 25.229
Track 13.243 21.764 5.674 36.028 21.486 98.195
Station 0.138 0.275 0.413 0.688 0.688 2.200
Level Crossing 0.000 0.125 0.250 0.000 0.250 0.625
Signal &
0.651 1.205 1.070 2.533 7.126 12.585
Telecommunication System
Sub-Total 24.449 28.009 25.746 43.841 34.112 156.158
Rolling Stock 0.000 0.000 0.000 0.000 46.500 46.500
Diesel Locomotive 0.000 0.000 0.000 0.000 30.000 30.000
Freight Wagon 0.000 0.000 0.000 0.000 13.500 13.500
Passenger Coach 0.000 0.000 0.000 0.000 3.000 3.000
Engineering Cost (10%) 2.445 2.801 2.575 4.384 3.411 15.616
Contingency (10%) 2.445 2.801 2.575 4.384 3.411 15.616
Total 29.339 33.611 30.895 52.610 87.434 233.890
Average Cost per km
1.146 0.740 3.551 0.687 0.930 0.936
excluding Rolling Stock
Source: Study Team
b) Concrete Work
The onsite temperature is high year-round. The maximum daytime temperature only drops
below 30°C for two months. A small quantity of concrete could be cast early in the morning or
at night. However in order to cast the huge concrete volume such as the footing of the
substructure, concrete casting would need to continue during day and night, therefore the
concrete temperature would need to be controlled by a cooling plant or ice maker plant.
c) Culvert Work
The Malawi concrete box type uses concrete pipe which is not a hume pipe, and corrugated
metal pipes as a culvert structure. To prevent the corrosion of corrugated metal pipes, a
bituminous coating is applied to the external surface during road construction between
Chikwawa and Bangula. The Contractors do not recommend the use of corrugated metal pipes
because of theft or vandalism which could cause the culvert to collapse. Therefore the use of a
concrete culvert has been recommended.
d) Embankment Work
The selected material for fill shall be obtained as close as possible to the site and the work
shall be carried out as much as possible in the dry season.
9 - 57
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 58
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
several months. The procurement shall be confirmed before the construction begins from RSA
as well as a third country.
e) Construction Equipment
Major contractors in Malawi have sufficient equipment for the road construction and they can
be used for civil works for railway reconstruction. However they do not have special equipment
for bridge construction. Therefore, special equipment shall be procured from abroad.
g) Labour
Some skilled labour could be procured in Lilongwe or Blantyre. Common labour could be
procured near the site. However specialists for construction of the foundation or superstructure
of the bridge, and reconstruction of track shall be from abroad.
h) Contractor in Malawi
There are more than 10 A-class contractors and they have equipment for road construction
mainly and 25 ton truck cranes and concrete plant.
9 - 59
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
The present maintenance system involves assessing the soundness of the structure by
periodical inspection, identification of deteriorated or deformed parts, detailed inspection of
9 - 60
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 61
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Overall Inspection
Investigation Extraordinary Inspection
C,S B
Judgment of integrity degree
AA,A
Investigation Individual Inspection
Estimation of causes of deformation
Prediction of deformation
Record
The objective of the economic analysis is to analyse and evaluate the viability of
implementing this project from the viewpoint of the national economy. A comparative analysis
of the costs and benefits both in the case of executing the project ("With project") and not
executing the project ("Without project") is carried out. Economic Internal Rate of Return
(EIRR), Benefit and Cost Ratio (B/C Ratio) and Economic Net Present Value (ENPV) are
estimated as the evaluation indexes. The methodologies of these indexes are as follows.
(1) Economic Internal Rate of Return (EIRR)
The EIRR is the discount rate whereby total benefits and total costs calculated into the net
present value become equal. The EIRR is evaluated in comparison with the opportunity cost of
capital. In the analysis, the Social Discount Rate (SDR) of 12% is applied as the opportunity
cost of capital. In Malawi, an SDR of 12% is widely applied in the analysis of infrastructure
9 - 62
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9.9.2 Premises
In this study, the economic analysis is carried out based on the following premises.
(1) Period of the Analysis
The period of the analysis is set at 33 years including the construction (investment) period
from 2017, and 30 years of operation from 2020 to 2049.
(2) Exchange Rate
The exchange rate is assumed to be US$1.00 = MWK165.00 = JPY78.60 as the monthly
average of November 2011. All costs are given in US$.
(3) Economic Price
All figures are based on constant prices in 2011. The economic prices are calculated
excluding transferable items such as various taxes, customs duty and subsidies etc., from the
viewpoint of the national economy. In order to translate market price into economic price,
Standard Conversion Factor (SCF) as 0.85 is applied in the economic analysis referring
previous studies in Malawi.
(4) Inflation
Since it is difficult to estimate the inflation rate during the overall period of the project, it is
not considered in the analysis.
(5) Residual Value
The residual value in the last year (2049) of the analysis is counted as a negative investment
cost. The residual value is calculated based on the life cycle of the facilities stated below.
(6) Life Cycle of Facilities
The following durations are assumed for the life cycle of the facilities, based on previous
studies.
9 - 63
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Item Duration
Bridge (new) 100 years
Bridge (rehabilitated) 50 years
Track 40 years
Signal and telecommunication 25 years
Diesel locomotive 35 years
Freight wagon, passenger coach 50 years
Source: Study Team
9 - 64
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
US$0.03/tonne-km as a variable cost. The annual fixed cost is estimated from the length of the
rehabilitated railway section at a unit cost of US$4,200/km. Furthermore, the cost of
maintaining the railway bridge once every 10 years after completion is added.
(2) Project Benefits
The quantified benefits of Vehicle Operating Cost (VOC) savings and Transport Time Cost
(TTC) savings are estimated in the analysis. The benefits and measures are summarised in Table
9-32.
Table 9-32 Project Benefits
Benefit Measure
Freight by railway ("With project" - "Without project" (tonne-km)) x (unit VOC of railway)
Freight by road ("With project" - "Without project" (tonne-km)) x (unit VOC of road)
VOC saving
Passenger transport ("With project" - "Without project" (vehicle-km)) x
by car and bus (unit VOC of car and bus)
Freight by railway ("With project" - "Without project" (tonne-hour)) x (unit time value)
Freight by road ("With project" - "Without project" (tonne-hour)) x (unit time value)
TTC saving
Passenger transport
("With project" - "Without project" (passenger-hour)) x (unit time value)
by car and bus
Source: Study Team
a) VOC Savings
The VOC savings are calculated by taking the difference in tonne-km between "With project"
and "Without project". The unit VOC for railways was estimated to be US$0.07/tonne-km from
CEAR’s financial statements. The unit VOC for roads was estimated to be US$0.10/tonne-km
from the average freight transport cost. The unit VOCs for cars and buses are US$0.30/km and
US$0.56/km, respectively.
b) TTC Savings
To calculate the TTC savings for road and railway, the unit time value of freight was
estimated to be US$0.03/tonne-km from the average freight value and hourly lending rate. The
unit time value of passengers is US$0.09/hour.
(3) Results of Economic Evaluation
The results of the economic evaluation based on the above conditions are summarised in
Table 9-33. Detail cash flow of economic cost and benefit is shown in Table 9-34.
Table 9-33 Results of Economic Analysis
(Social discount rate = 12.0%)
Total Investment Cost Economic Internal Benefit and Cost Economic Net Present
(in economic price) Rate of Return Ratio Value (ENPV)
(US$ million) (EIRR) (B/C Ratio) (US$ million)
198.81 17.40 % 1.53 72.43
Source: Study Team
9 - 65
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Cost
-10% -5% 0% +5% +10%
Benefit
+10% 18.92% 18.84% 18.77% 18.69% 18.62%
+5% 18.25% 18.17% 18.09% 18.02% 17.94%
0% 17.56% 17.48% 17.40% 17.32% 17.25%
-5% 16.85% 16.77% 16.69% 16.61% 16.53%
-10% 16.13% 16.04% 15.96% 15.88% 15.80%
Source: Study Team
9 - 66
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
As a result, even in the case of +10% increase in the costs and -10% decrease in the benefits,
the value of EIRR exceeds the 12% of social discount rate. It is therefore this project considered
to be economically viable from the viewpoint of the national economy.
The objective of the financial analysis is to evaluate the financial adequacy of the project and
management soundness by the operation body. Financial Internal Rate of Return (FIRR) and
Financial Net Present Value (FNPV) are used as evaluation indexes. The methodologies of
these indexes are as follows.
(1) Financial Internal Rate of Return (FIRR)
The FIRR is the discount rate whereby the totals of revenue and expenditure (investment cost
and O&M cost) converted into the net present value become equal. The FIRR is evaluated in
comparison with the Financial Opportunity Cost of Capital (FOCC). In the analysis, the
Weighted Average Cost of Capital (WACC) serves as a proxy for the FOCC.
(2) Financial Net Present Value (FNPV)
The FNPV is the total net benefit calculated from the net present value of total revenue and
total expenditure.
9.9.5 Premises
9 - 67
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
cost. The residual value is calculated based on the life cycle of facilities stated in Table 13-30.
The Weighted Average Cost of Capital (WACC) is assumed based on the combination of the
above financial sources. Table 9-37 shows the proposed financial plan and WACC of each case.
Table 9-37 Proposed Financing Plan
(2) Expenditure
The expenditure is composed of the investment cost and O&M cost as shown in Tables 9-38
and 9-39
9 - 68
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
(3) Revenue
Annual fare revenue consists of fare revenue and non-fare revenue. According to CEAR’s
financial statements, non-fare revenue is estimated around 5% of fare revenue. The annual
revenue is summarised in Table 9-40.
Table 9-40 Annual Revenue
(Unit: US$ million)
Year Fare Revenue Non-fare Revenue Total
2020 2.47 0.12 2.59
2030 13.09 0.65 13.74
2040 22.15 1.11 23.26
Source: Study Team
Financial Internal Rate of Return Weighted Average Cost of Capital Financial Net Present Value
(FIRR) (WACC) (FNPV)
2.05 % 1.53 % US$ 22.70 million
Source: Study Team
9 - 69
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
9 - 70
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Reconstruction of Railway between Limbe and Border (Marka)
Expenditure
-10% -5% 0% +5% +10%
Revenue
+10% 3.78% 3.29% 2.83% 2.39% 1.96%
+5% 3.40% 2.91% 2.45% 2.00% 1.57%
0% 3.00% 2.52% 2.05% 1.60% 1.16%
-5% 2.59% 2.10% 1.63% 1.17% 0.73%
-10% 2.16% 1.66% 1.19% 0.72% 0.28%
Source: Study Team
9 - 71
Table 9-44 Construction Schedule (Whole Project)
Year 2014 2015 2016 2017 2018 2019 2020 2026 2027 2028 2029 2030
Task Duration
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
(month)
Feasibility Study 12
Decision on Investment 3
Selection of Engineering
3
Consultant
Detailed Design 12
Project for the Study on Development oh the Sena Corridor
Selection of Contractor 6
- Medium-term Project 3
- Long-term Project 3
9 - 72
Execution of Project 72
Start of Service
- Medium-term Project 36
Start of Service
- Long-term Project 36
9 - 73
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Improvement of Railway between Limbe and Border (Marka)
9 - 74
Project for the Study on Development of the Sena Corridor Final Report
Chapter 9 Pre-Feasibility Study on Rehabilitation/Improvement of Railway between Limbe and Border (Marka)
block instrument system should be installed outside of the signals to check the trains in and out.
Regarding compatibility with the signalling system of Nacala Railway where Vale is planning
to construct a new line and rehabilitate the existing line, it is important and inevitable to secure
mutual compatibility.
Similarly, CEAR does not have any dedicated telecommunication system other than mobile
phones which do not cover the whole line. To overcome this situation, a new railway
telecommunication network is to be established by the combination of a transmission network
deployed along the rail line using voice cables, multiplex carriers, radio systems, or other forms
of transmission media, that are suitable for transmission between terminals, and voice/data
exchange equipment, data processing equipment, etc.
(7) Rolling Stock
At present, only 4 out of 10 diesel locomotives (DL) can be made available. It is necessary to
introduce new diesel locomotives. However, the Bombardier MX615 is not currently available. New
locomotives with similar specifications should be procured. The Japanese DF200 type diesel
locomotive would be a candidate diesel locomotive.
(8) Establishment of Railway Maintenance Plan
After rehabilitation or reconstruction of the section, the railway facilities should be
maintained properly by limited human resources and utilized longer to provide safe and stable
railway transport service. To achieve this, a reliable and efficient maintenance plan should be
established.
(9) Economic and Financial Analysis
In the economic analysis, all the values of the evaluation index are in good standard and this
project is considered to be economically feasible from the viewpoint of the national economy.
The results of the financial analysis also indicate that the project will be feasible. To implement
the project, a management plan including actual finance arrangement and financial plan must be
established in future. It is inevitable to arrange governmental subsidies for the infrastructure
portion of the project.
(10) IEE Results
According to the scoping results of the project, executing the project will generate various
positive impacts particularly for the local economy and social lives of local residents along the
railway line. On the other hand, negative effects under the environment and social consideration
are very limited. Mitigation measures for these limited negative impacts should be studied in
detail when the horizontal alignment of the road for improvement will be more concrete under
the feasibility study stage.
9 - 75
CHAPTER 10
ENVIRONMENTAL AND
SOCIAL CONSIDERATIONS
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The Constitution of Malawi 1995 provides a basis for the sustainable development of natural
resources and improved living conditions for people in Malawi. Section 13 (d) of the
Constitution states that the environment should be managed in order to i) prevent degradation of
the environment; ii) provide a healthy living and working environment, iii) accord full
recognition to the rights of future generations by means of environmental protection and iv)
conserve and enhance the biological diversity of Malawi. In line with this, the GoM launched
MGDS in 2006, which is to achieve “strong and sustainable economic growth, building a
healthy and educated human resource base, and protecting and empowering the vulnerable”.
The strategy for sustained economic growth described in MGDS recognises that sustainable use
of natural resources contributes to many of the goals in MGDS.
The World Summit on Sustainable Development held in Johannesburg in 2002, ten years
after the 1992 Earth Summit, called upon governments to develop “National Strategies for
Sustainable Development”. In line with the commitments made at the World Summit, the GoM
prepared the “National Strategy for Sustainable Development” in 2004, which became the basis
for Malawi’s “Sustainable Development Framework for Action”. There are nine thematic areas
of the Johannesburg Plan of Implementation. In the thematic area of “Poverty Reduction”, for
instance, poverty is to be reduced, among others, by transport and public works through:
• Building basic rural infrastructure, diversifying the economy and improving transportation
and access to markets to support sustainable agricultural and rural development
• Implementing transport strategies for sustainable development, reflecting specific regional,
national and local conditions, to improve the affordability, efficiency and convenience of
transportation as well as urban air quality and health and to reduce greenhouse gas
emissions.
The National Environmental Action Plan (NEAP) was also drawn up in 2002 with the
bottom-up involvement of all 27 district assemblies and the participation of all local
communities. The main purpose of NEAP is to integrate the strategies and measures for
environmental protection and management into plans and programmes for the social and
economic development of Malawi. The GoM launched the Malawi Decentralised Governance
Programme in 1998 and appointed Environmental District officers in all 27 districts. In
compliance with the Environmental Management Act 1996 (EMA), the district officers are to
produce District State of Environment Reports and Environmental Action Plans. In response to
NEAP, the National Biodiversity Strategy and Action Plan was prepared to provide a strategic
framework for action for the conservation and sustainable use of biodiversity by the year 2020.
10 - 1
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The legal and policy framework for environmental and social considerations in the transport
sector is summarised in Table 10-1. The details of the Environmental Impact Assessment (EIA)
process, land acquisition and resettlement process, and protected areas in the project area are
discussed in the following sections.
Table 10-1 Legal and Policy Framework in Malawi (1/2)
Law/Policies Description
EIA Process
Environmental Management The policy highlights the areas of high priority for the promotion of sustainable social and
Policy, 1996, Revised in economic development. The policy also provides that an Environmental Mitigation and
2004 Management Plan shall be required for all activities.
Environmental Management Sections 24-26 legislate the EIA Process and administration of EIA (Director of Environmental
Act, 1996 Affairs Department (EAD), Technical Committee on the Environment (TCE), and National
Council for the Environment (NCE)).
Guidelines for Environmental Guideline of the EIA process including: 1) screening process and project brief, 2)scoping
Impact Assessment, 1997 process and 3) undertaking the EIA study.
Land Acquisition/ Resettlement
Land Act Cap 57:01, 1965 The policy defines 1) government land, 2) public land, 3) private land, and 4) customary land.
The policy provides that a landholder is entitled to compensation if the owner’s property
happens to be acquired by the Government for public use. For customary land, compensation
shall be based on the open market value of the land and all permanent improvements on the
land. The policy states that developing activities in fragile ecosystems like wetlands will only
be permitted after the appropriate authority has conducted an environmental impact assessment
study.
Land Act Cap 57:01, 1965 The Act gives the Minister power to acquire customary land needed for a public purpose. The
Act also provides that any person who suffers from loss, damage, or disturbance to his/her land
shall be compensated (Section 28). There is a section to regulate unlawful use or occupation of
any land.
