SFC Cover Note - MMLP Bangalore

The document discusses the development of a multi-modal logistics park in Bangalore, Karnataka, India. It will be developed on 184 acres through a public-private partnership. The logistics park will include facilities like a rail terminal, warehouses, vehicle parking, utilities and landscaping. Connectivity infrastructure like a 6.25 km rail line and 5.5 km road will also be developed to connect the site. The estimated cost of the logistics park development is 935.90 crores and completion is targeted for March 2023.

Uploaded by

a
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
201 views7 pages

SFC Cover Note - MMLP Bangalore

The document discusses the development of a multi-modal logistics park in Bangalore, Karnataka, India. It will be developed on 184 acres through a public-private partnership. The logistics park will include facilities like a rail terminal, warehouses, vehicle parking, utilities and landscaping. Connectivity infrastructure like a 6.25 km rail line and 5.5 km road will also be developed to connect the site. The estimated cost of the logistics park development is 935.90 crores and completion is targeted for March 2023.

Uploaded by

a
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Cover-Note

Development of Multi Modal Logistics Park at Bangalore and its External Trunk
Infrastructure Connectivity.

Part-I
Development of Multi Modal Logistics Park at Bangalore

Main Part Sub-Part Details/Particulars


Development, Operation and Maintenance of the Multi Modal
Logistics Park (MMLP) Bengaluru at Muddalinganahalli, in
Name of the Project
Bangalore Rural District in the State of Karnataka through PPP
on Design, Build, Finance, Operate and Transfer (DBFOT) basis.
Mode of Implementation Design Build Finance Operate Transfer (DBFOT)
Area of MMLP 184.27 acres for development of MMLP
Specifications of the The specifications of the project have been elaborated in
Project Schedule D of the Draft Concession Agreement.
Estimated Traffic (MMT) 29.46 MMT in horizon year of 2068.
National Highways Logistics Management Limited (NHLML), Rail
SPV Partners Vikas Nigam Limited (RVNL), and Karnataka Industrial Area
Development Board (KIADB).
Land of 400 Acres is in advance stages of acquisition by
Status of Acquisition Land
Karnataka Industrial Area Development Board (KIADB).
Under process (included in LA
Conversion of Land Use
Status of other pre- activity)
conditions and approvals Environment Clearance Under process
Forest Clearance Not required
(a) Rail Terminal
(b) Container yard and custom bonder area
(c) Warehousing zone and allied facilities
(d) Internal roads & Circulation area
(e) Truck & vehicle parking, Supporting facilities
Project Components
(f) Administrative facilities & gate complex
(g) Utilities and Landscaping & Horticulture Area
(h) Commercial Zone
(i) Other facilities or services required for smooth functioning
and operation of MMLP.
Cost to be borne by Concessionaire for MMLP Development
Estimated Project Cost Basic Civil Cost INR 782.71 Cr
GST INR 93.93 Cr
Centages INR 59.26 Cr
Estimated Overall
INR 935.90 Cr
Total Project Cost
Cost to be borne by SPV
Main Part Sub-Part Details/Particulars
Cost to be borne by INR 583.34 Cr
Authority (for land,
utilities, etc.,)
Date by which Tenders
05.02.2022 (Tenders Invited)
to be invited
Proposed date of LoA 15.09.2022
Proposed Date of
Project Completion declaration of 01.04.2023
Schedule ‘Appointed date’
Projection Completion 24 months for phase 1 leading to
Time (No. of Months) COD
Scheduled Completion
31.103.2025
date
Part-II
External Trunk Infrastructure Connectivity to the Multi Modal Logistics Park site in
Bangalore

A) Rail Connectivity

Main Part Sub-Part Details/Particulars


Rail Connectivity Infrastructure to the proposed Multi Modal
Name of the Project
Logistics Park site in Bangalore.
Mode of Implementation EPC mode
6.25 Km track length including two handling lines in the MMLP and
Length of the Project
reversal line
Traffic (Rakes) Tentative 9,000 rakes in horizon year of 2068
RoW Details RoW (in Mtrs) 20-45 m
Land required (in Acres) 30.80
Land under possession (in Acres) 0.00
Status of Acquisition of
Land to be acquired (in Acres) 30.80
Private Land
Time by which complete RoW
Dec 2022
would be available
Status of other pre- Status of tree-felling permission,
Required
conditions if required
Area of Forest Land Diversion and NA
Status
Wild- life Clearance, if required NA
Nil
Major Bridges
12 Nos. (RCC Box-2 (Barrel) x
Minor Bridges 6m (clear width) x 4m (clear
height))
Culverts Nil
Total 3 No’s
RUBs (RCC Box-2 (Barrel)x 4m (clear
Additional Project Features width)x4m (clear height))
Loading Standards 25 Ton Axle Load
Track Structure 60 Kg Rail on PSC Sleeper
with LWR
Signaling & Telecommunication Electronic Interlocking
Overhead Electrification (OHE) Single phase AC 25 KV, 50
Hz conventional OHE
Any Other, specify -
Rs. 41.58 Cr. @ Rs. 1.35 Cr
Estimated Project Cost Cost of Land
per acre
Total EPC Cost Rs. 94.58 Cr. @ Rs. 15.13 Cr
per Km
Main Part Sub-Part Details/Particulars
Rs. 136.16 Cr @ Rs. 21.78 Cr
Total Estimated Project Cost
per Km
Date by which Tenders to be To be done after final DPR
invited approval from Railways
Proposed date of LoA -
Project Completion Proposed Date of declaration of
-
Schedule ‘Appointed date’
Projection Completion Time (No.
18 Months
of Months)
Scheduled Completion date -
B) External Road Connectivity

