Magnum MS2812 64-0007-12-04-MS-Manual
Magnum MS2812 64-0007-12-04-MS-Manual
Magnum MS2812 64-0007-12-04-MS-Manual
Operators Manual
IMPORTANT SAFETY INSTRUCTIONS
To reduce the risk of electrical shock, fire, or other safety hazard, the follow-
ing safety symbols have been placed throughout this manual to indicate
dangerous and important safety instructions.
All electrical work must be performed in accordance with local, state and
federal electrical codes.
Read all instructions and safety information contained in this manual before
installing or using this product.
Remove all jewelry such as rings, watches, bracelets, etc., when installing or
performing maintenance on the inverter.
Live power may be present at more than one point since an inverter utilizes
both batteries and AC.
Wear eye protection such as safety glasses when working with batteries.
Remove all jewelry such as rings, watches, bracelets, etc., when installing or
performing maintenance on the inverter.
Never work alone. Always have someone near you when working around
batteries.
Never use old or untested batteries. Check each battery's label for age, type
and date code to ensure all batteries are identical.
Provide at least one inch of air space between batteries to provide optimum
cooling.
To prevent a spark at the battery and reduce the chance of explosion, always
connect the cables to the batteries first. Then connect the cables to the
inverter.
Always verify proper polarity and voltage before connecting the batteries to
the inverter.
Table of Contents
Section Description Page
1. Introduction 1
1. Features and Benefits 1
2. Standard Features 1
3. How an Inverter/Charger Works 2
4. Advantages of a Pure Sine Wave Inverter 3
5. Appliances and Run Time 3
6. The MS Series Inverter/Charger 5
7. MS Series Neutral-to-Ground Safety System 6
2. Installation 7
1. Unpacking and Inspection 7
2. Pre-Installation 7
Locating the Inverter 7
Locating Dedicated Batteries (optional) 7
Hardware / Materials Required 8
Tools Required 8
Wiring 8
AC Connections 8
DC Connections 8
AC Grounding 8
DC Grounding 8
Torque Requirements 9
AC Main Panel 9
Circuit Protection 9
Wire Routing 9
3. Installation 10
Inverter Mounting 10
Ventilation Requirements 10
Battery Installation 11
Battery Cables and Sizing 12
DC Wiring 12
DC Grounding 12
Negative Cable 12
Positive Cable 12
Battery Wiring 13
Parallel Connection 13
Series Connection 15
Series/Parallel Connection 15
DC Fuse Block 17
AC Wiring 19
AC Input (Shore Power) Routing 19
AC Input (Generator) Routing 19
Main AC Electrical Panel Routing 19
Wiring the Inverter AC Input 21
Wiring the Inverter AC Output 21
Final Inspection 21
2. Installation, continued
4. Options 25
Battery Temperature Sensor Installation and Wiring 25
Remote Control Installation and Wiring 25
AGS Module 25
Smart Shunt 25
Stacking Cable Kit 25
5. Start-up and Test 26
Connecting the Batteries to the Inverter 26
Final Inspection and Power-up 26
Configuring the Inverter 27
3. Operation 28
1. Operating the Inverter 29
Search 29
Inverter Mode 29
AC Shore Power Mode 29
Bulk Charge Mode 29
Absorption Charge Mode 29
Float Charge Mode 29
Battery SaverTM Mode 29
Fault or Alarm Conditions 31
Low Battery 31
High Battery 31
Overload 31
Overtemperature 31
4. Troubleshooting 33
1. Basic Troubleshooting 33
5. Preventive Maintenance 34
1. Recommended Inverter and Battery Care 34
2. Off-Season Storage 34
6. Specifications 35
7. Warranty 36
The MS Series inverter is ETL Listed meeting the stringent requirements of UL458,
ensuring you the highest level of electrical safety and reliability.
2. Standard Features
• 2000, 2800 or 3600 Watt Models with 125 Amp Battery Charger
• Shelf, Bulkhead or Upside Down Mounting
• Pure Sine Wave Output
• Power Factor Corrected Charger (Sine Wave)
• RS485 Standard
• Remote Port
• Network Port
• Flash Programming
• ON/OFF Inverter-mounted Switch with LED Indicator
• 50 Amp Transfer (on Dual IN / Dual OUT Models)
• Extra Large AC Access Cover with Terminal Screw Block
• 360 degree DC Connection Terminals with Covers
• Battery Temperature Sensor - for optimum battery charging
• Aluminum Cover
• Smooth, Aesthetically Pleasing Design
• ETL listed to UL/cUL 458
An inverter takes direct current (DC) from your batteries and turns it into alter-
nating current (AC), exactly like you use at home. It also takes alternating current
(when connected to shore power) and transforms it into direct current to recharge
your batteries.