Land Acquisition Act Cap. The Act provides the procedure for land acquisition including: 1) notifying the person from
58:04 whom to acquire the land, 2) paying compensation, 3) assessing fair compensation, and 4)
transferring the land. No compensation shall exceed the current market value of the land.
Town and Country Planning The Act under Part VIII gives power to the Minister to acquire any land, either compulsorily or
Act Cap. 23:01 by agreement, paying such compensation as agreed and determined in accordance with law in
the interest of the implementation of any plan. Any acquisition of land and any payment of
compensation under this Act shall be in accordance with the Land Acquisition Act.
Public Roads Act, Cap. 69:02 The Act provides that the Minister may declare road reserves. Within a road reserve, no
compensation is required if the land is designated as a public road. The owner or occupier of
land in a road reserve is entitled to compensation. The compensation for customary land is
assessed after consultation with the Chief of the area.
Railway Act, Cap. 69:03, The Act gives the Minister power to acquire land for the purpose of a railway. The owner of
1907 land is entitled to compensation for any damage caused by the exercise. Compensation is
agreed with the owner.
Protected Areas
National Fisheries and The policy is to maximise the sustainable yield from the national waters of Lake Malawi,
Aquaculture Policy, 2001 Malombe, Chilwa, Chiuta, the Shire River and so on. The policy also promotes sustainable
utilisation of fish resources in the riverine and adjacent floodplains and wetlands to maintain
biodiversity.
Water Resources Act Cap. This regulates the pollution of public water and granting of water rights. Declaration of
72:03, 1969 controlled area.
10 - 2
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Law/Policies Description
National Water Policy, 2005 The guiding principles include the ‘Polluter-Pays’ principle controlling the pollution of water
resources, and the principle that water allocations shall consider ecosystem integrity and
biodiversity.
The Forestry Act, 1997 The Act gives the Minister power to declare any public land not already reserved for another
public purpose to be a forest reserve (22). The Act also gives the power to any village
headman, with advice of the Director of Forestry, to demarcate on unallocated customary land a
village forest area which shall be protected and managed in the prescribed manner (30).
National Forest Policy of The policy guides the sustainable use of forest resources for improving the quality of life in the
Malawi, 1996 country. The policy mentions the limitation of the Forestry Act (1942) in providing a
mechanism for managing trees and forests on customary land and the lack of clarification of the
rights of individuals and communities to own, manage and utilize indigenous trees growing on
such land.
National Parks and Wildlife The Act declares protected areas of public land to be known as national parks, wildlife reserves
Act, 2004 or nature sanctuaries. The Act also gives the Minister power to declare any area of land or
water to be a national park or wildlife reserve (28 (1)).
National Wildlife Policy, The policy ensures that the Department of National Parks and Wildlife has the responsibility to
2000 take into account the environmental impact assessment procedures when proposals, plans or
projects that are likely to have adverse impacts on wildlife are formulated. There is a section on
the conservation of wetland, which states that wetlands “have high biodiversity and are of
international importance especially for migrating birds”.
Monuments and Relics The Act gives the Minister power to declare a monument or group of monuments or any relic
Arrangement of Sections or collection of relics to be a protected monument or a protected group of monuments or to be a
Cap. 29:01 protected relic or a protected collection of relics.
Health and Safety
Code of Practice for This code of practice is to ensure the highest possible standards of occupational safety, health
Occupational Safety, Health and welfare at all levels within RA.
and Welfare in the Main
Road Sector, 2010 (2nd draft)
Occupational Safety, Health The Act provides for the registration of workplace and duties of employers with respect to
and Welfare Act Cap. 55:07, working environment.
2003
Road Traffic Regulations, The Regulations provide conditions for the use of vehicles and safety.
2000
National Gender Policy, 2000
This policy provides a guiding principle for equal employment opportunities and benefits for
women, men, girls and boys.
Worker’s Compensation Act, The Act provides legislation for compensation for injuries suffered or diseases contracted by
2000 workers.
Employment Act Cap. 55:01 The Act provides legislation for employment contracts, anti-discrimination, and equal
remuneration for work of equal value.
Human Immunodeficiency Virus (HIV)/Acquired Immune Deficiency Syndrome (AIDS)
National HIV/AIDS Policy, The policy provides technical and administrative guidelines for the design, implementation and
2003 management of HIV/AIDS interventions, programmes and activities. It provides guidance on
measures to prevent HIV/AIDS, protection of vulnerable people, and responses to HIV/AIDS
in the workplace.
HIV and Aids Mainstreaming The guideline provides a step by step approach to the HIV/AIDS Mainstreaming Process for
Guidelines for the Public, Public, Private, and Civil Society Organisations.
Private and Civil Society
Organisations, 2007
Roads Authority HIV/AIDS This policy provides employees and employers with sufficient updated information on
Policy HIV/AIDS and promotes effective measures for managing HIV/AIDS.
Source: Study Team
10 - 3
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The Environmental Management Act (1996) Section 24 stipulates that development projects
should be screened to establish major environmental and social considerations which may need
to be addressed before the commencement of project activities. Outlined below are legal
requirements and the process used to screen environmental and social impacts, in line with the
Malawi EIA process.
The EIA process is managed by EAD in the Ministry of Natural Resources, Energy, and
Environment (MoNREE). The implementation of EIA is guided by the National Environmental
Policy 1996, which was revised in 2004, and legislated by the EMA in 1996. Figure 10-1 shows
the EIA process in Malawi.
The first stage in the EIA is a screening process; a licensing authority determines if the EIA is
required. There are two categories of prescribed projects: 1) List A, those projects for which an
EIA is mandatory and 2) List B, those for which an EIA may be required. Table 10-2 lists the
prescribed projects relevant to this study. If the project is a prescribed project, then a project
brief must be submitted to the EAD, but if not, then no further action is required. Together with
advice from TCE, the director of EAD determines whether or not an EIA is required. If the
prescribed project is exempt from an EIA, no further compliance is required and the Director
issues a certificate along with any recommendations for environmental management activities.
If the screening criteria are not satisfied, an EIA must be undertaken.
The second stage is a scoping process in which the principal issues in the EIA are prepared
by the developer and approved by the Director. The scoping discussions between the developer
and EAD are undertaken to ensure that all potentially significant impacts are included in the
study.
After the preparation of TORs in the EIA, the developer then conducts an EIA. When the
draft EIA has been completed and submitted to the director of the EAD, a review process is
undertaken with assistance from the TCE. The EIA report is to be made available to the public
for consultation and a public hearing is mandatory under the EMA. The TCE then submits a
recommendation to the National Council for the Environment for approval. If the EIA report is
approved, the EAD issues a certificate to the developer. If some redesigns are required to
eliminate or reduce adverse impacts, the EIA report must be redone and resubmitted for the
revised project. Depending on the complexity of projects, it takes around two weeks for a
review by the TCE and around two weeks for a review by the National Council.
In Malawi, it is also mandatory to submit an Environmental Management and Monitoring
Plan together with the EIA report.
In addition to this EIA process, RA has prepared a guideline for environmental and social
management in the road sector. This guideline follows the EIA process described in the
Guidelines for Environmental Impact Assessment 1997. It also describes proposed mitigation
measures associated with road development projects.
10 - 4
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Developer prepares
Project Brief & submit
to DEA
Within 15 days
Developer submits
draft EIA Report to
DEA
Within 50 days
Within 25 days
Developer redesigns or
DEA reviews draft
revises draft EIA
EIA Report
Report
Source: Modified by JICA Study Team based on Guidelines for Environmental Impact Assessment (EAD, 1997)
10 - 5
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 6
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
In the case of railway projects, RD in MoTPI is responsible for the EIA process. There are
only two staff in RD at the time of writing this report. Since there is no environmental officer in
this division, the EIA process in railway projects is to be jointly handled by RD and EAD under
MoNREE. The GoM signed a Concession Agreement with CEAR in 1998, and there is a
Director of Engineering and Safety in CEAR in charge of environmental and social
management.
Recommendati
Assist in on for Approval NCE
resettlement
Submit an EIA Study
EMU Environmental Impact
Roads Authority Assessment and Inspection
Dept. of Planning
Dept. of and Design Environmental
Construction Affairs Department
Provide advice TCE
Figure 10-2 Institutional Structure of the EIA Process in the Road Sector
Malawi has a total area of 118,484 m2 (11.8 million hectares), of which 9.4 million hectares
are land. The Land Act 1965 defines three categories of land in Malawi, namely, 1) public land,
which is occupied, used or acquired by the GoM and any other land, not being customary land
or private land; 2) private land, which is owned, held or occupied under a freehold title, or a
leasehold title; and 3) customary land, which is held, occupied or used under customary law, but
does not include any public land. With due consideration of the land problems related to land
acquisition in the past, the Malawi National Land Policy 2002 introduced a new land category
of government land. The new land categories under this Malawi National Land Policy 2002 are
as follows:
• Government Land, which is acquired and privately owned by The GoM and dedicated to a
specified national use or made available for private use at the discretion of the GoM (e.g.,
government buildings, schools, hospitals)
• Public Land, which is held in trust and managed by GoM or TA openly used or accessible
to the public at large (e.g., national parks, forest reserves). This type of public land includes
1) the public land vested in the GoM as a result of uncertain ownership, abandonment and
land that is unusable for one reason or another, and 2) the community’s public land under a
TA, which includes all land within the boundaries of the TA not allocated exclusively to any
10 - 7
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
group, individual or family such as dambos (permanent wetland) and dry-season communal
grazing areas.
• Private Land, which is exclusively owned, held or occupied under 1) freehold tenure, and
2) customary land allocated exclusively to a clearly defined community, corporation,
institution, clan, family or individual, known as customary estate. A leasehold estate can be
created out of Government land or any private land including customary estates.
• Customary Land, which is all land falling within the jurisdiction of a recognised
Traditional Authority, which has been granted to a person or group and used under
customary land. The policy provides customary land with secure tenure by recognising such
customary allocations officially as a customary estate. The property rights contained in a
customary estate are private usufructuary rights in perpetuity.
A Special Law Commission on the Review of Land Related Laws was empanelled in 2003 to
review land related laws. The Special Law Commission recommends, pursuant to Section 133
(b) of the Constitution, that Government land shall be defined as land acquired and privately
owned by the GoM and public land shall be vested in the Republic, not the President as written
in the Land Act 1965.
Customary land accounts for around 66% of all land in Malawi, followed by public land
(21%) and private land (13%) (State of Environment Report, 2002). The statistics compiled by
MoAFS (2010) show that more than 76% of land in the Southern Region of Malawi used by
agricultural smallholders is customary land (Table 10-3). Apart from Chiradzulu District where
freehold land accounts for a majority of land tenure, most parcels of smallholders hold
customary land under the jurisdiction of Traditional Authority. Therefore, it is likely that land
required for the purpose of new construction or rehabilitation of transport projects in the Study
Area may fall under the category of customary land.
Table 10-3 Percentage Distribution of Parcels by Type of Land
(Unit: %)
Area Customary Leasehold Freehold Public
Land
Malawi 77 2 19 1
Southern Region 76 2 20 2
Blantyre City 70 2 26 2
Blantyre Rural 72 1 25 2
Zomba Rural 75 3 20 2
Chiradzulu 38 1 60 1
Thyolo 70 1 28 1
Mulanje 71 4 24 1
Phalombe 91 1 8 0
Mwanza 69 1 28 2
Chikwawa 83 0 14 2
Nsanje 98 1 0 0
Source: NCAL 2006/07, 2010
Note: A parcel of land is a piece of land that has been allocated to a member of a household, whether used for farming
or not. It includes grazing land, woodlot, orchard, and land where the household has built its dwelling unit.
Areas of parcels and plots were measured using GPS equipment.
10 - 8
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The principles and process of land acquisition for the purpose of development projects are
provided by the Constitution, Land Act 1965, Land Acquisition Act, Public Roads Act 1971,
Town and Country Planning Act 1988, Malawi National Land Policy 2002, Forestry Act 1997,
Local Government Act 1998, and Railway Act 1907.
Sections 28 (2) and 44 (4) of the Constitution provide the guiding principles of land
acquisition in Malawi, stating that “no person shall be arbitrarily deprived of property” and
“expropriation of property shall be permissible only when done for public utility and only when
there has been adequate notification and appropriate compensation, provided that there shall
always be a right to appeal to a court of law”.
Section 28 under the Land Act recognises the need for compensation to individuals who
suffer any disturbance, loss or damage as shall be reasonable. Meanwhile, the Land Acquisition
Act provides the procedure for land acquisition, including: 1) notifying the person from whom
land is to be acquired, 2) paying compensation, 3) assessing fair compensation, and 4)
transferring land. Section 6 (1) under this Act provides for the possession of land by the GoM
after expiration of the period specified in the notice given by the Minister. A revision to this
section was recommended by the Special Law Commission to insert a provision that the land
should only be yielded up after compensation has been paid.
The Malawi National Land Policy was formulated in 2002 after reviews of land issues in
Malawi. It highlights that any private land (including customary land) acquired for the benefit of
national development shall be valued and compensated based on the open market value
(commercial rate) paid to the owner for both the land and improvement. The open market value
is defined as “the best price at which the sale of an interest in property might reasonably be
expected to have been completed unconditionally for cash consideration on the day of
valuation”. A reasonable period of valuation is ensured for the agreement of price and terms and
for the completion of the sale by this policy. The policy refutes the notion that customary land
has no value because “land has value as a scarce resource and has other physical and intrinsic
attributes that also contribute to its economic and social value”.
The Public Roads Act provides more comprehensive land acquisition procedures for the road
sector. The Act gives the Minister power to declare the width of road reserves to be 60 m for a
main road, 36 m for a secondary road and a district road, and 18 m for branch roads and estate
roads outside land declared under the Town and Country Planning Act. Part II under this Act
provides the procedure for compensating for use of a road project. For customary land, the
amount of compensation is assessed after consultation with the Chief of the area and based on
the loss suffered by the claimant. For private land, the amount of compensation is based on the
loss or damage suffered by the claimant, which is valued at the valuation date and the market
value of the land is taken into consideration (Section 44-46). If the market value has increased
due to any improvement by the claimant in interest within two years before the valuation date,
10 - 9
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
such increase is disregarded. The Special Law Commission recommended amending Section 44
(2) to assess the amount of compensation for customary land in the same way as private land
(open market value). There is a section which regulates the procedure for claims for
compensation in which the claim should be made in writing to the highway authority liable to
pay such compensation. Since the literacy rate in Southern Malawi is around 62% (Population
and Housing Census 2008), careful consideration should be given to those who cannot write a
claims letter for compensation.
The Railway Act 1907 provides the Minister power to acquire land for the purpose of a
railway. Section 10 ensures that the owner of land is entitled to compensation for any damage
caused by the exercise and this compensation shall be agreed by the owner. The Concession
Agreement between the GoM and CEAR includes a section on land acquisition, in which CEAR
may ask the Minister to implement the procedures for the acquisition of land by the GoM.
The Forestry Act 1997 provides for the licensing of forest land and utilization of forest
produce on customary land, public land, forest reserves and protected areas (Section 45).
JICA Guidelines for Environmental and Social Considerations 2004 require that people who
are required to resettle involuntarily and people whose means of livelihood will be hindered or
lost must be sufficiently compensated and supported by project proponents in a timely manner.
The recommended measures for this compensation include the provision of land and monetary
compensation for losses (to cover land and property losses), supporting means for an alternative
sustainable livelihood, and providing the expenses necessary for the relocation and
re-establishment of communities in the new area. The basic principle for involuntary
resettlement in the guidelines is to avoid involuntary resettlement wherever possible by
exploring all viable alternatives.
To apply the guidelines to the legal context of Malawi, the following resettlement framework
is considered:
• Involuntary resettlement should be avoided wherever possible by exploring all viable
alternatives.
• The study cites Section 28 (2) and 44 (4) of the Constitution as the basic principles for the
process of land acquisition.
• In the Study, the open market value outlined in the Malawi National Land Policy will be a
benchmark to assess private and customary land required for the benefit of development.
• Compensation should be paid by the GoM before the land is yielded up, as recommended by
the Special Law Commission.
• An appropriate grievance mechanism should be established to ensure the proposed project is
launched smoothly.
Table 10-4 illustrates the land acquisition process in a previous project in the road sector,
10 - 10
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
financed by AfDB. The Resettlement Policy Framework for the Malawi Power System Project,
financed by Millennium Challenge Corporation, provides more detailed resettlement procedures.
For instance, the valuation of tree crops and perennial crops shall be based on the market price,
i.e., the current government schedule for valuing crops and trees (e.g., forest tree rates for 2010
and crop prices for September 2010), while residential dwellings are valued on the basis of the
cost of constructing a new replacement structure, which includes the market price of required
construction materials and labour, the cost of sanitation facilities, and the cost of access to water
supply.
The Study Team undertook a field investigation in Nsanje and Thyolo districts from
November to December 2011 to understand the current land acquisition and resettlement
process in the project area. It was found that, although not explicitly stated, the Local
Government Act 1998 provides certain power to district assemblies to conduct the land
acquisition and resettlement process at the district level. According to Nsanje District Assembly,
the first step of resettlement is to conduct an assessment (or a census of Project Affected
Persons (PAPs) and affected assets). The assessment is normally carried out by a Land Officer
of the District Assembly and a Regional Officer for Land and Evaluation, in consultation with
TAs.