Main Part Sub-Part Details/Particulars


External Road Connectivity Infrastructure to the proposed Multi
Name of the Project
Modal Logistics Park site in Bangalore.
Mode of Implementation EPC mode
Length of the Project 5.5 Km
Length of Road Portion
(including approaches to 5.4 Km
structures)
Length of structures 0.05 km
Toll plaza NA
Specifications of the Project 4-Lane highway
Pavement Flexible Pavement
Traffic figures in 2021 was 14,050 PCU requiring four lane
Traffic (PCU)
configurations.
Existing RoW (in Mtrs) 20-46.2 m
Land area under the Existing RoW 13.70 Ha
Existing carriageway Brown Field
Encroachments on the already
-
RoW Details - acquired Row, if any
ROW acquired during earlier Proposed RoW 21.8 – 45.52 m
up-gradation project (e.g. Additional Land Required for the
2.67
for 4-laning project, ROW proposed RoW (Ha)
acquired for earlier Government Land (Ha) 0.537
executed 2- Laning work Forest land (Ha) -
should be mentioned) Private Land(Ha) 2.136
Estimation Land Acquisition
19.80
Cost (INR cr.)
Rate of Administrative Charges for
-
LA, if applicable
Section 3A (Ha) -
Section 3D (Ha) -
Section 3G (Ha) -
Status of Acquisition of Possession taken -
Private Land Continuous length of
-
encumbrance free available RoW
Time by which complete RoW
Dec 2022
would be available
Main Part Sub-Part Details/Particulars
Status of other pre- Status of tree-felling permission,
Required
conditions if required
Area of Forest Land Diversion and
Status NA
Wild- life Clearance, if required NA
Electrical utility Shifting-
Rs. 0.51 Cr.
estimated Cost
Water Supply Line Shifting-
-
estimated costs
Env. cost Rs. 1.08 Cr
Any other Utilities to be shifted -
Status of GAD approvals in case of
NA
ROB/RUB
Major Bridges Nil
Minor Bridges Nil
12 Nos. Box Culvert ,
1.5mx1.5m (1 nos –Widen, 5
Culverts nos –new) , 2.0m X 2.0m –(1
no new), 3.0m X 3.0m (4 nos
new), 2.5m X 2.5m (1 no new)
Interchange
ROB Nil
VUP/LVUP/SVUP 1 no ( 1x30.0m + 1x
20.0m)/Nil/Nil
VOP Nil
Additional Project Features
Details KM
Length of Slip/Connecting Road
Ramps 0.650
(km) Service Road 2.370
Length of VOP road -
Length of Lined Drain (PCC) 5.4km both sides
Bypass (No. & Length) -
Realignment (Length) -
Way side Amenities-Type A -
Way side Amenities-Type B -
Truck Lay-byes -
RoW Boundary Wall -
Any Other, specify -
Toll Plaza/ Toll Booths Not Applicable
Estimated Project Cost Cost of Addl. Land Rs. 19.08 Cr.
Cost of other Pre-construction
activities (Env. Mitigation and Rs. 1.59 Cr.
Utilities Shifting)
Total Civil construction Cost Rs. 74.31 Cr
Main Part Sub-Part Details/Particulars
Centages and GST Rs. 19.32 Cr
Total Estimated Project Cost Rs. 114.30 Cr
Date by which Tenders to be
30.06.2022
invited
Project Completion
Proposed date of LoA -
Schedule
Projection Completion Time (No.
18 Months
of Months)

Length of project road - 5.5 Km


Civil cost (including Utility Shifting) per km - Rs 74.81 Cr @ Rs 13.60 Cr. per km
Length of aerial distance - 5.3 Km
Civil cost (including Utility Shifting) per aerial km Rs 62.79 Cr @ Rs 11.84 Cr. per km
Length of structures - 0.05 Km