Charger Mode:
Alternating current (AC) is taken directly from shore power (or other AC sources)
and passed directly to your household appliances. At the same time, the incoming
AC is also converted to DC to recharge the vehicles batteries.
Figure 1
MS Series Inverter / Charger
Todays inverters come in two basic output waveforms: modified sine (which is
actually a modified square wave) and pure sine wave. Modified sine wave inverters
approximate a pure sine waveform and will run most appliances and electronics with-
out any problems. These inverters are less expensive and, therefore, offer a viable
alternative to more expensive pure sine inverters.
The output of a pure sine wave inverter is equal to or, in many cases, better than
the grid power used in your home. Virtually any electronic device will operate from a
pure sine wave inverter. Motors run cooler, microwaves usually cook faster and clocks
keep better time just to name a few examples. Without compromising quality or
performance, the MagnaSine provides you with all of the advantages of a pure sine
wave inverter at a much lower cost than many on the market.
The MagnaSine is built on the same platform as our popular ME Series modified
sine wave inverters allowing for an easy upgrade from the original ME installation.
This standard platform also helps reduce cost by using standard parts across many
models. All Magnum accessories such as the Remote Controller, AGS (AutoGen Start),
and network accessories are standard for all ME, RD and MS Series inverters.
Power ON/OFF
Switch
Charging / Inverting
LED
Stack Port
Magnum Net Port
Remote Port
Figure 2
MS Series Inverter / Charger
Switch, LED and Connection Ports
AC Connections DC Connections
Figure 3
MS Series Inverter / Charger
Electrical Connection Points
Remote Control Port - accepts connector for Magnum remote control cable.
BTS Port - accepts connector for remote battery temperature sensor cable.
MagnumNet Communication Port - accepts connector for Auto Gen Start or Smart
Shunt (DC current display) cable.
Positive Battery Terminal - provides 360 degree connection point for the positive
(+) cable from the vehicles batteries.
Negative Battery Terminal - provides 180 degree connection point for the
negative (-) cable from the vehicles batteries.
Figure 4
MS Series Inverter / Neutral-to-Ground Safety System
Carefully remove the MS Series inverter from its shipping container and inspect all
contents. If items appear to be missing or damaged, contact Magnum Energy
at (425) 353-8833 or your authorized Magnum Energy dealer. If at all possible,
retain the shipping container in the event the unit ever needs to be returned for
factory service.
2. Pre-Installation
Before installing the inverter, read all of the instructions and cautionary markings
contained in this manual.
NOTE: The inverter is heavy. Use proper lifting techniques during installation to
prevent personal injury.
Allow enough clearance to access the AC and DC connection points as well as the
inverters controls and status indicator. As with any inverter, it should be located as
close to the batteries as possible. Longer battery cable runs tend to loose efficiency
and reduce the overall performance of an inverter.
If you are planning to install dedicated batteries, other than the vehicles, make
sure they are in a dedicated compartment that has ventilation to the outside. Also it
is important that you never mount the inverter directly above the batteries as they
emit corrosive fumes which could damage the inverters electronics.
CAUTION: Never locate dedicated batteries near the vehicles fuel tanks
containing gasoline or propane.
2. Pre-Installation, continued
Tools Required
Misc screw drivers Level 1/2" wrench
Drill and drill bits Pliers Wire strippers
Level Pencil or Marker Multimeter
Wiring
Pre-plan the wire and conduit runs. For maximum safety, run both AC and DC
wires/cabling in (separate) conduit. Direct current wiring, due to its potential to
generate RFI, should be tied together with electrical tape. Wiring and installation
methods must conform to all applicable electrical codes.
NOTE: Run DC cabling in twisted pairs, keeping the runs as short as practical.
AC Connections
Use #10 AWG (or larger) THHN wire for all AC wiring. The inverters AC terminal
blocks accept up to #6 AWG wire.
DC Connections
Battery to inverter cabling should be only as long as required. If using #2/0 AWG
cables, do not exceed 5 feet (one way) for 12 VDC systems.
Crimped and sealed copper ring terminal lugs with a 5/16 hole should be used to
connect the battery cables to the inverters DC terminals.