Table 10-4 Land Acquisition Process in the Road Project between Zomba and Blantyre (M3)
Process Description
Identification For customary land, the Ministry of Land consults with the TA to identify land and persons for
compensation. For private land, the Ministry confirms the correct registered owners of the land from
the Land Registry.
Notification The Ministry notifies the public in widely circulated daily newspapers of its intention to acquire the
land.
Entitlement Displaced persons who encroach on the project area after the cut-off date (date of commencement of
the census of PAPs within the project area) are not entitled to compensation.
Compensation For the loss of land for property owners including those covered by customary land, the full
replacement value is provided.
Illegal For squatters who have no legal right or claim to the land they are occupying, compensation for loss
occupants of shelter is provided at cull replacement value for structures and relocation to a resettlement site, with
payment of site rent.
Grievance A complaints and grievances mechanism was proposed.
Source: Proposed Rehabilitation of the Zomba-Blantyre (M3) Road: Environmental and Social Impact Assessment Report: Abbreviated
Resettlement Action Plan, 2008
The assessment is based on the market price, whose value shall be determined in consultation
with a District Commissioner, TAs, and the Road Authority, in case of a road project. The
District Commissioner declares the date of this assessment as a cut-off date. The assets for
compensation normally include lands (including agricultural land), houses, forests, and other
assets. After the assessment, consultation with PAPs is carried out, in which many local people
are usually involved in order to ensure transparency in the consultation process and incorporate
their views and opinions (Nsanje District Assembly). Regarding compensation for houses, the
developer normally provides a residential dwelling equivalent to, or better than, the previous
10 - 11
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
JICA Guidelines for Environmental and Social Considerations April, 2010 (hereafter referred
to as “JICA Environmental Guidelines” require that people who are required to resettle
involuntarily and people whose means of livelihood will be hindered or lost must be sufficiently
compensated and supported by project proponents in a timely manner. To apply the guidelines
to the legal and customary context of Malawi, the following resettlement framework is
considered:
• Involuntary resettlement should be avoided wherever possible by exploring all viable
alternatives.
• Where resettlement is unavoidable, the resettlement process should be planned and
conducted as a sustainable development programme, enabling those displaced by the project
to share in its benefit.
• The study cites Section 28 (2) and 44 (4) of the Constitution as the basic principles for the
process of land acquisition.
• In the Study, the open market value outlined in the Malawi National Land Policy will be a
benchmark to assess private and customary land required for the benefit of development.
10 - 12
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The valuation shall be based on the market price of building a new replacement structure
equivalent to, or better than, the previous one for residential dwellings and business
structure, and the current government schedule for trees and crops. Compensation for trees
shall be done either in cash or by replanting trees in case of felling.
• As in the case of Nsanje District, valuations shall be assessed by the District Assembly, in
consultation with community/TAs, executing agents, and financial providers.
• PAPs shall be (a) those who have the formal legal right to land (including customary and
traditional rights recognized under the law of Malawi), (b) those who do not have formal
legal rights to land at the time when the assessment begins but have a claim to such land or
assets (for instance, those who reside in ROW for more than 5 years), (c) those who have no
recognized legal right or claim to the land they are occupying.
• Full replacement cost must be provided wherever possible for those who need to be resettled
involuntarily and those whose means of livelihoods will be hindered or lost (for PAPs of 6.
(a) and (b) above). Measures to achieve this include: i) providing land and money for losses
of residential dwelling and business structure, ii) supporting means for an alternative
sustainable livelihood for those whose income sources or means of livelihood will be lost,
and iii) providing the expenses necessary for the relocation of agricultural crops and forest
resources. For squatters who have no legal and customary right or claim to the land they
occupy, resettlement assistance to relocate to a resettlement site can be provided, if they
occupied the area prior to a cut-off date established by the local government.
• Appropriate consultation with stakeholders and PAPs needs to be conducted in the
following stages:
Consultation with stakeholders during the Pre-F/S stage: consultation with District
Assembly, Working Group Meetings, Consultation with stakeholders in Lilongwe and
Blantyre
Consultation with PAPs during the F/S stage: during the assessment (census), public
hearings
Consultation with PAPs during the implementation and post-resettlement monitoring
Consultation with PAPs includes the dissemination and gazetting of alignment information,
which is required under the law of Malawi, the assessment of affected people/assets, and
public hearing on resettlement plans and mitigation measures. As many people as possible
should be involved in the consultation in order to ensure transparency in the resettlement
process and to incorporate the views and opinions of local people.
• Compensation should be paid by the GoM before the land is yielded up, as recommended by
the Special Law Commission.
• An appropriate grievance mechanism should be established to ensure the proposed project is
launched smoothly.
10 - 13
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
This study applies the Initial Environmental Examination (IEE) level study for the Master
Plan and the IEE level for the pre-Environmental Impact Assessment for priority projects,
which will be selected by the Master Plan. The IEE level study means, “an analysis of
alternative plans, a prediction and assessment of environmental impacts, and a preparation of
mitigation measures and monitoring plans based on easily available information including
existing data and simple field surveys” (“JICA Environmental Guidelines”). At the Master Plan
stage, a methodology of Strategic Environmental Assessment (SEA) is normally required to
assess environmental and social impacts from an early stage, according to the “JICA
Environmental Guidelines”. The SEA is an assessment that is implemented at the policy,
planning, and programme levels and uses a range of “analytical and participatory approaches
that aim to integrate environmental considerations into policies, plans and programmes and
evaluate the inter-linkages with economic and social considerations” (Organization for
Economic Co-operation and Development (OECD), Applying Strategic Environmental
Assessment, 2006). In this study, the proposed nine options, including the zero option, are
regarded as regional transport programmes, and each programme will be evaluated based on the
analytical tools of the SEA. The following approaches are considered at the Master Plan stage:
(1) Screening of Proposed Projects
The screening process is carried out by using the Malawi EIA process and the SEA
methodology. After screening by the EAD guidelines, the proposed projects are briefly checked
to assess whether they are in line with the objectives of the proposed development programme
and if there are clear economic, social, and environmental benefits. The objectives of the
development of the Sena Corridor are to facilitate sustainable economic growth and poverty
reduction in the Study Area by improving the inadequate transport network, and to promote
regional development in Southern Africa. The SEA mainly focuses on the first objective of the
Sena Corridor Development in the Study Area15.
(2) Scoping and SEA for the Master Plan for the Sena Corridor
After the selection of candidate projects by the screening process, the Study applied the SEA
methodology to evaluate qualitatively the environmental, social, and economic impacts of the
regional transport development programme for the Sena Corridor. The main analytical tools of
the SEA used in this study include:
• Assessment of cumulative environmental, economic, and social impacts at the programme
level (including zero option)
• Consideration of alternatives
• Participatory approaches to bring in relevant stakeholders
15
The contribution to regional development in Southern Africa is assessed by other evaluation criteria.
10 - 14
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The main negative anticipated environmental and social impacts found in the Study relate to
air pollution, water pollution, noise, biodiversity, soil erosion and topography, hydrology, and
resettlement. There are also positive impacts expected from the proposed transport projects in
terms of local economy, social infrastructure and social services.
(1) Air Pollution
Air quality is not measured or monitored in Malawi. There is no environmental standard to
regulate air pollution in the transport sector. However, the number of motorized vehicles has
been sharply increasing as evidenced by congested roads in the major cities in Malawi.
According to the State of Environment Report 2002, air pollution occurs countrywide in both
urban and rural areas in Malawi. In particular, diesel vehicles are poorly maintained and make a
10 - 15
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
significant contribution to the levels of air pollution in urban areas. The major pollutants to
roadside air quality by motorized vehicle emissions are dust, gaseous emissions (nitrogen oxides
(NOx), sulphur dioxide (SO2), hydrocarbons (HC), and carbon monoxide (CO)) and
particulates.
However, the traffic volume in the project area is relatively low compared to other regions in
Malawi: traffic volumes of motorised vehicles on M1 (Bangula) and S151 (Seven) in 2006 were
216 veh./day and 37 veh./day, respectively. The average speed of vehicles on unpaved roads in
the project area was about 32-40 km/h. In the proposed projects, the roads in the project area are
designed for an average speed of 70 km/h, which will result in more efficient combustion of
fossil fuels than at present. Some dust will be produced during construction, but no significant
adverse impacts are expected since most of the construction work will be done in open
agricultural/vegetation areas in dispersed settlements. The dust may be more intense during the
dry season in Malawi. It is possible to reduce dust generation to some extent by using
manpower for construction and sealing highly-used earth roads by water application.
Railway is an environment friendly means of transport in terms of air pollution. For the
section between Limbe and Makhanga, diesel locomotives are currently utilised for passenger
trains, which run once a week. Diesel engines emit combustion products such as NOx and
particulate matter (PM). In the designed railway projects, passenger trains will run daily
between Limbe and Nsanje (or Border Station (Marka)). Freight trains from Bangula to Limbe
are expected to resume operation after the rehabilitation of this section, and the trucks that are
currently used to carry sugar from Illovo may be replaced by freight trains, for instance.
Although there may be increased air pollutants emitted by locomotive engines, this increase
may be partially, offset by the change of transport mode from minibus/truck to railway.
(2) Water Pollution
As shown in Section 2.4.3, three major rivers, namely, the Shire River, Ruo River, and
Mwanza River flow into the project area. In addition, two wetlands, Elephant Marsh and Ndinde
Marsh, extend along the Shire River Basin in this region. The GoM launched the Greenbelt
Irrigation initiative to transform the lakeshore, the Shire Valley and other valleys in the 17
major catchment basins into a planted green belt. Many river basins and wetlands are under
pressure from human activity, which may cause a deterioration in water quality. The Shire
Valley and rivers that flow into Lake Chilwa accumulate soil loads, which could change the
channel configuration and increase the risk of flooding. Agricultural and industrial wastes are
the main causes of degradation of water quality.
Groundwater is also an important source of water for the rural population in this region: there
were 14,074 wells in the Southern Region in 2006. Groundwater resources are thought to be
diminishing, especially with the ever-increasing number of wells being dug (State of
Environment Report 2002). In the Lower Shire Valley, groundwater holes tend to have high
levels of salt, causing boreholes to be abandoned.
10 - 16
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
In the transport projects, diesel fuels and other fuel products will be transported and used
throughout the worksite. In addition, solid and liquid wastes generated by the construction work
will be of particular concern where the projects involve crossing rivers and wetlands. If proper
management is not ensured, waste oils could contaminate groundwater and affect the health of
the surrounding population. This potential negative impact can be mitigated by proper siting of
work camps to avoid sensitive areas such as water catchments, and by locating the stockyard for
all construction materials far from rivers, wetlands and drinking water source. According to the
Environmental and Social Management Guidelines in the Road Sector, it is recommended to
stockpile waste materials 15 km away from water resources.
(3) Noise and Vibration
Noise associated with road projects has four main sources: a) vehicle noise; b) friction
between vehicles and road surface; c) driver behaviour; and d) construction and maintenance
work. On the other hand, noise/vibration associated with railway development is generated from
three main sources: a) rolling noise between wheel and rail during normal movement and
braking; b) aerodynamic noise generated by the train pushing air; and 3) engine noise.
The proposed projects do not pass populous cities except Limbe, but people living close to
the roads and railways could be disturbed. To mitigate the potential noise and vibration during
the rehabilitation period, working hours can be set from morning to evening to avoid disturbing
the people. Noise barriers can also be used to reduce noise levels in residential areas.
(4) Protected Areas and Biodiversity
Malawi is endowed with unique and diverse flora and fauna, with over 800 species of fish
and 651 species of birds. The GoM has designated protected areas as a measure to conserve and
protect the unique ecosystem and species. The total protected area covers approximately
180,000 ha or 20% of the total land area (National Biodiversity Strategy and Action Plan 2006).
There are three categories of protected area:
i) Game Reserves, which are protected by the National Park and Wildlife Act 2004 and the
Forestry Act 1997
ii) National Parks, which are protected by the National Park and Wildlife Act 2004 and
guided by the National Wildlife Policy 2000
iii) Forestry Reserves, which are protected by the Forestry Act 1997 and guided by the
National Forestry Policy of Malawi 1996
The National Park and Wildlife Act 2004 gives the Minister power to declare any area of land
or water to be a national park or wildlife reserve (28 (1)). An environmental impact assessment
on wildlife species or community must be conducted with a public hearing, which includes an
account of the species, communities, and habitats affected, and a statement of whether rare,
endangered or endemic species are or may be affected (23 (1), 25 (1)).
The National Wildlife Policy 2000 ensures that the Department of National Parks and
Wildlife is responsible for taking into account the environmental impact assessment procedures
10 - 17
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
when proposals, plans or projects are formulated that are likely to have adverse impacts on
wildlife. The guiding principles state that infrastructure development in national parks and
wildlife reserves shall be undertaken according to the guidelines for such activities. The policy
also requires that road construction, maintenance, and traffic do not inflict damage on wildlife
resources. There is a section on the conservation of wetlands, which states that wetlands “have
high biodiversity and are of international importance especially for migrating birds”.
The area of forests and woodlands in Malawi is estimated at 3,237,000 ha, accounting for
about 34% of the total land area (Food and Agriculture Organization (FAO), 2010). The
Forestry Act 1997 gives the Minister power to declare any public land not already reserved for
another public purpose to be a forest reserve (22). The Act also gives the power to any village
headman, with advice from the Director of Forestry, to demarcate on unallocated customary
land a village forest area, which shall be protected and managed in the prescribed manner (30).
The National Forestry Policy provides guidelines on the sustainable use of forest resources to
improve the quality of life in the country. The Policy mentions the limitation of the Forestry Act
(1997) in providing a mechanism for managing trees and forests on customary land and the lack
of clarification of the rights of individuals and communities to own, manage and utilise
indigenous trees growing on such land.
In the project area, there are three national parks and game reserves: 1) Lengwe National Park,
2) Majete Wildlife, and 3) Mwabvi Wildlife Reserve. There is a Ramsar protected lake, Lake
Chilwa. Figure 7-3 shows the locations of the protected areas along the Lower Shire River.
The Lengwe National Park, for instance, was established to conserve the northernmost
population of Nyala antelope in its range in Southern Africa. The number of Nyala was found to
be in the low hundreds by the Wildlife Society of Malawi in 1999. Rare, endangered, and
endemic mammal species in this park were listed as follows: Rhynchocyon cirnei-shirensis (a
subspecies of chequered elephant shrew endemic to Malawi), Cercopithecus albogularis
(Nchima monkey), Tragelaphus angasi (Nyala), Neotragus moschatus (a particular subspecies
of Livingston’s Suni, which occurs in Lengwe and has a very restricted range) and Hippotragus
niger (Sable antelope, the Lengwe population may be a subspecies restricted to Malawi and
eastern Zambia). For birds, Apalis ruddi caniviridis (a subspecies of Rudd’s Apalis),
Francolinus sephaena zambesia (a subspecies of Crested Francolin) and Nectarinia veroxii (the
Grey Sunbird, confined to Lengwe within Malawi) are regarded as important species within the
park.
The current park plan for the Lengwe National Park includes two separate systems of zoning,
namely: 1) the delineation of compartments for ecological management based on the landscape
classification and, 2) the designation of zones for public use and development according to a set
of established categories. The park plan specifies five categories of zone to separate public use
zones from development zones within the park. The zoning categories include: 1) special areas
(relatively small sites designated to protect unique, unusual or otherwise important biotic,
10 - 18
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
abiotic or cultural features), 2) wilderness areas (relatively large tracts of undisturbed land
intended for aesthetic recreational experience and conservation of biological diversity), 3)
semi-wilderness area (relatively undisturbed but accessible land designated primarily for public
use, 4) resource use zones (areas where controlled consumptive use of wild resources is
permitted, 5) utility areas (sites for management and visitor purposes).
In general, the faster access to the National Park brought by transport development projects
poses a serious risk of escalated poaching activities, solid wastes from tourists, and pressure for
wildlife resources. Although the current National Parks seem to be effectively managed by the
zoning process, further reviews of the park management plan and conservation measures may be
necessary when a transport development project is planned.
There are currently 23 gazetted forest reserves in the project area (Table 10-6).
Table 10-6 Gazetted Forest Reserves as of June 2010
10 - 19
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The section between Chikwawa and Mwanza (S136) passes through 106.7 km2 of the
Thambani Forest Reserve. The improved access to commercial sites in Chikwawa may cause
deforestation and a threat to the forest ecosystem of the Thambani Forest Reserve. To mitigate
this adverse impact from the road development project, ROW can be minimized for the road
section through the Reserve. The clearance of trees along the road should be carried out in an
environmentally friendly way, i.e., by cutting instead of bulldozing, and without using chemical
and fertilizer. Further investigation on the ecosystem in the Thambani Forest Reserve may be
required before undertaking the road project in this section.
Wetlands are not protected
areas under Malawian law.
Most of the wetland areas are
under customary land tenure
and accessed openly, except
at Lake Chilwa, which is
protected by the Convention
on Wetlands, internationally
known as the Ramsar
Convention.