AC Grounding
The MS Series inverter/charger contains an internal neutral-to-ground switching
circuit for the AC electrical system.
DC Grounding
The inverter/charger should always be connected to a permanent, grounded
wiring system. For the majority of installations, the negative battery conductor is
bonded to the vehicles safety-grounding conductor (green wire) at only one point in
the system. The size for the conductor is usually based on the size of the largest
conductor in the DC system. DO NOT connect the battery negative (-) cable to the
vehicles safety ground. Connect it only to the inverters negative battery terminal.
If there are any non-factory installed DC appliances on board the vehicle, DO NOT
ground them at the safety ground. Ground them only at the negative bus of the DC
load center (as applicable).
2. Pre-Installation, continued
Torque Requirements
Torque all AC wiring connections to 16 inch pounds. Torque DC cable connections
to 10-12 foot pounds.
AC Main Panel
If the installation will be powering a wide-range of appliances throughout the
vehicle, an AC main panel is often recommended. This is similar in appearance and
function as your homes circuit breaker panel, providing an additional level of control
and protection for the various circuits. Always refer to electrical codes for safe wiring
practices.
Circuit Protection
If using a AC main panel for distribution, always use breakers that provide the
correct ampere branch circuit protection in accordance with the National Electric
Code. The breakers must be properly rated for the appliances being powered.
Wire Routing
Determine all wire routes throughout the vehicle both to and from the inverter.
Conductors that are at risk to physical damage must be protected by conduit, tape,
or placed in a raceway. Conductors passing through walls, bulkheads or other struc-
tural members must be protected to minimize insulation damage such as chafing.
During the installation, always avoid placing conductors near sources of chafing
caused by vibration or constant rubbing.
3. Installation
NOTE: Read all instructions and cautionary markings located at the beginning of this
manual and in the pre-installation section, before installing the inverter and
batteries.
CAUTION: Do not mount the inverter or the batteries near the vehicles
gasoline or propane fuel tanks.
Provide adequate clearance and ventilation to the inverter
Mount the inverter only on a noncombustible surfaces.
Maximum abient temperature MUST NOT exceed 113 °F (45 °C).
For Canadian installations, the inverters vents must face
downward.
Inverter Mounting
Position the inverter in the designated mounting location: shelf, bulkhead or up-
side-down. Allow enough clearance to access the AC and DC connection points as
well as the inverters controls and status indicator. Also allow for air flow in to and
around the inverter, especially near the cooling fans (approximately 3).
Mark the mounting holes in the base of the inverters chassis. Remove the in-
verter and drill pilot holes into the mounting surface.
Secure the inverter to the mounting surface using appropriate screws and lock
washers.
Remove the inverters AC access panel in accommodate the AC Input and Output
wiring and conduit.
Ventilation Requirements
In order to provide optimum performance, longer inverter life and reliability, and
avoid "Overtemp" fault conditions," clearances around the inverter MUST be:
Side and Back: 3 minimum - Front (with DC connections): 6" minimum
If the inverter is mounted in an enclosed compartment, airflow must be at
least 100 cfm in order to maintain no more than a 20 0C degree rise in compartment
temperature. Minimum clearances can be reduced if airflow is increased, but in no
case should clearance around inverter be less than 2" on all sides.
If an "Overtemp" faults occur, reduce the load or increase ventilation to the
inverter.
Mounting Screw
Placements
Figure 5
MS Series Inverter / Charger Base Plate
10 2004 - Magnum Energy, Inc.
2. INSTALLATION
3. Installation, continued
Battery Installation
NOTE: To ensure the best performance from your inverter system, do not use old or
untested batteries. Batteries must be of the same size, type, rating and age.
NOTE: If using Flooded Lead Acid batteries, they must be mounted upright.
CAUTION: Install batteries in a well ventilated area. Batteries can produce explosive
gasses. For compartment or enclosure installations, always vent batteries
to the outside.
Secure the batteries to the mounting surface with battery hold down clamps.
3. Installation, continued
Battery cables must be color coded with colored tape or heat shrink tubing: RED
for positive (+); BLACK for negative (-); and GREEN for DC ground.
The cables must have soldered and crimped lugs, crimped copper compression
lugs, or aluminum mechanical lugs. Soldered connections alone are not acceptable
for this application.
DC Wiring
Refer to the safety information at the beginning of the manual before proceeding. DC
wires and cables should be tied together with wire ties or electrical tape approxi-
mately every 6 inches.
NOTE: DO NOT connect the battery cables to the inverter until all wiring is complete
and the correct DC voltage and polarity has been verified.
NOTE: Make sure cables have a smooth bend radius and do not become kinked.
Place long cable runs in conduit and follow existing wire runs where possible.
DC Grounding
Route a grounding cable (GREEN) from the inverters ground lug to a dedicated
vehicle ground.
Negative Cable
Route a negative cable (BLACK) from the house battery bank (or dedicated bat-
tery compartment) to the inverters negative terminal
Positive Cable
Route a positive cable (RED) from the house battery bank (or dedicated battery
compartment) to the Fuse Block assembly (DC Disconnect). The DC disconnect is
usually located next to or near the batteries. DO NOT connect the positive cable to
the batteries at this time.
Route a positive cable (RED) from the Fuse Block assembly (DC Disconnect) to
the
inverters positive terminal DO NOT connect the positive cable to the inverter at this
time.
12 2004 - Magnum Energy, Inc.
2. INSTALLATION
3. Installation, continued
Battery Wiring
WARNING: During the installation and wiring process, cover exposed battery
cable ends with electrical tape to prevent shorting the cables.
NOTE: DO NOT connect the positive cable to the inverter at this time.
Depending upon the type of battery you use in the installation (6 or 12 VDC), the
batteries must be wired in series, parallel or series/parallel to provide 12 VDC. The
interconnecting battery cables must be sized and rated exactly the same as those
that used to connect the inverter.
When connecting the cable to the battery terminal, hardware should be installed
in the following order: bolt, ring washer, cable lug, (battery terminal), ring washer,
lock washer, nut. Tighten terminal connections to at least 10 to 12 foot pounds.
When two cables are connected to a terminal (i.e., negative terminal), the hard-
ware should be installed in the following order: bolt, ring washer, DC negative cable
lug, inverter negative cable lug, (battery terminal), ring washer, lock washer, nut.
Parallel Connection
(multiple 12 VDC batteries to create a 12 VDC string)
A parallel connection combines overall battery capacity by the number of batter-
ies in the string. Even though there are multiple batteries, the voltage remains the
same. In the example on the next page (Figure 7), four, 12 VDC, 100 AHr batteries
are combined into a single string, resulting in a 12 VDC, 400 AHr bank.
Connect the negative battery cable (BLACK) from the inverter to the negative
terminal of the end battery. At the same time, connect a DC ground cable between
the negative terminal and the vehicles DC grounding bus.
Connect the positive (RED) battery cable from the inverter to the positive termi-
nal of the battery at the opposite end of the string. This is essential to ensure even
charging and discharging across the entire battery string.
NOTE: A fuse must be placed between the positive terminal and the positive (RED)
battery cable to the inverter.
Once the batteries are completely wired and tested, coat the terminals with an
approved anti-oxidizing spray.
Nut - Washer - Lug - Terminal - Washer - Bolt Nut - Washer - Lug - Inverter Terminal
Figure 6 Figure 7
Battery Hardware Installation Inverter Hardware Installation
>
+
+ + + +
- - - -
-
>
Figure 8
Parallel Battery Wiring
individual battery capacity = 100 AHr @ 12 VDC
combined battery capacity = 400 AHr @ 12 VDC
>
+
+ + + +
- - - -
-
>
Figure 9
Series Battery Wiring
individual battery capacity = 200 AHr @ 6 VDC
combined battery capacity = 200 AHr @ 24 VDC
>
+
+ + + +
- - - -
-
>
Figure 10
Series/Parallel Battery Wiring
individual battery capacity = 200 AHr @ 6 VDC
combined battery capacity = 400 AHr @ 12 VDC
14 2004 - Magnum Energy, Inc.
2. INSTALLATION
3. Installation, continued
Series Connection
(four 6 VDC batteries to create a 24 VDC bank)
A series connection combines overall battery voltage by the number of batteries
in the string. Even though there are multiple batteries, the capacity remains the
same. In the example at the left (Figure 8), four 6 VDC, 100 AHr batteries are com-
bined into a single string resulting in a 24 VDC, 200 AHr bank.
Connect the negative battery terminal of one battery to the positive of the other
using a short cable.
Connect the negative battery cable (BLACK) from the inverter to the open nega-
tive terminal of one of the batteries. At the same time, connect a DC ground cable
between the negative terminal and the vehicles DC grounding bus.