Lake Chilwa has a wide
water catchment area,
comprising Phalombe
District, most of Zomba
District, and 43% of
Machinga District (Figure
10-3). The lake and wetland
contain water most of the
time, but the water has
completely dried up three
times in the last 100 years.
Lake Chilwa has up to 164
species of birds, of which 41 Source: Lake Chilwa Wetland Management Plan, 2001
species are Palearctic migrant Figure 10-3 Biodiversity and Hot Spots
species that migrate from Europe through the Rift Valley. The Shire River flows through an
area of swamp called Elephant Marsh. The marsh is bound on the east by the Thyolo
escarpment and on the immediate west by the alluvial floodplain of the river. This marsh was
around 150 square miles in area and about 10 miles wide, as shown in Figure 10-4.
Following the flooding of the Shire River in 1997, the marsh area became larger. Elephant
Marsh is not a protected area by law in Malawi and some farmers have cultivated this area
10 - 20
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
openly. However, the wetland plays an important role in biodiversity as a bird sanctuary and as
a destination for migrant birds (a draft “Malawi State of Environment and Outlook 2010” and
interviews with the Department of National Parks and Wildlife in Lengwe National Park).
Ninety-eight bird species were recorded in an inventory survey of birds in Elephant Marsh done
by the Cambridge Expedition to Malawi July-August 1991. The Palearctic birds, which are
migrant birds from the Palearctic region including Europe, North Africa and all of Asia except
its southern region, come from Europe to Elephant Marsh through the Rift Valley during the
European winter.
10 - 21
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
In addition, some inter-African migrant birds were recorded in Elephant Marsh as shown in
Table 10-7. A more recent inventory survey was conducted in August 2008 on the lower side of
the Kamuzu Truss Bridge (Chiromo) and found one species of inter-African migrant bird and
several resident birds. Birdlife International listed 32 bird species occurring in Malawi as
Globally Threatened Species (Red List Category).
Table 10-7 Examples of Migratory Bird Species from Elephant Marsh
Species Name Scientific Name Status
Little Bittern Ciconia Ciconia Palearctic migrant
Ruff Philomachus pugnax Palearctic migrant
Greenshank Tringa nebularia Palearctic migrant
African Skimmer Rynchops flavirostris Inter-African migrant
Mascarene Martin Phedina borbonia Malagasy migrant
Source: Data adapted from a bird checklist by Cambridge Expedition to Malawi July-August 1991;
Perspectives on wild birds in Malawi in relation to avian bird flu, by W. O. Mgoola
The National Parks and Wildlife Act (2004) provides a classification of protected species,
some of which are also classified as game species for the purpose of hunting. Based on the
inventory surveys in 1991 and 2008 in Elephant Marsh and a book detailing the 650 bird species
in Malawi, the Study Team compiled a list of Red Listed species that may exist in Elephant
Marsh in Table 10-8. Although Elephant Marsh is not a protected area, its biodiversity and
importance as a destination for migrant birds need to be taken into consideration when
undertaking a development project in this area (interview with the Department of National Parks
and Wildlife). For instance, a developer may need to take measures to reduce the negative
effects on biodiversity in terms of noise, water pollution, and air pollution, as discussed above.
Other possible mitigation measures to protect biodiversity in this area are to minimize water
crossing and reclamation, design a narrower ROW, and minimize the felling of trees in which
birds nest.
Table 10-8 Possible Existence of Red Listed and Protected Species in Elephant Marsh
English Scientific Red Status Description in “The Elephant Kamuzu
Name Name List Birds of Malawi” Marsh Truss
Bridge
(2006) (1991) (2008)
Madagascar Ardeola idea EN Non breeding visitor The earliest photographed
Squacco Heron from Madagascar on 18 April 2002 in
Elephant Marsh
Long-crested Lophaetus Resident Widespread species Recorded
Eagle* occipitalis
African Rynchops NT Moved from the Most regularly seen on the Recorded Recorded
Skimmer flavirostris Shire River to the Shire River.
lake shore
Spotted Eagle Bubo Resident The most common and Recorded
Owl* africanus widely spread
Lilac-breasted Coracias Mainly resident Widespread and fairly Recorded
Roller* caudatus common
Sources: The Birds of Malawi, Françoise Dowsett-Lemaire and Robert J. Dowsett (2006); Data obtained from the Department of
National Parks and Wildlife.
Notes: EN=Endangered, NT=Near Threatened. * means a protected species by law in Malawi.
10 - 22
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The number of hippo has fallen significantly since the peak of 234 counted in 1998 in the
Lower Shire (Hippo and Crocodile Counts in the Lower Shire, 1998). The Crocodile and Hippo
Census in the Shire River in 2009 estimated the number of hippo in the Lower Shire River at 38,
a drastic decline from the 1998 level (Table 10-9). The conflicts between wildlife and humans,
increasing cultivation in the Shire River, and poaching are the main reasons for the decline of
hippo in Elephant Marsh. Some 754 crocodiles were recorded in 1998, but due to conflicts with
human activities and hunting, the number had decreased to 464 by 2008. There used to be some
800 elephants in Elephant Marsh when Livingstone travelled through this area, but it is thought
that the elephants moved either to the Majete Wildlife Research or dispersed to Mozambique
along the Ruo River. No elephant has been recorded in this area in recent times.
The improved accessibility around the marsh might lead to increased poaching activities and
encroachment. As the marsh is not only rich in biodiversity but also a source of human
livelihood, an appropriate wetland management plan, as illustrated in the case of Lake Chilwa,
is desired.
Table 10-9 Hippo and Crocodile Counts in the Lower Shire River
Hippo Crocodile
Area Sightings Density Population Sightings Density Population
(Animal/km) Estimate (Animal/km) Estimate
Chikwawa–Illovo 16 0.76 25 98 4.7 150
Illovo–Chiromo 2 0.03 13 29 0.6 234
Chiromo–Nsanje 0 0 0 63 1.5 80
Total 18 0.26 38 190 2.27 464
Source: Hippo and Crocodile Counts in the Shire River, National Parks and Wildlife Research Unit, 2009
10 - 23
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
landslides and slope failures, and there is now an urgent need to stabilize the slopes along the
railway line.
In the proposed railway rehabilitation projects, the risk of landslides and slope failures will be
minimized by replanting vegetation and trees on cleared areas and slopes, using slope retaining
techniques, improving the drainage system, and conducting a community education programme
to protect slope vegetation along the railway line.
Photo 10-1 M1 Section for Climbing Lane Photo 10-2 Section between Sandama and
Thekerani
Table 10-10 Occurrence of Landslides and Slope Failure between Limbe and Makhanga
Year Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Total
2008 3 4 0 0 0 0 0 0 0 0 1 4 12
2009 2 4 0 0 0 0 0 0 0 0 0 1 7
2010 1 1 0 0 0 0 0 0 0 0 0 2 4
2011 2 1 6 0 0 - - - - - - - 9
Source: CEAR
(6) Hydrology
As shown in Section 2.4.3, the roads and railways in this study are within the drainage area of
the Lower Shire Valley and cross several rivers/streams. The section between Makhanga–
Bangula passes through the Shire River and Elephant Marsh, while S152 receives regular
torrential rains from the escarpment, which occasionally cause inundations on the road and
10 - 24
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
disrupt transport. Roads and railways that intersect river/streams generally have the potential to
modify the natural flow of overland surface water by increasing the water flow in the roadside
drains. To prevent severe impacts on the hydrological environment, water crossings should be
minimized. Other mitigation measures include providing of relief culverts, and techniques for
reducing water speed such as riprap, settling basins, and infiltration ditches.
(7) Resettlement
The proposed road and railway projects follow the existing alignments, except for the
disconnection section at Chiromo on S151. The population density in the project area varies by
district from 92.3 persons/km2 in Chikwawa to 342.5 persons/km2 in Thyolo, as shown in Table
2-19 and Figure 2-19.
a) Upgrading of S152 between Thabwa and Seven
The current width of S152 is around 6 m and the additional land required for upgrading work
is around 9-10 m in width or 0.6 km2 (10 m×59.1 km). Most houses on this road are located
outside of ROW, but this area is a populous area of Thyolo. Photo 10-4 shows the houses along
the S152 road. On the other hand, there are some agricultural fields illegally occupying ROW in
this section. These illegally extended agricultural fields result from the shortage of available
arable land and increasing population in this region. The illegally occupied fields need to be
relocated for the upgrading.
10 - 25
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 26
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Photo 10-5 Banana Field Close to Railway Line Photo 10-6 Market near Makhanga Crossing
Photo 10-7 Market at Thekerani Station Photo 10-8 Maize field between Bangula and Nsanje
10 - 27
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
(8) Socio-Economy
The average poverty headcount (percentage of people below the poverty line) in the Study
Area is 61.1%, 9 points higher than the national average of 52.4%. The lowest levels of annual
household expenditure are found in Thyolo District (MWK69,195.6) and Phalombe District
(MWK70,530.4). The unemployment rate is highest in the urban areas such as Blantyre City
(21.3%) and Zomba Municipality (15.9%), although some rural areas have unemployment rates
of more than 10% (Blantyre Rural, Thyolo). The deterioration of the livelihoods of people in
Chiromo and along the railway line between Luchenza and Makhanga is described in details in
Chapter 2.
The Study Team undertook a brief field survey on in February 2011 and June 2011 to
research the social and economic impacts of Chiromo washaway in 1997 and along the railway
line between Thekerani and Luchenza. The objectives of this survey were to understand the
level of poverty in terms of infrastructure and other socio-economic issues. The methodology
for this survey was based on key informant interviews due to the limited time at the site. The
interviews for the impact of the washaway were conducted with a local person residing near
Kamuzu Truss Bridge and local people near the Thekerani and Sandama stations. The interview
for local infrastructure was conducted with a head teacher at Makhanga Primary School. The
results of this survey are as follows:
a) Impact of Chiromo Washaway
• Before the washaway, there was a lot of traffic using the road with more than 50 cars,
around 100 bicycles, 5-6 trucks, and 2 buses each day. There were two bus routes: a)
Blantyre–East Bank (S152 via Chikwawa)–Nsanje and b) Blantyre–Thyolo–Nsanje. In
addition to passenger traffic, trucks and trains used to carry cash crops such as cotton and
tea, and food crops such as bananas and oranges from Thekerani in Thyolo District.
• After the washaway, life became very difficult. For instance, to go to Nsanje, it costs MWK
100 by boat and a bicycle taxi costs MWK70, placing a significant burden on living
expenditure.
• Since the washaway, railway freight arrives only once a week, and as a result, food supplies
have fallen significantly. Food such as bananas and oranges is not produced in this area, so
the people depend on rail transport from Thekerani in Thyolo District for their livelihoods.
• School access became difficult after the washaway. In the past, people use to go to the
primary school at Makhanga by train, but now there is no train to commute to school, and
life has become very difficult. Access to a hospital is not difficult since there is a hospital
located nearby.
b) Impact of Chiromo Washaway at Thekerani and Sanaama Stations
• The livelihoods of people near Thekerani Station became worse after the washaway; in
particular, transporting agricultural products such as banana, cassava, and orange from this
area became very difficult. In the past, there were two passenger trains and one freight train
10 - 28
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
every day between Nsanje and Blantyre, but there is now only one mixed train a week. The
train fares to Makhanga, Luchenza and Limbe are MWK200, 200 and 300, respectively. The
railway is much cheaper than minibus16, but due to the lack of availability of trains, some
people travel by bicycle. There are schools and hospitals near Thekerani, but there is no
well, energy, or cell phone coverage.
• After the major washaway, the living conditions of people near Sandama Station worsened
due to the decrease of income sources. For instance, one businessman in Sandama used to
transport charcoal, lemon and banana to Limbe and brought fishes and food groceries from
Limbe, but he could not work as a businessman after the washaway and was forced to
change job from businessman to ticket collector at the station. In the past, he used to go to
school or hospital (3 km away from Sandama) by train, but must now go on foot. A mixed
train come to Sandama once a week, but is often too crowded to get on board.
c) Local Infrastructure between Makhanga and Chiromo
A mapping exercise was used to identify the location of local infrastructure and protected
areas in Makhanga and Nsanje. The map drawn during the interview with the head teacher at
Makhanga is shown in Figure 10-5. The results of the mapping exercise were as follows:
• There is now only one school in this area (Makhanga Primary School). There used to be a
primary school in Chiromo but it was closed.
• A health post is located near the Makhanga Research Station.
• There are four wells in this area, located at a) the primary school, b) the Makhanga Research
Station, c) Mwanabvumbwe village, and d) Mkolimbo village. Water near the Ruo River
contains a lot of salt and therefore some boreholes are not used.
• There is no cemetery or protected area such as a forest reserve along the railway line and the
road.
• There are some irrigated areas along the Ruo River. The Kalonga Irrigation Programme has
been implemented near Elephant Marsh.
• There are no job opportunities except for governmental institutions such as the school.
There are no factories.
• There is a market along the railway line.
• The water level rises to the railway line two or three times a year, normally between January
and March. No cars can use the road when there is a flood, and occasionally water covers
the railway line.
The above interviews revealed that the washaway in 1997 had a significant impact on the
local economy and social services in Chiromo and along the railway line. Due to the
disconnection, local people living in the eastern side of the washaway section need to spend
MWK100 to go to Nsanje to sell their products. Agricultural products from Thekerani, on which
the local people living in the eastern side of the washaway section are heavily dependent,
16
The minibus fare costs MWK700 between Limbe and Luchenza,
10 - 29
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
became very limited after the washaway. Since there is no road nearby, local people along the
railway line could not sell their agricultural products as occasionally as before, thus reducing
their sources of income.
10 - 30
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10.4.3 Screening of Proposed Projects using the EAD Guidelines and the SEA Methodology
As described in Section 10.1, a proposed project needs to be screened according to a list for
prescribed projects. If the project is under List A, an EIA is mandatory and the developer needs
to prepare a project brief. If the project is under List B, an EIA may be required and the
developer needs to prepare a project brief. Table 10-11 shows the necessity of submitting a
project brief to the EAD. The EAD will evaluate the project brief and determine whether an EIA
is required.
All proposed projects are expected to contribute to the objectives of the Sena Corridor to
facilitate sustainable economic growth and alleviate poverty in the Study Area. Since all
projects are under List B, less significant environmental and social impact is expected. The
detailed economic, social, and environmental impacts of the proposed projects will be analysed
in the next scoping process.
Table 10-11 Screening of Proposed Projects
A scoping checklist for each proposed project is provided in the following tables, which is
10 - 31
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
based on the analysis of Section 10.5. Both negative and positive impacts are evaluated in a
scoping matrix. The non-project option is also evaluated to compare the impact of the proposed
project.
Table 10-12 Reconstruction of S151 between Makhanga and Bangula
Construction
Non-project
Operation
Phase
Phase
Impacts
1 Resettlement/land acquisition B B D
2 Local economy such as employment and livelihood, etc. B+ B+ A
3 Land use and utilisation of local resources C C D
4 Social institutions such as social infrastructure and local decision-making institutions B B D
Social Environment
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, fauna and biodiversity B B B
19 Meteorology D D D
20 Landscape B C D
21 Global warming D D D
22 Air pollution B B D
23 Water pollution B D D
24 Soil contamination B C D
25 Waste B D D
Pollution
10 - 32
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition B B D
2 Local economy such as employment and livelihood, etc. B+ D D
3 Land use and utilisation of local resources C C D
4 Social institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
15 Groundwater D D D
16 Hydrological situation D D D
17 Coastal zone D D D
18 Flora, fauna and biodiversity C D D
19 Meteorology D D D
20 Landscape B B D
21 Global warming D D D
22 Air pollution B B D
23 Water pollution B D D
24 Soil contamination B C D
25 Waste B D D
Pollution
10 - 33
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition A A D
2 Local economy such as employment and livelihood, etc. B+ B+ B
3 Land use and utilisation of local resources B B D
4 Social institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, fauna and biodiversity B B B
19 Meteorology D D D
20 Landscape D D D
21 Global warming D D D
22 Air pollution B B D
23 Water pollution B D D
24 Soil contamination B C D
25 Waste B D D
Pollution
10 - 34
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Impact
Phase
Phase
1 Resettlement/land acquisition B B D
2 Local economy such as employment and livelihood, etc. B+ B+ D
3 Land use and utilisation of local resources C C D
4 Social institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
14 Soil erosion B B+ B
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, fauna and biodiversity C C D
19 Meteorology D D D
20 Landscape D D D
21 Global warming D D D
22 Air pollution B B+ D
23 Water pollution B D D
24 Soil contamination B C D
Pollution
25 Waste B C D
26 Noise and vibration B B D
27 Ground subsidence C C D
28 Offensive odour B C D
29 Bottom sediment B D D
30 Accidents B B+ B
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicate a positive impact
Source: Study Team
10 - 35
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition B B D
2 Local Economy such as employment and livelihood, etc. B+ A+ A
3 Land use and utilisation of local resources B B D
4 Social Institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
14 Soil erosion B B+ B
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, fauna and biodiversity B B D
19 Meteorology D D D
20 Landscape B B D
21 Global warming D D D
22 Air pollution B B+ D
23 Water pollution B D D
24 Soil contamination B C D
Pollution
25 Waste B C D
26 Noise and vibration B B D
27 Ground subsidence C C D
28 Offensive odour B C D
29 Bottom sediment B D D
30 Accidents B B+ B
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicate a positive impact
Source: Study Team
10 - 36
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition B B D
2 Local Economy such as employment and livelihood, etc. B+ B+ A
3 Land use and utilisation of local resources C C D
4 Social Institutions such as social infrastructure and local decision-making institutions B B D
Social Environment
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, fauna and biodiversity B B B
19 Meteorology D D D
20 Landscape C C D
21 Global warming D D D
22 Air pollution B B+ D
23 Water pollution B D D
24 Soil contamination B C D
Pollution
25 Waste B C D
26 Noise and vibration B B D
27 Ground subsidence C C D
28 Offensive odour B C D
29 Bottom sediment B D D
30 Accidents B A+ B
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicate a positive impact
Source: Study Team
10 - 37
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition B B D
2 Local economy such as employment and livelihood, etc. B+ B+ D
3 Land use and utilisation of local resources C C D
4 Social institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, Fauna and biodiversity C C D
19 Meteorology D D D
20 Landscape D D D
21 Global warming D D D
22 Air pollution B B+ D
23 Water pollution B D D
24 Soil contamination B C D
25 Waste B C D
Pollution
10 - 38
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact
1 Resettlement/land acquisition B B D
2 Local economy such as employment and livelihood, etc. B+ B+ B
3 Land use and utilisation of local resources C C D
4 Social Institutions such as social infrastructure and local decision-making institutions D D D
Social Environment
14 Soil erosion B B+ A
15 Groundwater C C D
16 Hydrological situation B B D
17 Coastal zone D D D
18 Flora, Fauna and biodiversity C C D
19 Meteorology D D D
20 Landscape D D D
21 Global warming D D D
22 Air pollution B B+ D
23 Water pollution B D D
24 Soil contamination B C D
Pollution
25 Waste B C D
26 Noise and vibration B B D
27 Ground subsidence C C D
28 Offensive odour B C D
29 Bottom sediment B D D
30 Accidents B B D
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicate a positive impact
Source: Study Team
10 - 39
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Based on the results of the scoping matrix for the proposed projects of nine transport network
alternatives, the Study attempts to evaluate the three alternative transport network options for
the Master Plan on the development of the Sena Corridor, using the SEA methodology at the
IEE level. The option of no investment on the Sena Corridor (zero-option) is also evaluated for
comparison. As explained in Section 10.4.1, the SEA methodology integrates environmental
considerations into economic and social aspects and the study evaluates each project in terms of
economic, social and environmental aspects. The results of each alternative are then cumulative
at the programme level in order to compare the three alternatives of the Master Plan for
Development of the Sena Corridor from the SEA perspective.