Connect the positive battery cable (RED) from the inverter to the positive termi-
nal of the opposite battery.
NOTE: A fuse must be placed between the positive terminal and the positive (RED)
battery cable to the inverter.
Once the batteries are completely wired and tested, coat the terminals with an
approved anti-oxidizing spray.
Series/Parallel Connection
(four 6 VDC batteries to create a 12 VDC bank)
A series/parallel connection increases both voltage and capacity using smaller,
lower-voltage batteries. In the example at the left (Figure 9) four 6 VDC, 200 AHr
batteries are combined into two pairs resulting in a 12 VDC, 400 AHr bank.
Connect the negative battery terminal of one 6 VDC battery to the positive of the
next (creating a pair) using a short battery cable.
Connect the negative battery terminal of another 6 VDC battery to the positive of
its next using a short battery cable (creating a second pair).
Connect the remaining negative battery terminal of the first pair to that of the
second pair using a short battery cable.
Connect the remaining positive battery terminal of the first pair to that of the
second pair using a short battery cable.
Connect the negative battery cable (BLACK) from the inverter to the end batterys
negative terminal. At the same time, connect a DC ground cable between the nega-
tive terminal and the vehicles DC grounding bus.
Connect the positive battery cable (RED) from the inverter to the opposite end
batterys positive terminal.
NOTE: A fuse must be placed between the positive terminal and the positive (RED)
battery cable to the inverter.
Once the batteries are completely wired and tested, coat the terminals with an
approved anti-oxidizing spray.
In-line fuse
~ >
+
+ + + +
- - - -
-
>
Figure 11
Parallel Battery Wiring - Fuse Placement
In-line fuse
~ >
+
+ + + +
- - - -
-
>
Figure 12
Series Battery Wiring - Fuse Placement
In-line fuse
~ >
+
+ + + +
- - - -
-
>
Figure 13
Series/Parallel Battery Wiring - Fuse Placement
3. Installation, continued
DC Fuse Block
A fuse or circuit breaker must be located within 18 inches of the battery to pro-
tect the DC wiring system. The device must be rated to match the size of the cable,
but can be rounded up to the next larger size (i.e., a cable rated at 150 amps can
accept a 175 amp fuse) as necessary.
Mount the fuse block (or circuit breaker assembly) as near as practical to the
batteries.
Remove the fuse (or open the circuit breaker) and connect a short cable (same
rating as the battery cables) to one end of the fuse block.
Connect the positive cable (RED) from the inverter to the assembly. DO NOT
connect the positive cable to the inverter at this time.
Securely tighten the fuse blocks lugs. Once the entire installation is complete,
reinsert the fuse into the fuse block before connecting the positive cable to the
inverter.
AC Output
Cable Clamp
AC Input
Cable Clamp DC Chassis
Ground
Figure 14
MS Series Inverter / Charger - AC Wiring
AC Access Cover
Figure 15
MS Series Inverter / Charger - AC Wiring (Access Panel)
3. Installation, continued
AC Wiring
NOTE: Read all instructions and cautionary markings located at the beginning of this
manual and in the pre-installation section, before installing the inverter and
batteries.
The minimum wire size for all MS Series models must be #10 AWG. The
installer must provide the appropriate circuit protection for the wire size used.
Refer to appropriate electrical codes for wire sizing and circuit protection.
AC Input (Shore Power) Routing
Route a 30 amp service (shore power) to the inverter. If the installation includes a
generator, route a 30 amp service (shore power) to an approved selector switch and
then to the main AC panel. Route 2-30 amp services for 240 VAC, 50 A applications.
Figure 16
MS Series Inverter / Charger - AC Wiring Diagram
(located on back of cover plate)
AC Ground
Figure 17
MS Series Inverter / Charger - AC Terminal Block
3. Installation, continued
Route the cable and conduit from the main panel, approved bypass selector
switch or main AC panel to the inverters AC INPUT conduit clamp. Tighten
the clamp securely on the conduit. Always leave a little extra slack in the wiring.
Connect the hot wire (BLACK) from the main panels dedicated 30 amp breaker to
the AC INPUT (HOT 1 IN) terminal. Tighten the screw terminal to 16 inch-pounds.
NOTE: If using dual inputs, connect the RED wire from the main panel to AC INPUT
(HOT 2 IN)
Connect the neutral (WHITE) from the main panels neutral bus bar to the AC
INPUT (NEU) terminal. Tighten the screw terminal to 16 inch-pounds.
Connect the ground (GREEN) wire from the main panels neutral bus bar to the
GROUND terminal. Tighten the terminal to 16 inch-pounds.
Connect the hot (BLACK) wire to the AC OUTPUT 1 (HOT) terminal. Tighten the
terminal to 16 inch-pounds.
NOTE: If using dual outputs, connect the RED wire to the AC OUTPUT 2 (HOT)
terminal.
Connect the neutral (White) wire to the AC OUTPUT (NEU) terminal. Tighten the
terminal to 16 inch-pounds.
Connect the ground (Green) wire to the GROUND terminal. Tighten the termi-
nal to 16 inch-pounds.
Final Inspection
Verify all cables / conduit runs are secured with wire ties or other nonconductive
fasteners to prevent chafing or damage from movement and vibration.
Verify strain reliefs or grommets are in place to prevent damage to the wiring or
conduit where it passes through walls, bulkheads or other openings.
AC Ground
Figure 18a
Typical Wiring - Single IN / Single OUT (120 VAC)
Figure 19a
Typical Wiring - Single IN / Dual OUT (120 VAC)
Figure 20a
Typical Wiring - Dual IN / Dual OUT (120 VAC / 240 VAC)
Water Heater
Microwave
Outlets
30 Amp Outlet
TV / Entertainment
Inverted Outlets
Figure 18b
Typical Wiring - Single IN / Single OUT (120 VAC)
Figure 19b
Typical Wiring - Single IN / Dual OUT (120 VAC)
L1
L1 L2 Transfer
Switch
AC Main L2
Breaker Panel L2 L1 Shore
L1 L2 Power
AC Sub-panel 50 Amp Main 50 Amp Main
L1 L2 Generator
30 Amp Main 30 Amp Main 20 Amp 20 Amp
L1 L2 AC Front AC Rear
20 Amp 20 Amp 20 Amp 20 Amp
Microwave Kitchen, Bath Refridgerator Water Heater
20 Amp 20 Amp 20 Amp 20 Amp
Front Outlets Rear Outlets Block Heater Outlets
Spare Spare
L1 L2
Inverter/Charger
30 Amp AC IN 30 Amp AC IN
(Hot) - L1 (Hot) - L2
30 Amp AC OUT 30 Amp AC OUT
(Hot) - L1 (Hot) - L2
Figure 20b
Typical Wiring - Dual IN / Dual OUT (120 VAC / 240 VAC)
2004 - Magnum Energy, Inc. 23
2. INSTALLATION
Stack Port
Magnum Net Port
Remote Port
Figure 21
MS Series Inverter / Charger - Option Connection Ports
4. Options
AGS Module
The Auto Gen Start (AGS) is designed to automatically start your coach generator
based on low battery condition or the inside temperature of the coach. These fea-
tures allow you to enjoy a day away golfing, touring or just sight seeing, all the while
knowing your coach will stay cool and comfortable and your batteries will stay
charged. There's nothing better than returning to a nice cool comfortable coach with
charged batteries while dry camping in hot weather.
Adjustable settings include battery start voltage 10-12VDC, start temperature
65-85 0F, run time 1-5 hrs, and Quiet Time with an easy to set clock. AGS settings
do not interfere with the manual start / stop operation of the generator. Just use any
existing start / stop switch in your coach.
Two models are available. The Stand-alone version for installation and opera-
tion without an inverter; or the Network version, allowing operation of the AGS via the
ME Series Remote Control.
Fuses
The ME-300F and ME-400F protect the battery bank, inverter, and cables from
damage caused by short circuits and overloads. The option includes a Slow-Blow,
high current fuse with mounting block and cover.
Smart Shunt
future option - available soon
CAUTION: Verify correct battery voltage and polarity before connecting the
cables to the inverter.
Remove the electrical tape from the cable lugs and verify 12 VDC at the cable
connectors using a multimeter. Verify correct polarity: Black is negative (-); Red is
positive (+).
Connect the negative (BLACK) battery cable to the inverters negative terminal.
The cable lug must be flush to the terminals surface. Place a lock washer and nut
over the lug and torque the connection to 10 to 15 foot pounds.
NOTE: There may be a spark (and audible snap) when the cable lug first contacts the
inverters positive terminal. This is a normal condition.