Table 10-20 shows the local economic impact, social impact, and environmental impact of
the three alternatives. The overall cumulative results for the Sena Corridor’s Master Plan are
summarised in Table 10-21. These shows that Alt. 1 (Scenario 3: connection to Beira by road
and railway) and Alt. 3 (Scenario 3: connection to Beira by road and connecting to Nsaje by
railway) have the relatively positive impacts. Both cases will improve the disconnection at
Chiromo washaway, which will benefit the local population in terms of access to agricultural
products, schools and health posts. Although the boat association, bicycle operators and vendors
at the disconnection site will lose their sources of income by the upgrading and the appropriate
compensation for affected people is needed, the project will significantly improve the
livelihoods of poor people, who currently suffer from expensive transport costs due to the
disconnection. The overall impact on the local economy by connecting at Chiromo washaway is
anticipated to be positive. The population living between Luchenza and Makhanga, where there
is no road nearby and the train service is currently not sufficient to meet the demands along the
railway line, are expected to benefit significantly from the improved mobility by the
rehabilitation of the railway. Improved transport at the disconnection will help reduce the
number of accidents by boats. The rehabilitation of the railway line is expected to change the
transport mode from truck/car to railway, which will reduce total air pollutants emissions. The
current landslides, slope failure, and soil erosion that occur along the railway line are expected
to be improved by the stabilisation of slopes and soil while the occurrence of floods and
overflow of water on the road are expected to be minimized.
On the other hand, the zero option is expected to deteriorate the local economy due to the
limited availability of transport, especially at the disconnection at Chiromo washaway, and will
cause a significant negative social impact in terms of boat accidents at Chiromo washaway and
the soial transport services to schools and health posts.
10 - 40
Table 10-20 SEA Results for Master Plan on the Development of the Sena Corridor
Alternative
Project Zero Alt. Alt. Alt. Local Economic Impact Social Impact Environmental Impact
Option 1 2 3
The non-project option will cause significant
Since the local population suffers from the limited negative impact in terms of boat accidents at No negative impact on biodiversity and forest resources
availability of transport, especially due to the is expected, but the current landslides, slope failure
Zero Option X D disconnection at Chiromo, the non-project option is D Chiromo, and the social transport services in C floods, and overflow of water on the roads and railways
terms of access to agricultural products, schools,
expected to deteriorate the local economy. and health posts remain limited in the region. will remain.
Since the local population currently suffers from the Some negative impact of resettlement of
S151 disconnection at Chiromo, the improved access to households and boat associations is expected. The project passes the wetland and the Shire River,
Improved transport will help reduce the number which may affect biodiversity and the hydrological
Makhanga– X X A agricultural products and improved mobility will B of boat accident. Local people will benefit from C situation. Soil erosion is expected to be improved by
Bangula significantly benefit the local population, including the
(8.7 km) poor who suffer from expensive transport costs due to the improved transport services in terms of access the project. The occurrence of floods and overflow of
to agricultural products, schools, health posts, and water on the road are expected to be minimized.
the disconnection. so on.
M1 The lands acquired for constructing climbing lane Although some negative changes of geographical
Blantyre–Thabwa Some employment opportunities for local people are are in the hilly area and largely away from human features are expected, the project does not pass through
X X X C expected, but in general, no negative or positive impact C C
Climbing Lane on the local economy is expected. settlements. Therefore, the impact of resettlement an ecologically sensitive area and its impact on the
(5.0km) and social services is negligible. environment is expected to be negligible.
Some negative impact of resettlement of
Chapter 10 Environmental and Social Considerations
households is expected. Since this is a populous Since the project passes near the sensitive area of forest
reserves and wetland, cutting trees and vegetation
Project for the Study on Development of the Sena Corridor
S152 The local population is expected to benefit from the area, the extent of resettlement could be during the upgrading work could cause further stress
Thabwa–Seven X X X B improved access to agricultural products and improved C significant. The local population will benefit from C
(59.1 km) mobility. the improved transport services in terms of access and deterioration of biodiversity and forests. The soil
erosion and overflow of water on the road are expected
to agricultural products, schools, health posts, and to be minimised.
so on.
Some negative impact of resettlement is expected.
Railway The local population is expected to benefit from the The local population will benefit from the The railway line does not pass through an ecologically
Limbe–Luchenza X X X B improved access to agricultural products and improved B improved transport services in terms of access to B sensitive area. Air pollution will be reduced by the
(44 km) mobility. agricultural products, schools, health posts, and so change of transport mode from truck/car to railway.
10 - 41
on.
Since there is no road nearby and the train service is
currently not sufficient to meet the demands along the Some impact of resettlement of households, The current landslides, slope failure, and soil erosion
agricultural fields, and vendors along the railway
Railway railway line, the local population is expected to benefit line is expected. The improved track and bridge along the railway line are expected to be improved by
significantly from the improved access to agricultural the stabilisation of slopes and soils. Air pollution will
Luchenza– X X X A products and improved mobility. Due to the limited B will help reduce the number of derailment B be reduced by the change of transport mode from
Makhanga accidents and engine troubles. Local people will
(76.6 km) access to transport, the poverty rate is high in this area benefit from the improved transport services in truck/car to railway. The occurrence of floods and
and the project will benefit all strata of the local overflow of water on the railway are expected to be
population, including the poor, to provide less terms of access to agricultural products, schools, minimized.
and health posts.
expensive transport.
Since the local population currently suffer from the Some impact of resettlement of households and The project passes the wetland and the Shire River,
disconnection at Chiromo, the improved access to boat associations is expected. Improved transport which may affect biodiversity and the hydrological
Railway situation. Soil erosion is expected to be improved by
Makhanga– X X X A agricultural products and improved mobility will B will help reduce the number of boat accidents. B the project. Air pollution will be reduced by the change
benefit the local population, including the poor who Local people will benefit from the improved
Bangula (8.7km) suffer from expensive transport costs due to the transport services in terms of access to of transport mode from truck/car to railway. The
occurrence of floods and overflow of water on the road
disconnection. agricultural products, schools, and health posts. are expected to be minimised.
Some illegally occupied agricultural fields and
Railway The local population is expected to benefit from the vendors need to be resettled. Local people will The project does not pass through an ecologically
Bangula–Nsanje X X X B improved access to agricultural products and improved B benefit from the improved transport services in B sensitive area. Air pollution will be reduced by the
(45.3 km) mobility. terms of access to agricultural products, schools, change of transport mode from truck/car to railway.
health posts, and so on.
Railway Some negative impact of resettlement of houses,
Nsanje–Border The local population is expected to benefit from the agricultural fields, and vendors is expected. Local The project does not pass through an ecologically
X X B improved access to agricultural products and improved B people will benefit from the improved transport B sensitive area. Air pollution will be reduced by the
(Marka) mobility. services in terms of access to agricultural change of transport mode from truck/car to railway.
(26.4 km)
products, schools, and health posts.
Notes: A = A significant positive impact is expected, B = Some positive impact is expected, C = Some negative/negligible impact is expected, D = Significant negative impact is expected.
Final Report
Based on the results of scoping checklists, several measures are recommended to minimize
adverse impacts from the proposed Master Plan.
(1) Air Pollution
a) Utilization of Environment-friendly Mode of Transport
The increase in air pollutant emission from motor vehicles can be offset by the change of
transport mode from truck/car to railway. The proposed rehabilitation of railways would
significantly reduce the amount of air pollution in the project area. In general, one diesel
locomotive can replace the amount of air pollutants generated from 20–30 trucks, which would
reduce the overall amount of air pollution in Malawi.
b) Design to Minimise Air Pollution from Motor Vehicles
The average speed of 60–70 km/h is considered to be the most efficient in combusting fossil
fuels of motor vehicles. The roads in the proposed projects are designed to be operated at the
average speed of 70 km/h, which will improve the efficiency of fossil fuel combustion. To
promote the efficient use of fossil fuels, the road alignment can be designed to avoid traffic
congestion, sharp curves, and steep grades, which would cause acceleration and deceleration.
c) Minimization of Dust by Appropriate Instructions to Contractors
The dust produced during the construction phase can be minimized by providing appropriate
instructions to contractors, such as spraying water on provisional earth road.
(2) Water Pollution
a) Proper Siting of Work Camp and Stockyard
The potential water pollution can be mitigated by proper siting of work camps, that is, by
avoiding sensitive areas such as water catchments, and by locating the stockyard for all
construction materials far from rivers, wetlands and drinking water intake. The recommended
siting from the Environmental and Social Management Guidelines in the Road Sector is to
stockpile waste materials 15 km away from water resources. This is possible in the proposed
projects.
(3) Mitigation Measures for Biodiversity in Wetlands
a) Environmentally Friendly Construction Work in Wetlands
The biodiversity in Elephant Marsh will be taken into consideration in the Master Plan, in
particular, the avoidance of water pollution and preservation of trees used by nesting birds will
10 - 42
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The Study Team has conducted an IEE of the pre-Environmental Impact Assessment for the
proposed priority projects. The IEE is a preliminary analysis of alternative plans, a prediction
and assessment of environmental impacts, and preparation of mitigation measures and a
monitoring plan on the basis of existing data and simple field surveys (“JICA Environmental
Guidelines”).
The proposed priority projects selected by the Master Plan are 1) Reconstruction of the S151
Road between Makhanga and Bangula, and 2) Rehabilitation/Reconstruction of the Railway
between Limbe and Border (Marka). This survey follows the standard methodology of IEE, but
due to the limited information on socio-economic data and flood damage in the project area, a
field investigation was carried out for the section between Makhanga and Bangula. This
includes a questionnaire survey of PAPs, data collection on agriculture and land use in the
project area, and consultation with district governments.
In addition, the IEE for priority projects requires consultation with stakeholders during the
scoping process, according to the Environmental Management Act 1997 and “JICA
Environmental Guidelines”. A stakeholder meetings were held to encourage relevant
stakeholders to understand the project needs, the project design and adverse impacts on the
environment and society, and to participate in the analysis of alternatives and mitigation
measures at an early stage of the proposed projects. Table 10-22 shows an outline and the main
features of the proposed projects for the IEE in the Pre-F/S.
10 - 43
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-22 Outlines of Priority Projects for the IEE in the Pre-F/S
Due to the limited existing documents and data on the socio-economic situation and flood
damage in the project area, the survey carried out a field investigation in the project area
between Makhanga and Bangula. The proposed projects require an analysis of alternative routes
(road project) and mitigation measures for PAPs, especially for the loss of income of the boat
association and vendors after the Chiromo washaway is connected (both road and railway
projects). Therefore, a questionnaire survey was undertaken to assess the impact on the
livelihoods of people affected, and their willingness to find alternative sources of income, and to
analyse possible mitigation measures for PAPs. This questionnaire survey focused on specific
groups and was not statistically representative, since the sample size was limited due to the
study schedule. However, the survey collected some useful information to understand the
socio-economic situation and flood damage, which is not well known from existing documents
and data. The detailed findings of the field investigation are provided in Appendix 5. Table
10-23 describes the major findings of the survey.
Based on the analysis of environmental and social impacts, the Study evaluates the proposed
projects in the scoping matrix and describes the major impacts on each project section.
10.5.3 IEE Results for Reconstruction of the S151 Road between Makhanga and Bangula
(1) Scoping Matrix
Table 10-24 shows the scoping matrix for the reconstruction of the S151 road between
Makhanga and Bangula (9.5 km).
10 - 44
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 45
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-24 Scoping Matrix for Reconstruction of S151 Road between Makhanga and Bangula
(1/2)
Construction
Non-project
Operation
Phase
Phase
Impact Outline
1 Resettlement/land acquisition B B D - Due to the realignment and upgrading of the road, the resettlement of some houses
and shops in Makhanga is expected.
- Some land acquisition is expected due to the change of alignment. Proper mitigation
measures need to be taken.
2 Local economy such as B+ B+ A - The local population is expected to benefit significantly from the improved access to
employment and livelihood, agricultural products and improved mobility.
etc. - Employment opportunities for local people are expected to be created during the
reconstruction.
- Members of the boat association and vendors at the Chiromo washaway section will
lose their sources of income, and the incomes of members of the bicycle taxi
association may decrease due to construction of the Chiromo Road Bridge.
- Appropriate compensation for affected people is needed. The overall impact is
anticipated to be positive.
3 Land use and utilisation of B B D - Land acquisition will be necessary for some plots of farmers’ land which will be
local resources affected by the new alignment of the reconstructed S151 at Makhanga and both sides
of the Chiromo washaway and the New Shire Bridge.
- In addition, land will need to be rented during construction for temporary
construction yard(s).
- Water pumped up from shallow wells has the potential to be affected by the
reconstruction works.
- In order to identify the impact of the project, detailed observation will be required
during the F/S stage.
4 Social institutions such as B C D - The boat association and bicycle taxi association will be affected by the
social infrastructure and local reconstruction.
decision-making institutions
5 Existing social infrastructure B A+ A - The local population will significantly benefit from the improved transport services in
and services terms of access to agricultural products, schools, and health posts.
Social Environment
10 - 46
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-24 Scoping Matrix for Reconstruction of S151 Road between Makhanga and Bangula
(2/2)
13 Topography and geographical B C D - Construction of embankments with a height of 1.1 m to 4.0 m will modify
features existing geographical features in the project area.
14 Soil erosion B B+ A - Further soil erosion is anticipated at construction sites of the Chiromo Road Bridge
and the New Shire Bridge due to excavation of the river bank and river bed, unless
proper revetment works are carried out for the excavated river bed and
abutments/piers of the newly constructed bridges.
15 Groundwater C C D - Construction of embankments may have adverse effects on groundwater.
- Appropriate consideration for existing water sources (shallow wells) can prevent
adverse effects on groundwater.
Natural Environment
16 Hydrological situation B B D - Construction of the Chiromo Road Bridge is planned and the locations of abutments
and piers are planned so as not to disturb the present water flow. However, there is a
risk of frequent flooding due to a narrow river section caused by the existing road
embankment on the Bangula side of the Chiromo washaway unless this road
embankment is demolished.
- It will be difficult to drain flooded water on the land between the existing railway
embankment and the planned road embankment from the Chiromo washaway section
towards the Shire River. This is a negative impact for land use for cultivation.
17 Coastal zone D D D - The project does not pass near the coast.
18 Flora, fauna and biodiversity B B B - The planned alignment of S151 will pass through the outer edge of Elephant Marsh,
which is not a protected area by law in Malawi.
19 Meteorology D D D - There is no activity that might affect meteorology.
20 Landscape B C D - Construction of the Chiromo Road Bridge and the New Shire Bridge could change
the landscape.
21 Global warming D D D - Due to the volume of traffic in this area, the impact on global warming is expected to
be negligible.
22 Air pollution B B D - In the proposed projects, the roads in the project area are designed for an average
speed of 70 km/h, which will result in more efficient combustion of fossil fuels than
at present.
- Some dust will be produced during construction and some adverse impacts are
expected in the residential area at Makhanga, but other places will suffer no
significant impact since most of the construction work will be done in open
agricultural/vegetation areas amid dispersed settlements.
23 Water pollution B D D - There are potential sources of pollution of surface and groundwater flows in the
Project. These are: 1) runoff soil from the construction site, particularly due to
excavation of river beds and banks for constructing the foundations of bridges and
demolition of the road embankment on the Bangula side, 2) surface soil erosion
caused by rain water from the excavation site, 3) accidental leakage of fuel/oil and 4)
structures, such as drains and bridges, connected to or placed in/under surface water
flow.
- Sewage will be discharged from the toilets and food courts of the construction camp
into surrounding water flows if appropriate measures are not taken.
24 Soil contamination B C D - During the construction, accidental leakage of fuel/oil is anticipated to cause soil
Pollution
contamination.
25 Waste B D D - Solid waste will be produced during the road improvement process, starting with
surplus soil and rocks from the excavation work and also metallic parts, cut wood
from road sides and slopes, and food waste from construction workers.
26 Noise and vibration B B D - Trucks and heavy equipment working along the road will be noisy and cause
vibration.
27 Ground subsidence C C D - There is no extraction of groundwater which might lead to ground subsidence.
28 Offensive odour B D D - Offensive odour is temporarily expected due to exhaust gas from construction
vehicles and heavy equipment.
29 Bottom sediment B D D - The construction work could generate dust from construction materials and
excavation work.
30 Accidents B B B - During the construction process, there will be more heavy traffic, which may increase
A+ the risk of traffic accidents.
- During the operational phase of the project, the higher speed and increase amount of
traffic may hinder the movement of farmers and livestock, and the risk of traffic
accidents may increase.
- There have been boat accidents at the disconnection site every year and some people
have died in such accidents. Improved transport at the Chiromo washaway will help
reduce the number of boat accidents significantly in this area.
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicates a positive impact
Source: Study Team
10 - 47
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 48
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
local people are expected to be created during the reconstruction works. The local population
will also benefits from improved transport access for agricultural crops during the rainy season,
and some people may no longer need to borrow a boat to transport agricultural crops.
Reconstruction of the S151 road may reduce the income of some vendor, whose shops are
relocated.
d) Land Use and Utilisation of Local Resources
Land acquisition will be necessary for some plots of farmer’s land which will be affected by
the new alignment of the reconstructed S151 at Makhanga and both sides of the Chiromo
washaway and the New Shire Bridge. In addition, land will need to be rented during
construction for temporary construction yard(s). These will be negative impacts caused by the
project.
Water pumped up from shallow wells has the potential to be affected by the reconstruction
works. In order to identity the impact of the project, detailed observation will be required during
the F/S stage.
e) Hazards
There is serious erosions on the right-side bank of the Ruo River near Makhanga and this
could have a negative impact if it is decided to improve the existing road alignment, which
passes only 30 m from the river bank.
Planned road reconstruction on the existing alignment with an embankment of 1.1 m to 2.0 m
near Makhanga may provide protection against flood water from the Ruo River for residences
north of the existing road, while also preventing water from flooding the central part of
Makhanga. This is a combination of positive and negative impacts.
Construction of the Chiromo Road Bridge is planned in the Study and the locations of
abutments and piers are planned so as to disturb the present water flow. However, there is a risk
of frequent flooding due to a narrow river section caused by the existing road embankment on
the Bangula side of the Chiromo washaway.
It will be difficult to drain flooded water on the land between the existing railway
embankment and the planned road embankment from the Chiromo washaway section towards
the Shire River. This is a negative impact for land use for cultivation.
During the construction process, there will be more heavy traffic, which may increase the risk
of traffic accidents. During the operational phase of the road and railway of the Project, the
higher speed and increased volume of traffic may hinder the movement of farmers and livestock,
and risk of traffic accidents may increase.
f) Forests Biodiversity and Social Condition
• It is expected that no forest cutting will be necessary for the Project.
• There are no historical and cultural heritages, including World Heritage Sites, along the
selected roads.
10 - 49
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
• There are no indigenous people in Malawi. However, there are minority people living in the
country since Malawi is a conglomerate state that consists of multi-ethnic groups and
religious sects.
g) Flora, Fauna, and Biodiversity
As noted in Section 10.4, the proposed projects pass through the outer edge of a wetland
called Elephant Marsh, which is not a protected area by law in Malawi. However, the wetland
plays an important role in biodiversity as a bird sanctuary and as a destination for migrating
birds, and its biodiversity and importance as a destination for migrating birds need to be taken
into consideration when undertaking a road project in this area.
The Lower Shire Valley is a breeding site for crocodiles and hippos, as noted in Section 10.4.
Improved accessibility around the marsh might lead to increased poaching activities and
encroachment. As the marsh is not only rich in biodiversity but also a source of human
livelihood, an appropriate wetland management plan, as illustrated in the case of Lake Chilwa,
is desired.
h) Topography and Soil
Construction of road embankments with height of 1.1 m to 4.0 m will modify the existing
geographical features in the project area.
i) Hydrology
Construction of the Chiromo Road Bridge is planned and the locations of abutments and piers
are planned so as not to disturb the present water flow. However, there is a risk of frequent
flooding due to a narrow river section caused by the existing road embankment on the Bangula
side of the Chiromo washaway unless this road embankment is demolished.
It will be difficult to drain flooded water on the land between the existing railway
embankment and the planned road embankment from the Chiromo washaway section towards
the Shire River. This is a negative impact for land use for cultivation.
j) Air Pollution
The traffic volume in the project area is relatively low compared to other regions in Malawi:
the volumes of motorised vehicles on the S151 (Seven) in 2006 was 37 veh./day. The average
speed of vehicles on unpaved roads in the project area was about 32–40 km/h. In the proposed
projects, the roads in the project area are designed for an average speed of 70 km/h, which will
result in more efficient combustion of fossil fuels than at present.
Some dust will be produced during construction and some adverse impacts are expected in
the residential areas of Makhanga, but other places will suffer no significant impact since most
of the construction work will be done in open agricultural/vegetation areas amid dispersed
settlements. The dust may be more intense during the dry season in the project area.
k) Water Pollution
There are potential sources of pollution of surface and groundwater flows in the Project.
These are: 1) runoff soil from the construction site, particularly due to excavation of river beds
and banks for constructing the foundations of bridges and demolition of the road embankment
10 - 50
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
on the Bangula side, 2) surface soil erosion caused by rain water from the excavation site, 3)
accidental leakage of fuel/oil and 4) structures, such as drains and bridges, connected to or
placed in/under surface water flow.
Solid waste will be produced during the road improvement process, starting with surplus soil
and rocks from the excavation work and also metallic parts, cut wood from road side and slopes
and food waste from construction workers.
Sewage will be discharged from the toilets and food courts of the construction camp into
surrounding water flows if appropriate measures are not taken.
Groundwater is also an important source of water for the rural population in this region. In
the Lower Shire Valley, groundwater tend to have high levels of salt, causing shallow wells to
be abandoned. There are two shallow wells in the project area, and a detailed survey of the
groundwater near the shallow wells is needed to prevent water pollution from construction
work.
l) Noise and Vibration
Trucks and heavy equipment working along the road will be noisy and cause vibration.
10.5.4 IEE Results for Rehabilitation of Railway between Limbe and Luchenza
(1) Scoping Matrix
Table 10-25 shows the scoping matrix for the rehabilitation of railway between Limbe and
Luchenza (44.0 km).
Table 10-25 Scoping Matrix for Rehabilitation of Railway between Limbe and Luchenza (1/2)
Construction
Non-project
Operation
Phase
Phase
Impact Outline
1 Resettlement/land acquisition B B D - Land acquisition will be necessary for some plots of farmers’ land
which will be affected by changing of the alignment for small bridges
to be reconstructed.
- Illegal farming activities within the railway ROW need to be stopped.
2 Local economy such as B+ B+ D - The local population is expected to benefit from the improved
employment and livelihood, mobility. Employment opportunities for local people are expected to
etc. be created during the rehabilitation.
3 Land use and utilisation of B B D - Land will need to be rented during construction for temporary
local resources construction yard(s).
Social Environment
4 Social institutions such as D D D - There is no social association affected by the railway project.
social infrastructure and local
decision-making institutions
5 Existing social infrastructure B B+ B - The local population will benefit from the improved transport services
and services in terms of access to agricultural products, schools, and health posts.
6 Poor, indigenous and ethnic D B+ B - The rehabilitation will benefit all strata of the local population,
people including the poor.
7 Misdistribution of benefit and D D D - Equal employment opportunities for the local population can avoid
damage the misdistribution of benefit.
8 Cultural heritage D D D - No important cultural sites have been identified near the project area.
9 Local conflicts of interest D D D - There is no significant local conflict caused by the rehabilitation
project.
10 Water usage or water rights C C D - Major damage to water usage by the local population is not
anticipated, but it is necessary to confirm the water sources near the
railway line.
10 - 51
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-25 Scoping Matrix for Rehabilitation of Railway between Limbe and Luchenza (2/2)
11 Sanitation C D D - The construction camp will adversely affect sanitation if proper
measures are not taken.
12a Hazards (risks) D D D - Major hazards such as floods and washaways are not expected in this
section.
12b Infectious diseases such as B B B - In general, the construction workers could increase the prevalence of
HIV/AIDS HIV and other infectious diseases, if proper preventive measures are
not taken.
13 Topography and geographical D D D - The project site is on hilly terrain and a major impact on geographical
features features is not expected.
14 Soil erosion B B+ B - Soil erosion due excavation and water flow diversion is expected
during the rehabilitation work and proper mitigation measures are
required to prevent it. The improved drainage system will minimise
further soil erosion.
15 Groundwater C C D - In-situ piling of the foundations of bridges for reconstruction will
Natural Environment
10 - 52
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 53
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
particulate matter (PM). In the planned railway projects, passenger trains will run daily between
Limbe and Nsanje, some freight trains will run between Limbe and Border, and trucks that are
currently used to carry sugar from Nchalo and cotton from Bangula will be replaced by freight
trains. Although there may be an increase in air pollutants emitted by locomotives, this increase
may be partially offset by the change of transport mode from minibus/truck to railway.
g) Water Pollution
There are potential sources of pollution of surface and groundwater flows in the Project.
These are: 1) runoff soil from the construction site, 2) surface soil erosion caused by rain water
from the excavation site, 3) accidental leakage of fuel/oil and 4) structures, such as drains and
bridges, connected to or placed in/under surface water flow.
Solid waste will be produced during the road improvement process, starting with surplus soil
and rocks from the excavation work and also metallic parts, cut wood from road side and slopes
and food waste from construction workers.
Sewage will be discharged from the toilets and food courts of the construction camp into
surrounding water flows if appropriate measures are not taken.
h) Noise and Vibration
Trucks and heavy equipment working along the road will be noisy and cause vibration.
10.5.5 IEE Results for Rehabilitation of Railway between Luchenza and Makhanga
Non-project
Operation
Phase
Phase
Impact Outline
1 Resettlement/land acquisition B B D - Land acquisition will be necessary for some plots of farmers’ land which
will be affected by changing the alignment for 2.3 km of the section
between Makhanga and Sankhulani and small bridges to be
reconstructed.
- Illegal farming activities within the railway ROW need to be stopped.
2 Local economy such as B+ A+ A - Since there is no road nearby and the train service is currently not
Social Environment
employment and livelihood, etc. sufficient to meet demands along the railway line, the local population is
expected to benefit significantly from the improved access to agricultural
products and improved mobility.
- Employment opportunities for local people are expected to be created
during the rehabilitation.
3 Land use and utilisation of local B B D - Land will need to be rented during construction for temporary
resources construction yard(s).
4 Social institutions such as social D D D - There is no social association affected by the railway project.
infrastructure and local
decision-making institutions
5 Existing social infrastructure and B A+ A - The local population will significantly benefit from the improved
services transport services in terms of access to agricultural products, schools,
and health posts.
10 - 54
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-26 Scoping Matrix for Rehabilitation of Railway, Luchenza–Makhanga Section (2/2)
6 Poor, indigenous and ethnic D A+ A - The rehabilitation will benefit all strata of the local population,
people including the poor. The poverty rate is high in the project area, partly
due to the limited access to transport.
7 Misdistribution of benefit and D D D - Equal employment opportunities for the local population can avoid the
damage misdistribution of benefit.
Social Environment
8 Cultural heritage D D D - No important cultural sites have been identified near the project area.
9 Local conflicts of interest D D D - There is no significant local conflict caused by the rehabilitation
project.
10 Water usage or water rights C C D - Major damage to water usage by the local population is not anticipated,
but it is necessary to confirm the water sources near the railway line.
11 Sanitation C D D - The construction camp will adversely affect sanitation if proper
measures are not taken.
12a Hazards (risk) B B+ B - The occurrence of floods and overflow of water on the railway are
expected to be minimised by the improved drainage system.
12b Infectious diseases such as B B B - In general, construction workers could increase the prevalence of HIV
HIV/AIDS and other infectious diseases if proper preventive measures are not
taken.
13 Topography and geographical B B+ A - The current landslides and slope failures that occur along the railway
features line will be improved by the stabilisation of slopes and soils. The
rehabilitation work could change geographical features in the project
area.
14 Soil erosion B B+ B - Soil erosion due to excavation and water flow diversion is expected
during the rehabilitation work and proper mitigation measures are
required to prevent it. Slope failures cause soil erosion at the moment,
which can be improved by the better drainage system, and replanting
Natural Environment
cause vibration.
- Increased train operations could generate more noise and vibration
along the railway line.
27 Ground subsidence D D D - There is no extraction of groundwater that could lead to ground
subsidence.
28 Offensive odour B C D - Offensive odour is temporarily expected due to exhaust gas from
construction vehicles and heavy equipment.
- The operation of diesel locomotives will generate some offensive
odour.
29 Bottom sediment B D D - The rehabilitation work could generate dust from construction
materials and excavation work, in particular near the river.
30 Accidents B B B - After the completion of rehabilitation and reconstruction works, the
number of trains will increase between Luchenza and Makhanga. This
may increase the risk of accidents between a train and a vehicle,
bicycle or pedestrian along the railway line or at a level crossing.
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. * indicates a positive impact.
Source: Study Team
10 - 55
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 56
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
impact.
f) Forests Biodiversity and Social Condition
• The railway line between Luchenza and Makhanga does not pass through an ecologically
sensitive area and the impact on biodiversity is considered to be negligible.
• It is expected that no forest cutting will be necessary for the Project.
• There are no historical and cultural heritages, including World Heritage Sites, along the
selected roads.
• There are no indigenous people in Malawi. However, there are minority people living in the
country since Malawi is a conglomerate state that consists of multi-ethnic groups and
religious sects.
g) Flora, Fauna and Biodiversity
The railway lines between Luchenza and Makhanga, does not pass through an ecologically
sensitive area and the impact on biodiversity is expected to be negligible. Most of the
construction work will be done within the ROW.
h) Topography and Soil
In the proposed railway rehabilitation projects, the risk of landslides and slope failures
between Luchenza and Makhanga will be minimized by replanting vegetation and trees on
cleared areas and slopes, using slope retaining techniques, improving the drainage system, etc.
i) Air Pollution
Railway is an environment-friendly means of transport in terms of air pollution. For the
section between Luchenza and Makhanga, diesel locomotives are currently used for passenger
trains, which run once a week. Diesel locomotives emit combustion products such as NOx and
particulate matter (PM). In the planned railway projects, passenger trains will run daily between
Limbe and Nsanje, some freight trains will run between Limbe and Border, and trucks that are
currently used to carry sugar from Nchalo and cotton from Bangula will be replaced by freight
trains. Although there may be an increase in air pollutants emitted by locomotives, this increase
may be partially offset by the change of transport mode from minibus/truck to railway.
j) Water Pollution
There are potential sources of pollution of surface and groundwater flows in the Project.
These are: 1) runoff soil from the construction site, 2) surface soil erosion caused by rain water
from the excavation site, 3) accidental leakage of fuel/oil and 4) structures, such as drains and
bridges, connected to or placed in/under surface water flow.
Solid waste will be produced during the road improvement process, starting with surplus soil
and rocks from the excavation work and also metallic parts, cut wood from road side and slopes
and food waste from construction workers.
Sewage will be discharged from the toilets and food courts of the construction camp into
surrounding water flows if appropriate measures are not taken.
k) Noise and Vibration
Trucks and heavy equipment working along the road will be noisy and cause vibration.
10 - 57
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10.5.6 IEE Results for Reconstruction of Railway between Makhanga and Bangula
(1) Scoping Matrix
Table 10-27 shows the scoping matrix for the reconstruction of railway between Makhanga
and Bangula (8.7 km).
Table 10-27 Scoping Matrix for Reconstruction of Railway between Makhanga and Bangula (1/2)
Construction
Non-Project
Operation
Phase
Phase
Impact Outline
1 Resettlement/land B B D - Due to the reconstruction of the railway, the eviction of some vendors near
acquisition Makhanga and Bangula Station is expected.