Connect the positive (RED) battery cable to the inverters positive terminal. The
cable lug must be flush to the terminals surface. Place a lock washer and nut over
the lug and torque the connection to 10 to 15 foot pounds.
Place the red and black terminal covers on the inverters DC connector. Secure
the covers with enclosed hardware.
If the batteries are in an enclosure, perform a final check of the hold down brack-
ets and all connections. Close and secure the battery enclosure.
Switch the inverter power switch to ON. The inverters LED will flash indicating
DC power and the start-up sequence.
NOTE: When using the remote control, the inverters ON/OFF switch is disabled in
Charge mode.
Verify the breakers on the distribution panel are switched ON.
Use a true RMS multimeter to verify 120 VAC at the coachs AC outlets.
Connect the inverter to shore power and switch the main circuit breaker ON.
Verify the inverters LED switches from INVERTER to AC IN (SHORE POWER).
Use a true RMS multimeter to verify 120 VAC at each of the coachs AC outlets.
Switch the Shore Power OFF. Verify the inverters LED switches to inverter mode.
26 2004 - Magnum Energy, Inc.
2. INSTALLATION
Refer to the MS Series Remote Control operators manual to configure the following
parameters:
Shore (5, 10, 15, 20, 30, 50)
AGS OFF
Enable
Meter DC
Setup Search
LBCO
Battery Bank
Battery Type
Charge Rate
Contrast
Factory Reset
Tech Temps
Fault Record
The MS Series inverter/charger also allows you to select an equalize charge for
the batteries. Press and hold the Charger ON/OFF switch for 4 seconds. The Equal-
ize (EQ) function will be initiated (and the correct code will be sent to the remote.)
The EQ function automatically terminates after 4 hours of operation. You can also
manually stop the equalize mode by pressing and holding the Charger ON/OFF switch
while the inverter is in EQ mode.
Function Default
Search 5 watts
LBCO 10 VDC
Battery Bank 400 AHr
Battery Type Liquid Lead Acid
Charge Rate 80 %
Contrast 37 %
Charging / Inverting
LED
Figure 22
MS Series Inverter / Charger - LED Indicator
LED
Figure 23
MS Series Inverter / Charger - Fault Conditions
Fault LED
Figure 24
Optional Remote Control - Fault Conditions
Low Battery
Whenever the battery voltage reaches a low level, the inverter will initiate Low
Battery Cutoff (LBCO) which automatically shuts the inverter down, along with all
connected loads, to protect the batteries from over-discharge damage. The
inverters LED turns OFF to indicate the fault condition.
High Battery
As the inverter is charging, it constantly monitors the batteries. In the event the
battery voltage approaches too high of level, it automatically turns off the battery
charger to protect the batteries from damage. The inverters LED turns OFF to
indicate the fault condition.
NOTE: High battery voltage may be caused by excessive voltage from the alternator,
solar panels or other external charging sources.
Overload
During inverter and AC Shore Power operation, the inverter monitors the AC and
DC circuits. In the event of a short-circuit or overload condition, the inverter will shut
down. The inverters LED turns OFF to indicate the fault condition.
Overtemperature
During inverter operation, if the inverter becomes overheated, it will shut down to
protect itself from damage. The inverters LED turns OFF to indicate the fault condi-
tion.
1. Basic Troubleshooting
The MS Series inverter/ charger is a fairly simple device to troubleshoot. There
are only two active circuits (AC and DC) as well as a charging circuit. The following
chart is designed to help you quickly pinpoint the most common inverter failures.
No output power. High or low battery voltage. Check the battery voltage at
Inverter LED is OFF. the inverter's terminals.
No output power. Load is too small for search Reduce the search threshold
Green LED is flashing. mode circuit detection. or defeat search mode.
Appliances turn OFF/ON. Loose or corroded battery cables. Clean and tighten all cables.
Green LED is flashing.
Low batteries. Recharge or replace batteries.
AC output voltage seems Wrong type of voltmeter used Use a true RMS voltmeter.
too low when using a meter. (displays 80 VAC to 100 VAC).
Low charging rate Charge rate set too low. Adjust charge rate from remote.
when connected to
shore power. Low AC voltage (< 90 VAC). Check AC input wiring.
Low charging rate Generator output is too low Reduce the load.
when using a generator. to power both load and charger.
Increase the generators RPMs.
Charger doesnt charge. Loose or corroded battery cables. Clean and tighten battery cables.