- Some land acquisition is expected due to the change of alignment for construction
of the Chiromo Railway Bridge.
2 Local economy such as B+ B+ A - The local population is expected to benefit significantly from the improved access
employment and to agricultural products and improved mobility. Employment opportunities for
livelihood, etc. local people are expected to be created during the reconstruction. The overall
impact is anticipated to be positive.
- After the completion of rehabilitation and reconstruction of the railway between
Limbe and Nsanje, or even Bangula, the local economy in Makhanga is expected
to change dramatically, because Makhanga Station will become just one of the
small stations between Luchenza and Bangula, and most of the passengers from
Limbe and Luchenza will continue their trip to Bangula or Nsanje, instead of using
Makhanga Station as a transit point for their trip as at present. This is a very
common situation all over the world when bypass is constructed for either a
railway or road, and indirect negative impacts for the local economy are
unavoidable. To address this issue, a rural development plan will be necessary
rather than mitigation measures in this project.
3 Land use and utilisation of C C D - Land will need to be rented during construction for temporary construction
local resources yard(s).
4 Social institutions such as B C D - The bicycle taxi association will be affected by the reconstruction of the railway
social infrastructure and line and resumption of operation of passenger trains to Bangula.
Social Environment
local decision-making
institutions
5 Existing social D A+ A - The local population will benefit significantly from the improved transport
infrastructure and services services in terms of access to major markets, schools, and health posts.
6 Poor, indigenous and D A+ A - The reconstruction will benefit all strata of the local population, including the
ethnic people poor. The poverty rate is high in the project area, partly due to the disconnection at
Chiromo.
7 Misdistribution of benefit D D D - Equal employment opportunities for the local population can avoid the
and damage misdistribution of benefit.
8 Cultural heritage D D D - No important cultural sites have been identified near the project area.
9 Local conflicts of interest C C D - Bicycle taxi pedalers may be disadvantaged by the reconstruction project while
most other people will benefit. It is necessary to appropriately compensate the
disadvantaged groups to avoid local conflict.
10 Water usage or water rights C C D - Some farmers using irrigation could be affected by the reconstruction. Some
fishermen could be affected by the construction of the Chiromo Railway Bridge.
11 Sanitation C D D - The construction camp will adversely affect sanitation if proper measures are not
taken.
12a Hazards (risks) B C B - Construction of the Chiromo Railway Bridge is planned and the location of
abutments and piers are planned so as not to disturb the present water flow.
However, there is a risk of frequent flooding due to a narrow river section caused
by the existing road embankment on the Bangula side of the Chiromo washaway.
- It will be difficult to drain flooded water on the land between the existing railway
embankment and the planned road embankment from the Chiromo washaway
section towards the Shire River. This is a negative impact for land use for
cultivation.
12b Infectious diseases such as B B B - Construction workers could increase the prevalence of HIV and other infectious
HIV/AIDS diseases, if proper preventive measures are not taken.
10 - 58
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-27 Scoping Matrix for Reconstruction of Railway between Makhanga and Bangula (2/2)
13 Topography and B C D - Construction of new embankments at the approach section of the Chiromo
geographical features Railway Bridge will modify existing geographical features in the project area.
14 Soil erosion B B+ A - Further soil erosion is anticipated at construction sites of the Chiromo Railway
Bridge due to excavation of the river bank and river bed, unless proper revetment
works are carried out for the excavated river bed and abutments/piers of the newly
constructed bridge.
15 Groundwater C D D - Construction of a new embankment at the approach section of the Chiromo
Railway Bridge may have adverse effects on groundwater. Appropriate
consideration for existing water sources (shallow wells) can prevent adverse
effects on groundwater.
Natural Environment
16 Hydrological situation B B D - Construction of the Chiromo Railway Bridge is planned and the locations of
abutments and piers are planned so as not to disturb the present water flow.
However, there is a risk of frequent flooding due to a narrow river section caused
by the existing road embankment on the Bangula side of the Chiromo washaway
unless this road embankment is demolished.
- It will be difficult to drain flooded water on the land between the existing railway
embankment and the planned road embankment from the Chiromo washaway
section towards the Shire River. This is a negative impact for land use for
cultivation.
17 Coastal zone D D D - The project does not pass near the coast.
18 Flora, fauna and B B B - The existing railway alignment passes through the outer edge of Elephant Marsh,
biodiversity which is not a protected area by law in Malawi.
19 Meteorology D D D - There is no activity that might affect meteorology.
20 Landscape C C D - Construction of the Chiromo Railway Bridge could change the landscape..
21 Global warming D D D - Due to the volume of traffic in this area, the impact on global warming is expected
to be negligible.
22 Air pollution B B+ D - Dust and other air pollutants are expected to be produced during the
reconstruction.
- The change of transport mode from truck/car to more environment-friendly
railway will reduce total pollutant emissions.
23 Water pollution B D D - There are potential sources of pollution of surface and groundwater flows in the
Project. These are: 1) runoff soil from the construction site, particularly due to
excavation of river beds and banks for constructing the foundations of bridges and
demolition of the road embankment on the Bangula side, 2) surface soil erosion
caused by rain water from the excavation site, 3) accidental leakage of fuel/oil and
4) structures, such as drains and bridges, connected to or placed in/under surface
water flow.
- Sewage will be discharged from the toilets and food courts of the construction
camp into surrounding water flows if appropriate measures are not taken.
24 Soil contamination B C D - During the construction, accidental leakage of fuel/oil is anticipated to cause soil
contamination.
25 Waste B C D - Solid waste will be produced during the road improvement process, starting with
surplus soil and rocks from the excavation work and also metallic parts, cut wood
Pollution
from railway sides and slopes, and food waste from construction workers.
26 Noise and vibration B B D - Trucks and heavy equipment working along the road will be noisy and cause
vibration.
- Increased train operation could generate more noise and vibration along the
railway line.
27 Ground subsidence C C D - There is no extraction of groundwater which might lead to ground subsidence.
28 Offensive odour B C D - Offensive odour is temporarily expected due to exhaust gas from construction
vehicles and heavy equipment.
- The operation of diesel locomotives will generate some offensive odour.
29 Bottom sediment B D D - Reconstruction work could generate dust from construction materials and
excavation work.
30 Accidents B B B - During the construction process, there will be more heavy traffic, which may
increase the risk of traffic accidents.
- After the completion of rehabilitation and reconstruction works, trains will resume
operation between Makhanga and Bangula. This may increase the risk of accidents
between a train and a vehicle, bicycle or pedestrian at the one main level crossing
with M1 and on the Kamuzu Truss Bridge (rail cum road bridge).
- Accident involving pedestrians and bicycle along the railway line are also
anticipated.
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicates a positive impact.
Source: Study Team
10 - 59
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 60
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10.5.7 IEE Results for Reconstruction of Railway between Bangula and Nsanje
10 - 61
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Construction
Non-project
Operation
Phase
Phase
Impact Outline
1 Resettlement/land acquisition B B D - A few illegally occupied agricultural fields and some illegally occupied
huts of vendors need to be relocated.
- Illegal farming activities within the railway ROW need to be stopped.
- Since the adjacent road can be utilised to transport construction
materials during the reconstruction, resettlement is not expected to have
a significant impact.
2 Local economy such as B+ B+ D - The local population is expected to benefit from the improved access to
employment and livelihood, agricultural products and improved mobility.
etc. - Employment opportunities for local people are expected to be created
during the reconstruction.
3 Land use and utilisation of C C D - Land will need to be rented during construction for temporary
local resources construction yard(s).
4 Social institutions such as D D D - There is no social association affected by the railway project.
social infrastructure and local
Social Environment
decision-making institutions
5 Existing social infrastructure B B+ D - The local population will benefit from the improved transport services
and services in terms of access to agricultural products, schools, and health posts.
6 Poor, indigenous and ethnic D B+ B - The reconstruction will benefit all strata of the local population,
people including the poor.
7 Misdistribution of benefit and D D D - Equal employment opportunities for the local population can avoid the
damage misdistribution of benefit.
8 Cultural heritage C C D - No important cultural sites have been identified near the project area.
9 Local conflicts of interest D D D - There is no significant local conflict caused by the reconstruction
project.
10 Water usage or water rights C C D - Major damage to water usage by the local population is not anticipated,
but it is necessary to confirm water sources near the railway line.
11 Sanitation C D D - The construction camp will adversely affect sanitation if proper
measures are not taken.
12a Hazards (risks) D D D - The occurrence of floods and overflow of water on the railway are
expected to be minimised by the improved drainage system.
12b Infectious diseases such as B B B - In general, construction workers could increase the prevalence of HIV
HIV/AIDS and other infectious diseases if proper preventive measures are not
taken.
13 Topography and geographical D D D - The project site is on the flat plain in the Lower Shire Valley and a
features major impact on geographical features is not expected.
14 Soil erosion B B+ A - Soil erosion due to excavation is not anticipated because there are only
wadis where reconstruction of bridges is planned.
- Soil erosion of wadis only during rainy season will be minimised by the
improved drainage system.
15 Groundwater C C D - In-situ piling of the foundations of bridges for reconstruction will have
Natural Environment
10 - 62
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-28 Scoping Matrix for Reconstruction of Railway betwen Bangula and Nsanje (2/2)
22 Air pollution B B+ D - Dust and other air pollutants are expected to be produced during the
reconstruction.
- The change of transport mode from truck/car to railway is expected to
reduce total pollutant emissions.
23 Water pollution B D D - Accidental leakage of fuel/oil and discharge of sewage from the toilets
and food courts of the construction camp into surrounding water flows
may occur if appropriate measures are not taken.
24 Soil contamination B C D - During the reconstruction, some chemical grouting is expected to cause
soil contamination.
25 Waste B C D - Solid waste will be produced during the road improvement process,
starting with surplus soil and rocks from the excavation work and also
metallic parts, cut wood from railway sides and slopes, and food waste
from construction workers.
- The increase of passenger trains could increase waste at stations.
26 Noise and vibration B B D - Trucks and heavy equipment working along the road will be noisy and
Pollution
cause vibration.
- Increased train operation could generate more noise and vibration along
the railway line.
27 Ground subsidence D D D - There is no extraction of groundwater that could lead to ground
subsidence.
28 Offensive odour B C D - Offensive odour is temporarily expected due to exhaust gas from
construction vehicles and heavy equipment.
- The operation of diesel locomotives will generate some offensive
odour.
29 Bottom sediment B D D - Reconstruction work could generate dust from construction materials
and excavation work, in particular near the river.
30 Accidents B B D - During the construction process there will be more heavy traffic, which
may increase the risk of traffic accidents.
- After the completion of rehabilitation and reconstruction works, trains
will resume operation between Bangula and Nsanje. This may increase
the risk of accidents between a train and a vehicle, bicycle or pedestrian
at the one main level crossings with M1.
Note: A = A significant impact is expected, B = Some impact is expected, C = Extent of impact is unknown, D = No or negligible impact is
expected. + indicates a positive impact.
Source: Study Team
10 - 63
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
resume between Bangula and Nsanje. This may increase the risk of accidents between a train
and a vehicle, bicycle or pedestrian at a level crossing with paved road. This will be a potential
negative impact.
d) Forests Biodiversity, and Social Condition
• The railway line between Border and Limbe does not pass through an ecologically sensitive
area and the impact on biodiversity is considered to be negligible.
• It is expected that no forest cutting will be necessary for the Project.
• There are no historical and cultural heritages, including World Heritage Sites, along the
selected roads.
• There are no indigenous people in Malawi. However, there are minority people living in the
country since Malawi is a conglomerate state that consists of multi-ethnic groups and
religious sects.
e) Flora, Fauna, and Biodiversity
The railway line between Bangula and Nsanje does not pass through an ecologically sensitive
area and the impact on biodiversity is expected to be negligible. Most of the construction work
will be done within the ROW.
f) Water Pollution
There are potential sources of pollution of surface and groundwater flows in the Project.
These are: 1) runoff soil from the construction site, 2) surface soil erosion caused by rain water
from the excavation site, 3) accidental leakage of fuel/oil and 4) structures, such as drains and
bridges, connected to or placed in/under surface water flow.
Solid waste will be produced during the road improvement process, starting with surplus soil
and rocks from the excavation work and also metallic parts, cut wood from road side and slopes
and food waste from construction workers.
Sewage will be discharged from the toilets and food courts of the construction camp into
surrounding water flows if appropriate measures are not taken.
g) Noise and Vibration
Trucks and heavy equipment working along the road will be noisy and cause vibration.
10.5.8 IEE Results for Reconstruction of Railway between Nsanje and Border (Marka)
(1) Scoping Matrix
Table 10-29 shows the scoping matrix for the reconstruction of railway between Nsanje and
Border (Marka) (26.4 km).
10 - 64
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-29 Scoping Matrix for Reconstruction of Railway between Nsanje and Border (1/2)
Construction
Non-project
Operation
Phase
Phase
Impact Outline
5 Existing social infrastructure and B B+ D - No significant impact on the mobility of people is expected because
services only freight trains are planned to operate on this section.
6 Poor, indigenous and ethnic D B+ B - The reconstruction will benefit all strata of the local population,
people including the poor.
7 Misdistribution of benefit and D D D - Equal employment opportunities for the local population can avoid the
damage misdistribution of benefit.
8 Cultural heritage C C D - One cultural site has been identified near the project area. It is
necessary to confirm the locations of cultural sites at the F/S stage.
9 Local conflicts of interest D D D - There is no significant local conflict caused by the reconstruction
project.
10 Water usage or water rights C C D - Major damage to water usage by the local population is not anticipated,
but it is necessary to confirm water sources near the railway line.
11 Sanitation C D D - The construction camp will adversely affect sanitation if proper
measures are not taken.
12a Hazards (risks) B B+ B - The occurrence of floods and overflow of water on the railway are
expected to be minimised by the improved drainage system.
12b Infectious diseases such as B B B - In general, construction workers could increase the prevalence of HIV
HIV/AIDS and other infectious diseases if proper preventive measures are not
taken.
13 Topography and geographical D D D - The project site is on the flat plain in the Lower Shire Valley and a
features major impact on geographical features is not expected.
14 Soil erosion B B+ A - Soil erosion due to excavation is not anticipated because there are only
wadis where reconstruction of bridges is planned.
- Soil erosion of wadis only during the rainy season will be minimised
by the improved drainage system.
15 Groundwater C C D - In-situ piling of the foundation of bridge for reconstruction will have
adverse effects on groundwater. Appropriate consideration for existing
Natural Environment
10 - 65
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-29 Scoping Matrix for Reconstruction of Railway between Nsanje and Border (2/2)
22 Air pollution B B+ D - Dust and other air pollutants are expected to be produced during the
reconstruction.
23 Water pollution B D D - Accidental leakage of fuel/oil and discharge of sewage from the toilets
and food courts of the construction camp into surrounding water flows
may occur if appropriate measures are not taken.
24 Soil contamination B C D - During the reconstruction, some chemical grouting is expected to cause
soil contamination.
25 Waste B C D - Solid waste will be produced during the road improvement process,
starting with surplus soil and rocks from the excavation work and also
metallic parts, cut wood from railway sides and slopes, and food waste
from construction workers.
26 Noise and vibration B B D - Trucks and heavy equipment working along the road will be noisy and
cause vibration.
Pollution
10 - 66
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
The Study Team proposed the preliminary design for the reconstruction of the S151 road
between Makhanga and Bangula and rehabilitation and reconstruction of the railway between
Limbe and Border (Marka). In order to avoid or alleviate the possible impacts of the Project,
mitigation measures should be taken during the construction and operational phases of the
Project. The expected negative impacts identified in the scoping matrices and possible
mitigation measures are shown in Table 10-30. These mitigation measures should be discussed
with stakeholders at public consultation meetings during the course of the F/S.
10 - 67
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-30 Anticipated Negative Impacts and Proposed Mitigation Measures (1/2)
10 - 68
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Table 10-30 Anticipated Negative Impacts and Proposed Mitigation Measures (2/2)
The consultation with stakeholders aims to encourage stakeholders to understand the project
needs, the project design, and the adverse impacts on the environment and society. In the Study,
consultations with stakeholders were held according to the following schedule:
• April 2011: First Technology Transfer Seminar in Lilongwe and Blantyre
• October 2011: Second Technology Transfer Seminar in Lilongwe and Blantyre
• November and December 2011: Consultation with related District Councils
• January 2012: Third Technology Transfer Seminar in Lilongwe and Blantyre
10 - 69
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Consultation Major Items Explained Items Discussed related to Environmental and Social
Considerations
First Technology Explanation of progress of No specific discussions related to environmental and social
Transfer Seminar study for preparation of the considerations.
Master Plan
Second Technology Explanation of outline of Question: How to determine the compensation cost for resettlement?
Transfer Seminar the Master Plan Response: The level of compensation will be determined based on
standards defined by district and RA (RA).
Question: Who is going to carry out the EIA?
Response: During the F/S stage, an independent consultant employed
by RA or MoTPI will carry out the EIA. (RA)
Consultation with Possible improvement plans * Process of resettlement and land acquisition in Nsanje District.
Nsanje District Council for road and railway * There are frequent flood damages in Makhanga and Chiromo.
and other related * Members of the boat association and vendors carrying out business
personnel near the boat landing point will lose their main source of income by
(see Appendix 5) construction of the Chiromo Road Bridge.
* Members of the bicycle taxi association may be affected by
construction of the Chiromo Road Bridge.
* Vendors in the Makhanga Market should be resettled if the existing
road alignment is improved.
* There are irrigation system from shallow wells between Makhanga
and the Chiromo.
Third Technology Explanation of outline of Comment: The EIA should be carried out at an early stage of the F/S
Transfer Seminar the Master Plan and Pre-F/S because of the size of the project.
Question: How much will the amount of compensation be?
Response: There is no standard compensation amount. It is calculated
based on the building and number of valuable trees, such as mango
and banana trees.
Comment: During the construction of projects, there were problems of
increased prevalence of HIV/AIDS among the workers of a contractor.
Mitigation measures should be noted in the report.
Source: Study Team
10 - 70
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
Waste Dumping of waste at appropriate places instructed by related District Council During construction work
District Councils. Contractor
Environmental management plan of a contractor to protect
the environment.
Accident Installation of warning signs and assignment of security staff Execution Agency, During construction work
in populated areas during construction. Contractor
Installation of traffic safety devices in populated area and Execution Agency, During construction work
near schools. Contractor and operation period
Installation of warning signs and barriers at major level Execution Agency, During construction work
crossings, and assignment of guard personnel at level Contractor and operation period
crossings and Kamuzu Truss Bridge to control vehicle
traffic.
Traffic safety education at primary schools Execution Agency, During construction work
Ministry of and operation period
Education
10 - 71
Project for the Study on Development of the Sena Corridor Final Report
Chapter 10 Environmental and Social Considerations
10 - 72
CHAPTER 11
INSTITUTIONAL ARRANGEMENTS
FOR IMPLEMENTATION OF
THE MASTER PLAN PROGRAMME
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
RA under MoTPI is currently responsible for the planning, design, construction and O&M of
Main, Secondary and Tertiary roads, while district assemblies are responsible for budget
allocation for improving other local roads. RA has implemented projects with general
government budget, financial assistance from foreign development partners, and allocation from
the Road Fund, which is funded by a fuel levy collected from sales of fuel in Malawi.
Improvement of most of the arterial roads in the Study Area is expected to be completed in
the medium term (2020), and O&M works to secure the functions of road assets will become
more important in the near future.
Therefore, the following programmes are considered to be desirable to maintain existing and
newly improved road assets to secure their functions.
• Routine maintenance work such as cleaning ROW and small-scale repairs of pavement
surface should be carried out according to the O&M programmes.
• Periodic maintenance works such as pavement repair or overlay works should be carried out
according to the O&M programmes. The road database with the Highway Development and
Maintenance Model 4 (HDM-4) is a suitable tool for identifying the priority of road sections
for periodic maintenance, as RA has already introduced this model.
• Inspection and maintenance of drainage structures and bridges should be carried out
annually to identify and repair/clean disorderly parts of structures.
The Road Fund is the most appropriate resource for these periodic and routine maintenance
works, as the revenues of the Road Fund each year are reasonably stable. However, the Road
Fund should not be allocated to development projects, in order to leave sufficient funding for
O&M.
O&M of local roads can be performed as part of community development programmes as
these roads cannot be improved as economically reliable projects.
The institutional arrangements for the railway sub-sector have various functions and
structures. The functions range from information-sharing and consensus-building to the
planning and implementation of rehabilitation/reconstruction projects. Each function of an
arrangement can be used to establish institutional arrangements as follows:
(1) Objectives
The main objectives of the institutional arrangements are:
11 - 1
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
11 - 2
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
Each option has its advantages and disadvantages. In the context of options of ownership and
operation of the railway, the following alternatives may be evaluated:
• The GoM rehabilitates the dilapidated railway facilities and operates the trains on its own by
creating a central authority.
• The GoM rehabilitates the dilapidated railway facilities on its own, but gives the right to
operate the trains to an independent operator on a revenue-sharing basis under a concession
agreement for a fixed-period tenure. In this arrangement, the GoM retains ultimate
ownership of either the physical assets or the right to supply, but grants operation rights to a
concessionaire. The concessions include leasing, franchising and BOT arrangements.
(6) Examination of Implementing Organization
MoTPI acts as an implementing organization of the rehabilitation project. It should exchange
a revised concession contract with CEAR and implement financing, EPC (engineering, purchase,
and construction), and O&M (operation and maintenance) of the Branch Line of the Sena
Railway. The project implementation structure of the rehabilitation is shown in Figure 11-1.
To decide the freight tariff, a tariff policy is required. The tariff policy should be established
based on a system of definite unified principles and priorities, rules and methods of the operator
regarding rolling stock, freight cars handled, and transit by freight tariff.
The main objective of the tariff policy is to preserve the balance between the operating
company and service consumers, for which the following matters should be considered:
11 - 3
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
GoM
Grant Aid
or Loan ODA
MoTPI
from international donors
Debt
Rehabilitation Contract
EPC Contractor Private Banks
Railway Division
(Management Authority
for Railway)
O&M contract
Administrative Management - Right of Concession
on Train Operation &
- Land Provision
Maintenance
- Partial Investment
- Subsidies
- Tax Incentive
Private Company Equity
(Vale, etc.) CEAR
11 - 4
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
The current concession with CEAR will expire in 2019. According to the concession
agreement, both parties should discuss revision or extension of the agreement 5 years before
expiration of the contract. Therefore, the discussion will start within 3 years from now.
This clause describes general matters regarding the concession to assist the revision of the
concession scheme.
(1) Characteristics of Railway Concessions
From a macroeconomic perspective, Malawi faces important structural changes to maintain
sustained economic growth and improve living standards. It requires more transport services to
import and export products. To provide stable transport services, operation and maintenance of
the railway were shifted from public to private operation by CEAR as a concession. However,
this concession has not worked well.
The “Review of Selected Railway Concessions in Sub-Saharan Africa” by the WB analyses
the major characteristics of railway concessions in Sub-Saharan Africa as follows:
• There is no evidence of a clear link between tariffs and rail market share. Instead, a strong
correlation exists between tariff levels and commodity value.
• The threat of the transport mode shifting from rail to road limits railway operators’ ability to
charge excessive tariffs to their customers.
• Increasing the competitiveness of rail appears to benefit transport users first through lower
road rather than rail transport costs.
• The profitability results achieved by private rail operators in terms of net income, net cash
flow and return on equity do not suggest excessive profiteering.
• Concession contracts generally contain an array of clauses designed to protect rail users
against excessive market/pricing power of rail operators. However, their enforceability
remains questionable due to information asymmetry between concessionaires and
regulators. Weak technical and financial capacity will limit the regulator’s enforcement
ability.
(2) Forms of Private-Sector Participation
There are many forms of private-sector participation (PSP) as summarized in Table 11-1. The
current concession with CEAR is one form of private-sector participation.
The forms of concession are summarized as follows:
• Operation management is conducted by the private sector.
11 - 5
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
11 - 6
Project for the Study on Development of the Sena Corridor Final Report
Chapter 11 Institutional Arrangement for Implementation of the Master Plan Programme
11 - 7
CHAPTER 12
CAPACITY DEVELOPMENT
PROGRAMME
Project for the Study on Development of the Sena Corridor Final Report
Chapter 12 Capacity Development Programme
The Study consists of a comprehensive transport master plan covering the road, railway and
inland waterway sub-sectors and a pre-F/S of selected priority projects in the Southern Region
of Malawi and Mozambique. Personnel in the executing agency, MoTPI, and other related
agencies have had limited experience of being involved in the preparation of transport master
plans in the past and it was desirable for them to learn the process of formulating a transport
master plan and understanding its contents for implementation in the near future.
The Study Team planned a capacity development programme in order to improve the skills of
counterpart personnel in related agencies in preparing a transport master plan and conducting a
pre-F/S of selected priority projects to improve the roads and railways in the Study Area.
Capacity development was planned to be carried out mainly through on-the-job (OJT)
training while Japanese experts were carrying out their studies in Malawi. The main activities of
the capacity development programme are as follows:
• Accompanying field surveys
• Discussion in the Working Group meetings
• Peer review of draft reports
• Preparation of materials for technology transfer seminars
• Presentation at technology transfer seminars
In addition to the capacity development in the Study, JICA selected one counterpart
personnel for one of the Training and Dialogue Programmes entitled “National and Regional
Development Policy” which was carried out in Japan and Malawi between August 2011 and
January 2012 with the Core Phase conducted in Japan from September to October 2011. This
programme was designed to give participating government officers lectures on practical
planning methods and management capacity, so that they could plan national and regional
development policies or schemes useful for regional development in their countries in an
appropriate manner according to particular social situations.
Since the commencement of the Study in October 2010, the following capacity development
activities have been performed with the active involvement of counterpart personnel to improve
their skills.
• Accompanying Study Team members of respective fields to assist supervision of the road
inventory survey, railway inventory survey, traffic survey, logistics survey and field
observation for social and environmental considerations carried out by local consultants
(November 2010 to February 2011)
• Discussion in the Working Group Meeting for road and railway planning, hydrological
analyses, traffic demand forecasting, and environmental and social considerations (first
12 - 1
Project for the Study on Development of the Sena Corridor Final Report
Chapter 12 Capacity Development Programme
meeting on 2nd November 2010, second meeting on 25th November 2010, third meeting on
21st January 2011, fourth meeting on 9th June 2011, fifth meeting on 14th December 2011)
• Peer review of draft of the Progress Report, the Interim Report and the Draft Final Report
by counterparts of road planning, road design, railway planning, and social and
environmental considerations (March, September and December 2011)
• Preparation of materials for the first and second technology transfer seminars by
counterparts of road planning and railway planning (March and October 2011)
• Presentation at the first technology transfer seminars by two counterpart personnel on the
following contents (15th April 2011 at Lilongwe and 18th April 2011 at Blantyre):
Present situation of the road network in the Study Area (Counterpart of road planning)
From a perspective of railways (Counterpart of railway planning)
• Presentation at the second technology transfer seminars by three counterpart personnel on
the following contents (26th October 2011 at Lilongwe and 28th October 2011 at Blantyre):
Development of the road network in the Study Area (Counterpart of road planning)
From a perspective of railways (Counterpart of railway planning)
Environmental and social considerations (Counterpart of environmental and social
considerations)
• Presentation at the third technology transfer seminars by three counterpart personnel on the
following contents (24th January 2012 at Lilongwe and 26th January 2012 at Blantyre):
Pre-F/S on Reconstruction of S151 Road between Makhanga and Bangula (Counterpart
of road planning)
Pre-F/S on Rehabilitation/Reconstruction of the Railway between Limbe and Border
(Marka) (Counterpart of railway planning)
Initial Environmental Evaluation of Projects for Pre-F/S (Counterpart of transport
planning)
Table 12-1 shows the capacity development programme in the Study.
During the course of the Study from commencement up to the end of December 2011, the
following counterpart personnel actively worked together with the Study Team to improve their
ability to prepare the transport master plan and pre-F/S for both the road and railway projects,
even though the number of personnel in the executing agencies is limited and they have their
existing duties.
• Railway Planning: Controller of Rail Transport Services, MoTPI
• Transport Planning: Transport Economist of Planning Dept. MoTPI
• Road Planning: Civil engineer of Road Dept. MoTPI
• Economic Evaluation: Transport Specialist, RA
• Bridge Planning: Senior Engineer, RA
12 - 2
Project for the Study on Development of the Sena Corridor Final Report
Chapter 12 Capacity Development Programme
Environmental
and Social
Consideration
Railway Study
Economic and
Financial
Analyses
Hydrological
Study
Road Planning
Study
Preparation for
Seminar
Working
Group
Meeting
Source: Study Team
12 - 3
CHAPTER 13
CONCLUSIONS AND
RECOMMENDATIONS
Project for the Study on Development of the Sena Corridor Final Report
Chapter 13 Conclusions and Recommendations
Conclusions for the Master Plan of Development of the Sena Corridor and the Pre-F/S of
projects selected in the Master Plan are as follows:
• The Basic Policy for development of the Sena Corridor is proposed in line with the national
development policy for sustainable economic growth and poverty alleviation in three main
areas: Southeastern Africa, Malawi and the Study Area.
• Based on the Basic Policy, development of the Sena Corridor is examined in terms of the
international north-south axis, the domestic north-south axis and arterial transport networks
in the study area, and then the targeted international transport corridor and arterial transport
network in the study area are identified. The development of transport infrastructure in
Mozambique is defined as an external factor and it is assumed that both the road and railway
will be developed up to 2030.
• Master Plans for the road and railway sectors are proposed divided into three terms, i.e.
short-term (2015), medium-term (2020) and long-term (2030), followed by the
Development Concept and Strategy for both sectors. Among the three alternatives, the entire
transport network including both the road and railway connecting to Beira Port is evaluated
as the most desirable for the Master Plan in terms of economic evaluation (EIRR=17.1%),
environmental impact and transportation.
• The proposed projects for the Master Plan in the Study, which consist of four road projects
(M1, S151, S152 and D379) and three packages (railway line rehabilitation and
reconstruction, procurement of rolling stock, and installation of signal and
telecommunication system) of railway projects, are judged as technically and economically
feasible. Hence, it is necessary to start preparing an investment programme for the Master
Plan.
• The projects in the Master Plan will greatly contribute to sustainable economic growth,
poverty alleviation and improvement of living conditions in the Study Area by improving
access to rural growth centres from local communities, particularly from isolated
communities with very limited access at present.
• These projects will also contribute to sustainable economic growth, improve the
international competitiveness of export products, and strengthen the redundancy of the
transport network in Malawi by improving access to ocean ports and international markets
for exporting cash crops and importing fuel and fertilizer from a view point of Malawi.
• These projects will strengthen the international north-south axis in the region by creating an
alternative international transport corridor to/from Beira Port from a view point of
Southeastern Africa.
13 - 1
Project for the Study on Development of the Sena Corridor Final Report
Chapter 13 Conclusions and Recommendations
• The Selected road project for the Pre-F/S, i.e., ”Reconstruction of S151 Road between
Makhanga and Bangula”, is judged as technically and economically feasible, based on the
preliminary design for improvement of the road section between Makhnaga an Bangula, and
construction of the Chiromo Road Bridge and the New Shire Bridge for the short term and
medium term programme.
• The Selected railway project for the Pre-F/S, i.e., ”Rehabilitation and Reconstruction of the
Railway between Limbe and Border (Marka)” is technically and economically feasible,
based on the preliminary design of rehabilitation and reconstruction of railway line,
including tracks and road bed, bridges, including the Chiromo Railway Bridge, installation
of a signalling/telecommunication system, and procurement of rolling stock. Financial
analysis results also indicate that the project will also be feasible.
• Results of IEE for both road and railway projects identified minimal negative environmental
and social impact as a result of these projects.
13 - 2
Project for the Study on Development of the Sena Corridor Final Report
Chapter 13 Conclusions and Recommendations
13.4 Recommendations
Recommendations for the Master Plan of Development of the Sena Corridor and Pre-F/S of
priority projects in the Master Plan are as follows:
(1) Recommendations for the Project Implementation
• The GoM will have to continue dialogs with counterparts in the GoMZ after the first
dialogue in November 2011, since it is necessary to coordinate with the GoMZ for
13 - 3
Project for the Study on Development of the Sena Corridor Final Report
Chapter 13 Conclusions and Recommendations
implementing projects in the Master Plan. The main topics to be discussed are
reconstruction of the branch line of the Sena Railway between Villa Nova de Frontera and
Dona Ana and improvement of the secondary roads N300 and N322 between Villa Nova de
Frontera and Caja via Mutarara.
• MoTPI can inform the outcome of the Master Plan as well as the Pre-F/S, particularly
“Reconstruction of S151 Road between Makhanga and Bangula” and “Rehabilitation and
Reconstruction of Railway between Limbe and Border (Marka)”, to development partners
for possible assistance with project implementation.
• MoTPI should carry out the F/S of priority projects identified as feasible under the Pre-F/S
at an early stage. Also, MoTPI should carry out a full-scale EIA, including public
consultations, during the course of the F/S for both the road and railway projects.
• MoTPI should allocate sufficient budget to the compensation for resettlement and land
acquisition necessary for executing the projects based on the results of the F/S.
(2) Recommendations for the Institutional Arrangements
• RA can consider changing the classification of S151 to “Main Road” after the completion of
upgrading to create complete arterial network in the Study Area.
• MoTPI needs to secure adequate budget for operation and maintenance of the road
sub-sector to maximise the use of existing road assets, including M1 between Blantyre and
Marka, S151 between Thyolo and Bangula, S152 between Thabwa and Seven, and S136
between Chikwawa and Muwanza.
• MoTPI needs to strengthen the organisation of the Railway Division (increase number of
staff from two at present) in the and develop capacity of personnel (to train newly appointed
or young staff to give them knowledge of railway management, operation and maintenance),
and revise Railway Act to supervise and check the performance of CEAR.
• MoTPI will have to review the present concession with CEAR starting from 2014. The past
performance of CEAR in management and operation of railway lines in Malawi will require
carefully checking.
13 - 4