The MS Series inverter/ charger is designed to provide you with years of trouble-
free service. Even though there are no user-serviceable parts, it is recommended
that every 6 months you perform the following maintenance steps to ensure optimum
performance and extend the life of your batteries.
Visually inspect the batteries for cracks, leaks, or swelling - replace if necessary
Use baking soda to clean and remove any electrolyte spills or buildups
Clean and tighten (10 to 12 foot pounds) all battery terminals and connecting
cables
Check and fill battery water levels (Liquid Lead Acid batteries only)
Check individual battery voltages (replace those that vary more than 0.3 VDC of
each other)
Check and tighten (16 foot pounds) the inverters internal AC terminal block
connections
2. Off-Season Storage
When placing the coach into seasonal storage, it is recommended that you per-
form the following to ensure the system is properly shutdown (or properly configured
for seasonal storage). This is especially important for maintaining the batteries.
Non-protected Storage
Perform the recommended maintenance steps above
Fully charge the batteries
Connect shore power and verify the breaker to the inverter is switched ON
Verify the inverter is switched ON
Switch OFF all unnecessary AC and DC loads
Protected Storage
Perform the recommended maintenance steps above
Fully charge the batteries
Switch OFF all AC and DC loads
Verify the inverter is switched OFF
Remove shore power and disable the generator (if installed)
MS Series Specifications
MS2012 MS2812 MS3624
Inverter Specifications
Input battery voltage 12.6 VDC 12.6 VDC 25.2 VDC
Nominal AC output voltage 120 VAC 120 VAC 120 VAC
Output frequency and accuracy 60 Hz ± 0.04% 60 Hz ± 0.04% 60 Hz ± 0.04%
Total Harmonic Distortion (THD) > 5% > 5% > 5%
1 msec surge current (amps AC) 60 70 100
100 msec surge current (amps AC) 37 40 60
5 sec surge power (real watts) 3700 3900 6500
30 sec surge power (real watts) 3450 3800 5500
5 min surge power (real watts) 3100 3200 5000
30 min surge power (real watts) 2400 3000 4000
Continuous power output at 25° C 2000 VA 2800 VA 3600 VA
Rated input battery current 190 ADC 267 ADC 336 ADC
Inverter efficiency 89% 88% 87%
Transfer time 16 msecs 16 msecs 16 msecs
Search Mode (with remote) 0.3 ADC 0.3 ADC 0.3 ADC
No Load (120 VAC output with remote) 2 ADC 2 ADC 2 ADC
Waveform Pure Sine Wave Pure Sine Wave Pure Sine Wave
Charger Specifications
Continuous output at 25° C 100 ADC 125 ADC 100 ADC
Charger efficiency 85% 85% 85%
Power factor 0.98 0.98 0.98
Input current at rated output (AC amps) 15 18 18
Environmental Specifications
Operating temperature -20° C to +60° C (-4° F to 140° F)
Nonoperating temperature -40° C to +70° C (-40° F to 158° F)
Operating humidity 0 to 95% RH non condensing
Physical Specifications
Dimensions (h x w x d) 13.75 x 12.65 x 8.0 (34.9 cm x 32.1 cm x 20.3 cm)
Mounting Shelf (top or bottom up) or bulkhead (vents up)
Weight 43 lb (19.5 kg) 53 lb (24.0 kg) 58 lb (26.3 kg)
Max operating altitude 15,000 (4570 m)
1. The limited warranty for the product extends for 36 months beginning from the
product's original date of purchase.
2. The limited warranty extends to the original purchaser of the product and is not
assignable or transferable to any subsequent purchaser.
3. During the limited warranty period, Magnum Energy will repair, or replace at
Magnum Energy's option, any defective parts, or any parts that will not properly
operate for their intended use with factory new or rebuilt replacement items if
such repair or replacement is needed because of product malfunction or failure
during normal usage. The limited warranty does not cover defects in appearance,
cosmetic, decorative or structural parts or any non-operative parts. Magnum
Energy's limit of liability under the limited warranty shall be the actual cash value
of the product at the time the original purchaser returns the product for repair,
determined by the price paid by the original purchaser. Magnum Energy shall not
be liable for any other losses or damages.
4. Upon request from Magnum Energy, the original purchaser must prove the
product's original date of purchase by a dated bill of sale, itemized receipt.
5. The original purchaser shall return the product prepaid to Magnum Energy in
Everett, WA. Magnum Energy will return the product prepaid to the original
purchaser after the completion of service under this limited warranty.